Yesterday (23rd), the People's Government of the Eastern District and Sichuan Fanhu New Energy Technology Co., Ltd. signed an agreement on investment promotion of new energy electric vehicle supporting industrial projects. According to the agreement, the company will build 10 new energy charging stations in the eastern district to provide charging services for new energy vehicles.

Panzhihua will build 10 new energy charging stations, distributed in these places

Image source: Photo.com (authorized)

It is understood that according to the agreement, from February 2022 to February 2032 (the first 3 years are the project construction period), Sichuan Fanhu New Energy Technology Co., Ltd. invested about 152 million yuan in three phases to build 10 new energy charging stations and 1 new energy charging energy-saving technology research and development center in the eastern district.

Panzhihua will build 10 new energy charging stations, distributed in these places

The details are as follows▼

Phase 1 Project Construction: (February 2022 to February 2023)

4 new energy charging stations (East District Government Station, Old Government Center Station, Central Tiandi Station, Olympic Station), 43 charging piles, 86 charging guns, and put into 100 electric network car operations.

Phase II Project Construction: (March 2023 to March 2024)

3 new energy charging stations (vanadium and titanium high-tech zone station, central square station, guaziping street station) were built, supporting 30 charging piles, 60 charging guns, and 100 electric network car operations were put into operation.

Complete the preliminary preparatory work such as land purchase and program design of the new energy charging and energy-saving technology research and development center (including the flagship station), and have the conditions for starting construction.

Phase III Project Construction: (March 2024 to March 2025)

3 new energy charging stations (Wal-Mart Station, Dongfeng Station, And Brides and Children's Stations) were built, supporting 30 charging piles and 60 charging guns, and put into operation.

Completed a new energy charging energy-saving technology research and development center (including flagship station) and put into operation.

Reporter: Xiao Yi of Panzhihua City Radio and Television Station

Correspondent: Luan Xi

Edit: Dai Lin

Audit: Ding Jie

Panzhihua released

Panzhihua party affairs and government affairs information disclosure WeChat

Sponsored by Panzhihua Municipal People's Government Office

Panzhihua City Radio and Television Station undertakes

Read on