29 relocation lines were completed and put into operation to help the Sichuan Neijiang City Transit Expressway open to traffic on schedule

author:Cover News

Video loading...

Li Yaxiong Luo Guoqiang Cover news reporter Huang Xiaoqing

On December 7, the 110 kV songhe line of the State Grid Neijiang Power Supply Company was completed and the power was put into operation, marking the completion of the relocation and transformation of 29 transmission lines of 35 kV and above involved in the construction of the Neijiang City Transit Expressway, laying a solid foundation for the opening of the expressway on schedule, and also contributing to the power grid force for the construction of the neijiang into the central city of the main axis of chongqing development.

The construction of the Neijiang Urban Transit Expressway involves 13 220 kV lines, 10 110 kV lines and 6 35 kV lines under the jurisdiction of the Neijiang Power Supply Company, with a total length of 30.8 km, requiring the construction of 129 new tower bases, and the relocation and reconstruction lines span the Neisui Expressway, Neiyi Expressway and other high-speed construction as many as 8 times, and cross the high-speed under construction 20 times.

29 relocation lines were completed and put into operation to help the Sichuan Neijiang City Transit Expressway open to traffic on schedule

In the face of difficulties, Neijiang Power Supply Company attaches great importance to it, takes the problem as the guide, overcomes difficulties, strives to promote the relocation and reform work, actively strengthens communication and contact with local governments at all levels, and jointly coordinates to solve existing problems, and at the same time, the Construction Department of Neijiang Power Supply Company has taken the lead in organizing and optimizing power outages and construction plans for many times. Since the start of construction in October 2018, two consecutive special actions of "100 Days of Power Relocation and Reform" have been carried out, and relevant leaders have repeatedly conducted in-depth on-site supervision, put forward clear requirements for construction safety and quality, and actively organized all units to work together to carry out power relocation and reform work.

"We have carried forward the spirit of the electric power iron army and overcome the difficulties such as the impact of the epidemic shutdown, the cross-crossing of lines, the coordination of power outage time, and the tight construction period." Liu Jun, project manager of Xingyuan Electric Power Group Co., Ltd., a subsidiary of Neijiang Power Supply Company, introduced at the acceptance site. In order not to affect the construction plan, the project departments have adhered to the construction site for a long time, driven full horsepower, made all-out efforts to "sprint", and while doing a good job in epidemic prevention and control, the site deployed multiple operating groups to promote various work at a fast pace, setting off a big dry boom, and more than 100 electric power employees were on the front line of project construction during peak hours, and finally successfully completed the relocation and reconstruction construction task.

29 relocation lines were completed and put into operation to help the Sichuan Neijiang City Transit Expressway open to traffic on schedule

"Economic development, electricity first". At the time of the opening of the Neijiang City Transit Expressway, neijiang Power Supply Company completed the relocation and construction of power lines in an all-round way after arduous construction, and practiced its social responsibility of serving local economic and social development with practical actions.