It was built by the Southwest Company of China Construction Eighth Bureau
Tuanjiehu Digital Economy Industrial Park Project
Intelligent manufacturing base AB area
Successfully completed the completion acceptance
A brand-new modern high-end intelligent factory
Standing on the shore of Tuanjie Lake in Jiangjin District with a high-spirited attitude
It will lead the upgrading of the digital economy in the entire Jiangjin Science City region
Tuanjiehu Digital Economy Industrial Park Intelligent Manufacturing Base AB Area
Tuanjiehu Digital Economy Industrial Park Project of China Construction Eighth Bureau
As one of the first EOD pilot projects in the country
A total of 17 children
The main construction content includes production and service buildings
There are three categories of public service facilities and supporting infrastructure
The AB area of the intelligent manufacturing base for this completion and acceptance
Take intelligent manufacturing as the core tentacles
Build a new urban industrial park
After the completion of the project as a whole
It will lead the upgrading of the digital economy in the entire region
It has become an important agglomeration area for the development of Jiangjin's digital economy industry
Promote high-quality economic development
The courtyard layout is natural and harmonious
Intelligent manufacturing base AB area
As the first batch of completion acceptance sub-items of the project
The total construction area is about 160,000 square meters
All of them are courtyard-style layouts with double ground floor designs
Improve the efficiency of road transportation in the factory
So as to realize the separation of people and vehicles
It also increases the proportion of the overall ground floor area of the project
The exterior wall of the factory is made of jasmine white matte aluminum plate in a large area
Ribbon transverse windows are interspersed
Equipped with arc corners
The overall architectural form is staggered and sparse
Warm white glow reflected in direct sunlight
It complements the green shore of the surrounding wetland park
And the terrace of the factory building adopts the design of planting roof
Effectively solve the contradiction between building and landscaping land
It fully embodies the design concept of harmonious coexistence with natural ecology
Technology empowers efficient construction
A large number of prefabricated structures are used in the physical construction of the project
The structure of the B6# building in Area B of the intelligent manufacturing base is ± or above
All of them are designed with prefabricated buildings
Prefabricated hollow floor slabs and cavity columns
Four main assembly components such as prestressed laminated plates and precast beams
Replace traditional concrete cast-in-place structures
Building B6# is located in the critical path of the project duration
There are many manufacturers of assembly components
The production schedule is not uniform
Deepening the design is slow to produce drawings and other problems
The project team chose a BIM platform for digital project management
The first time the drawing will be complicated
Numerous assembly components are converted into digital models
Clearly show the number of specific assembly components and pipe network arrangement on each floor
Reasonably divide the construction flow section and send special personnel to the factory
Ensure that the components arrive on schedule according to the established construction plan
The prefabricated components of the project are ensured
in processing, transportation, stacking, installation, etc
A series of processes are carried out in an orderly manner
Realize the nodes of the project as scheduled
Smart construction helps high-quality projects
Intelligent robotics
It is widely used in the construction of this project
In the main structure construction, decoration, quality inspection, etc
Important process links show their powers
Automate assistance programs by presetting them in advance
Concrete leveling robots, slat handling and installation robots, etc
It was realized in the construction of the main structure
Fast and accurate construction operations
The construction period has been greatly shortened
In the decoration link
Floor grinding robots, coating robots, etc
It can accurately control the operation accuracy and material ratio
Improved construction quality
In addition, high-resolution radar, pipeline inspection robots
Wall-climbing rebar scanning robot
wall-climbing elastic wave detection robots, etc
Through precise programming and efficient execution
It shines in application scenarios such as "high, dangerous, and deep".
Escort the quality improvement of the tamping base
More efficient progress of the project
and precise implementation provides strong support
Tuanjiehu Digital Economy Industrial Park Project
R&D and Innovation Center Area AB
The large-scale capping of the main structure was completed
Xiangtang Primary School has fully entered the stage of interior decoration
The overall steel structure of the waterfront convention and exhibition center is 95% complete
The construction of all sub-projects of the project is expected to be completed in 2025
After completion, it will focus on cultivating high-tech and strategic emerging industries
Material source: 丨China Construction Eighth Bureau Southwest Company, Chongqing Branch