98% complete! The Esplanade Sinking Tunnel is expected to ...... this year

author:Happiness Fukuda
98% complete! The Esplanade Sinking Tunnel is expected to ...... this year

Esplanade (ABP Section)

Comprehensive traffic renovation project

Where are we now?

When will it be open to traffic?

Hold your horses

Xiaofu brings you the latest progress!

98% complete! The Esplanade Sinking Tunnel is expected to ...... this year

Route map of the Corniche project

Shenzhen Binhai Avenue (ABP Section) Traffic Comprehensive Renovation Project, starting from the Shahe East Road Interchange in the west, to the Guangzhou-Shenzhen Expressway in the east, across the Nanshan and Futian districts, with a total length of 5,950 meters. Among them, the ABP section is sunk in its entirety, with a length of 1,560 meters in the sinking tunnel section and 4,390 meters in the ground reconstruction section.

After the renovation, the main line will be 8 lanes in both directions at a speed of 80 km/h, and the auxiliary road will be 6 lanes in both directions at a speed of 40 km/h.

The project adopts the integrated design of "sunken tunnel + underground harbor bus stop + Guangzhou-Dongguan-Shenzhen intercity station + super headquarters underground space", with the layout planning of five lines and six stations as the leading point, and the deep integration of urban design, traffic design, landscape environment and other disciplines, and the in-depth coordination of the relationship between multiple systems such as rail, bus, tunnel, and underground space development.

98% complete! The Esplanade Sinking Tunnel is expected to ...... this year

The main structure of the current sinking tunnel section

It is fully completed

The Binhai Avenue (ABP Section) Traffic Comprehensive Reconstruction Project is divided into a sunken tunnel section and a level road reconstruction section, of which the asphalt paving of the main line of the flat road reconstruction section and the south auxiliary road has been completed, and the remaining 300 meters of the north auxiliary road are being asphalt paving.

98% complete! The Esplanade Sinking Tunnel is expected to ...... this year

At present, the main structure of the sinking tunnel section has been completed, and the mechanical and electrical installation of the main line has been completed, and the opening conditions are met; The auxiliary road is carrying out mechanical and electrical installation and decoration work; The overall progress of the project is 98% complete.

The next step is to complete the mechanical and electrical installation and decoration of the auxiliary road of the sinking tunnel section, and complete the upper cavity, earthwork backfill, pipeline restoration and green covering project of the sinking tunnel section, and it is expected that the whole line will be basically ready for traffic in the second half of 2024.

Alleviate traffic bottlenecks on the Corniche

Promote the integration of urban architecture and coastal landscape

The opening of the main line of the sinking tunnel section and the retention of the two relief roads on the south side as auxiliary roads for temporary use can effectively alleviate the traffic pressure in the eastbound direction of Binhai Avenue, solve the problem of congestion at traffic nodes such as Shahe East Interchange to Binhai Avenue and Shenzhen Bay Park No. 3 parking lot, and increase the traffic rate by about 40%.

At the same time, the opening of the main road also released the conflict nodes between the relief road and the auxiliary road, which is of great significance to the construction of the subsequent auxiliary road of the project and lays a solid foundation for the official opening of the whole project.

98% complete! The Esplanade Sinking Tunnel is expected to ...... this year

After the completion of the project, it will effectively connect the Guimiao Road Tunnel and Binhe Avenue to alleviate the traffic bottleneck in the headquarters base section of Binhai Avenue; The sinking tunnel is reserved for 2 entry and 2 exit ramps to connect the underground road network of Shenzhen Super Total, which can meet the large amount of traffic arrival and departure needs generated by the total development of Shenzhen Super Tunnel.

The Shenzhen Bay Super Headquarters Base section will form a three-dimensional traffic of "ground + underground", which can effectively alleviate the traffic bottleneck of Binhai Avenue, and at the same time release a green space with an area of about 100,000 square meters, equivalent to the size of 14 standard football fields, eliminate the separation of Binhai Avenue from the Shenzhen Bay landscape belt, promote the integration of urban architecture and coastal landscape, provide higher quality public space, and create a new engine for the vitality of the Bay Area.

-END-

Edit | Yao Taosheng

Proofreading | Li Xia, Wei Ding, and Wang established diplomatic relations

Proofreading | Dong Fangjun

Executive Producer | Zheng Yongtao

Source of information | Shenzhen Satellite TV Deepvision News

Read on