The conditions are met! When will the Esplanade Sinking Tunnel be opened to traffic......

author:Innovation Nanshan
The conditions are met! When will the Esplanade Sinking Tunnel be opened to traffic......

There is a way

It always makes the hearts of Nanshan people miss it

It is the Corniche in the "renovation".

May 13th

Reporter visits

Esplanade (ABP Section)

Comprehensive traffic renovation project

Where has the project progressed?

When will it be open to traffic?

Let's learn about it with Xiaochuang

The latest progress of the project~

The conditions are met! When will the Esplanade Sinking Tunnel be opened to traffic......
The conditions are met! When will the Esplanade Sinking Tunnel be opened to traffic......

△ Binhai Avenue project route map

Shenzhen Binhai Avenue (ABP Section) Traffic Comprehensive Renovation Project, starting from the Shahe East Road Interchange in the west, to the Guangzhou-Shenzhen Expressway in the east, across the Nanshan and Futian districts, with a total length of 5,950 meters. Among them, the ABP section is sunk in its entirety, with a length of 1,560 meters in the sinking tunnel section and 4,390 meters in the ground reconstruction section.

After the renovation, the main line will be 8 lanes in both directions at a speed of 80 km/h, and the auxiliary road will be 6 lanes in both directions at a speed of 40 km/h.

The project adopts the integrated design of "sunken tunnel + underground harbor bus stop + Guangzhou-Dongguan-Shenzhen intercity station + super headquarters underground space", with the layout planning of five lines and six stations as the leading point, and the deep integration of urban design, traffic design, landscape environment and other disciplines, and the in-depth coordination of the relationship between multiple systems such as rail, bus, tunnel, and underground space development.

The conditions are met! When will the Esplanade Sinking Tunnel be opened to traffic......

Source: Shenzhen Transportation

In 2023, the project won the 9th International Tunneling and Underground Space Association (ITA) Project of the Year Award.

During construction

The construction unit actively promotes digital transformation

Accelerate the construction of intelligence

1. Independent research and development of safety risk management and control platform to monitor the main foundation pit of the tunnel and surrounding buildings in real time to ensure the safety and stability of the structure.

2. Use the smart construction platform to monitor the progress of the project in real time through the 3D twin model scene to ensure the project duration.

3. In addition, new technologies such as the introduction of tensile beam structure instead of reinforced concrete temporary support, extrusion and expansion of disc piles instead of traditional floating piles, hyperboloid lap retaining wall, etc., and the establishment of a mud treatment center, sand and gravel separation center and solid waste regeneration center composed of a resource regeneration center to achieve zero discharge of sewage and mud, save resources, protect the environment and improve efficiency to the greatest extent.

The conditions are met! When will the Esplanade Sinking Tunnel be opened to traffic......
The conditions are met! When will the Esplanade Sinking Tunnel be opened to traffic......

The main structure of the current sinking tunnel section

It is fully completed

The Binhai Avenue (ABP Section) Traffic Comprehensive Reconstruction Project is divided into a sunken tunnel section and a level road reconstruction section, of which the asphalt paving of the main line of the flat road reconstruction section and the south auxiliary road has been completed, and the remaining 300 meters of the north auxiliary road are being asphalt paving.

The conditions are met! When will the Esplanade Sinking Tunnel be opened to traffic......

At present, the main structure of the sinking tunnel section has been completed, and the mechanical and electrical installation of the main line has been completed, and the opening conditions are met; The auxiliary road is carrying out mechanical and electrical installation and decoration work; The overall progress of the project is 98% complete.

The next step is to complete the mechanical and electrical installation and decoration of the auxiliary road of the sinking tunnel section, and complete the upper cavity, earthwork backfill, pipeline restoration and green covering project of the sinking tunnel section, and it is expected that the whole line will be basically ready for traffic in the second half of 2024.

Alleviate traffic bottlenecks on the Corniche

Promote the integration of urban architecture and coastal landscape

The opening of the main line of the sinking tunnel section and the retention of the two relief roads on the south side as auxiliary roads for temporary use can effectively alleviate the traffic pressure in the eastbound direction of Binhai Avenue, solve the problem of congestion at traffic nodes such as Shahe East Interchange to Binhai Avenue and Shenzhen Bay Park No. 3 parking lot, and increase the traffic rate by about 40%.

At the same time, the opening of the main road also released the conflict nodes between the relief road and the auxiliary road, which is of great significance to the construction of the subsequent auxiliary road of the project and lays a solid foundation for the official opening of the whole project.

The conditions are met! When will the Esplanade Sinking Tunnel be opened to traffic......

After the completion of the project, it will effectively connect the Guimiao Road Tunnel and Binhe Avenue to alleviate the traffic bottleneck in the headquarters base section of Binhai Avenue; The sinking tunnel is reserved for 2 entry and 2 exit ramps to connect the underground road network of Shenzhen Super Total, which can meet the large amount of traffic arrival and departure needs generated by the total development of Shenzhen Super Tunnel.

The Shenzhen Bay Super Headquarters Base section will form a three-dimensional traffic of "ground + underground", which can effectively alleviate the traffic bottleneck of Binhai Avenue, and at the same time release a green space with an area of about 100,000 square meters, equivalent to the size of 14 standard football fields, eliminate the separation of Binhai Avenue from the Shenzhen Bay landscape belt, promote the integration of urban architecture and coastal landscape, provide higher quality public space, and create a new engine for the vitality of the Bay Area.

After the sinking and transformation of Binhai Avenue, whether it is driving or taking a bus, going to work in the city or intercity travel, all one road will be completed, this avenue with both appearance + strength is online, do you look forward to it? Welcome to the comment area and chat with us~

The conditions are met! When will the Esplanade Sinking Tunnel be opened to traffic......

Source | Shenzhen Satellite TV Shenshi News Shenzhen Transportation

Reporter | Dewey Zhang Shaoqiang

Edit | Guo Jiafeng Editor-in-charge| Dong Fei

Audit | Liang Yashu and Lu Dongbo

Please indicate the above information for reprinting

Some of the pictures in this WeChat article may come from the Internet

If your rights and interests are infringed, please contact us in time to delete it

Stormy coming? A new round of strong convective weather in Shenzhen is coming

Tickets are sent – come and watch the movie!

May Fourth Youth Day|Youth "politics" should be burned

Read on