A few days ago, Hunan Kaisa released the November project progress of Tianji Rongde Kaisa City Square. At present, Tianji Rongde Kaisa City Square is under normal construction.
1# Building 12 layer beam plate steel bar lashing is completed, and the outer wall is completed with a putty to complete the 4-9 floors;
2# Building 9 layer beam plate steel bar lashing completed, the outer wall of a putty to complete the 4-6 layers;
3# Building 17-storey beam plate steel bar lashing is completed, and the outer wall is completed with putty to complete the 5-14 floors;
4# Building 17 floors of wall column steel binding completed, the outer wall of a putty to complete the 5-13 floors, masonry completed 3, 4 floors;
5# Building 24 layer beam plate steel binding completed, the outer wall of a putty to complete 8-19 floors, masonry completed 1-11 floors;
6# Building 21 layer beam plate steel binding completed, the outer wall of a putty to complete the 5-18 layers, masonry completed 2-8 floors;
7# Building 17 floors of wall column reinforcement lashing is completed, the outer wall is completed with putty to complete 6-15 floors, and the masonry is completed on 2-7 floors;
8# Building 7-layer beam plate steel bar lashing is completed, and the outer wall is completed with putty to complete the 3-4 layers;
10# Building 8-layer beam plate steel bar lashing is completed, and the outer wall is completed with putty to complete 3-4 floors;
11# Building 9 layer beam plate steel bar lashing completed, the outer wall of a putty to complete the 3-4 layers;
12# Building 5-layer beam plate steel bar lashing is completed, 5-layer wall column sealing film is completed, and 6-layer beam plate formwork is 50% complete;
13# Building 9-layer beam plate steel bar lashing completed, the outer wall of a putty to complete the 3-4 layers;