The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed

Comprehensive shoreline improvement project of the Yangtze River section in Huangshi District

The comprehensive shoreline improvement project of the Yangtze River section of Huangshi District (the first phase of Yanjiang Avenue) has a total length of 8.88 kilometers and a planned investment of 1.6 billion yuan.

As of October 20, Yanjiang Avenue has completed an investment of 500 million yuan, accounting for 31.3% of the completed investment. Construction is scheduled to be fully completed and put into use by the end of 2022.

The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed

Under the overall coordination of the Municipal Party Committee and the Municipal Government

With the strong support and cooperation of various departments and units in the city

It is proceeding in an orderly manner according to the construction plan

The Huangshi Housing and Urban-Rural Development Bureau now informs the progress of the construction as follows

One lot

Completed the investment of 180 million yuan. The north extension of Huangshi Avenue has been opened to traffic; the Construction of the Bridge Safety Guardrail is underway on the Shanghai Gate Viaduct; and the road surface project of Ehuang Road has been completed.

The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed
The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed
The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed
The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed
The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed
The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed

Two-bid segment

Completed the investment of 0.9 billion yuan. The AB ramp bridge of Yingbin Avenue completed 300 meters of drainage pipe network; completed the BL3 joint prestressed steel tensile grout and the construction of 2 span BL1 joint box girder full hall supports; completed 957 cement mixing piles, 250 meters of retaining walls, 12,000 cubic meters of backfill earth, and 226 meters of pouring flood walls.

The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed

△ Huangshi District Yangtze River section shoreline comprehensive improvement project second bid section plan

The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed
The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed

△ Yingbin Avenue ramp bridge construction site

Three lots

The procedures for updating the forest harvesting on the berm are being submitted for approval by the Provincial Embankment Bureau, and the river-related plan is being docked with the Planning and Design Institute of the Yangtze River Commission to handle the approval of the flood control impact assessment report after completing the river-related plan. At present, the construction unit is in the preliminary work, planning to start construction after the end of the flood season, and is scheduled to be completed by the end of December 2022.

Three bid sections create five major plates, namely:

Rural Eco Harbor, Colorful Life Harbor,

Cultural experience port, historical story port, folk customs port

Transform the "polluting industrial rust belt" into

"Humanistic, green life show"

The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed
The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed
The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed
The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed
The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed
The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed

More 3 lots (Huangshi Jiangtan Park)

You can find out more about it by clicking on the links below

Heavy! The 14-kilometer-long Huangshi "Bund" will be built in October The Huangshi Harbor Sports Park will also be restored

The latest progress of the "Avenue + Park", which runs through the north and south of Huangshi City with a total investment of 1.6 billion yuan, has been exposed

In the next step, the command office will continue to coordinate the relevant departments

Strengthen overall planning and coordination

Supervise and promote the construction of the project along the river

01

It is planned to start the construction of the retaining wall of the Ehuang section of the Xingang Gate Viaduct after the end of the flood season

02

After the end of this year's flood season and before the flood season next year, the construction of the A and B ramp bridges on Yingbin Avenue, the relocation of pipelines, the reinforcement of the foundation of the river embankment and the reconstruction of some pumping stations and gates will be completed, and the traffic will be opened to the public;

03

Complete the procedures for updating forest logging on the berm as soon as possible and the approval of the Yangtze River Commission's flood control impact assessment report, complete the pipeline relocation, river beach topography, structure and part of the greening project this year, and plan to complete it by December 2023 and open to the public.

I heard that Yanjiang Avenue has changed from six lanes to four lanes

Chengjianjun will have an article published in the near future