August 10
Rail Transit Line 5 jumps to Jiangjin section
The stone bridge is divided into three sections of the elevated section
With 2 large concrete pump trucks
Lift the boom high
Align the base plate with the rebar laid
Concrete is injected into the mold under the guidance of the worker
The construction site was a busy scene

▲Stone slab elevated pouring site
The pouring was made of slate elevated pier d46-49
Continuous beams were poured in the first class
The length is 100 meters
1385 cubic meters of poured concrete
Estimated time is 23 hours
After this pour is completed
A second phase of pouring will be carried out on the side span of 40 meters
The full bridge closure is expected to be completed by the end of August
Original design scheme of the slate elevated slab
Construction for cantilever process
In order to save the duration
The parties involved in the construction have undergone many discussions
Adjust the construction plan
Put the original cantilever process construction
Changed to scaffolding construction
The construction period can be shortened by about 2 months
At present, rail transit line 5 jumps to Jiangjin section
Main body of the main line in Jiangjin District (including stations)
The project is complete
Interior and exterior decoration and ancillary works are underway
There are 18 single buildings in the depot
15 main works have been completed
Interior and exterior decoration of the main building is underway
and track laying and outdoor pipe network laying
90% of civil works outside Jiangjin District
The substructure of the outer section is basically completed
The main works of the two stations have been completed
It has fully entered the construction stage of the box girder
Come on!
Looking forward to the early opening of traffic
(Jiangjinrong Media Center reporter: Su Shengyu, Guo Kaixing, Wang Ming)