This year's urban construction key project "43322", that is, 4 roads, 3 water systems, 3 parks, 2 sheds, 2 old blocks of façade transformation. Among them, the Linxu River water system in the 3 water systems and one of the 2 sheds reformed, the Linxu River Shed Reform, due to its huge volume, was uniformly commanded, coordinated and promoted by the Linzhou Water System Planning and Construction Command. While doing a good job in epidemic prevention, the Linzhou Water System Planning and Construction Headquarters has taken various measures to promote the resumption of work and production of key project construction projects.
A few days ago, the reporter saw at the construction project site of the Linxuhe Shed Resettlement Area that the tower cranes were lined up, the hook machine roared, and there was a tense and orderly construction scene.

According to Fan Hongbin, director of the office of the water system headquarters and director of the water conservancy bureau, the Linxu River water system project is the ecological conservation project of the Hongqi Canal that the city focuses on. In the area west of Wangxiang Road, east of Xiyi Road, south of Hongqiqu Avenue, and north of Linzhou Avenue, along the planning experimental road construction, the newly excavated river channel is 3.9km, the average width of the planned water surface is 150m, the average width of the planned municipal road is 40m, the landscape green belt of 20-30m is reserved on the riverside side of the road, the green width of the road is 20m, and 2 new bridges and 5 middle bridges are built, a total of 7 bridges. From north to south, 8 important landscape nodes are planned and constructed, namely ecological Forest Lake, Cultural Memorial Park, Taihang Water Town Section Peripheral River Landscape, Renmin Street Ecological Amusement Park, LinXu River River Landscape, Gateway Park, Guanlinggou River Landscape, and Experimental Road Road Landscape. The total investment of the project is about 2.33 billion yuan, and it is planned to complete the investment of about 1 billion yuan in 2020, complete the demolition work by the end of June, complete the excavation and anti-seepage, municipal roads and supporting and greening work in the northern section of the Linxu River (north of the planned Renmin Road) within the year, have the conditions for water storage, and complete the bridge construction involved in the project area.
After the completion of the Hongqi Canal Ecological Conservation Project, it will effectively improve the living standards of the people of our city and the ability to open up to the outside world, and improve the quality of the city and the quality of ecological civilization. At that time, a beautiful picture of "blue and green intertwining, fresh and bright, harmonious people and water, and water city integration" will be rolled out in the western part of the city's urban area.
Project construction, resettlement first. As a people's livelihood project in our city, the Linxuhe Shed Resettlement Area began construction in April 2019. The resettlement community covers an area of about 281 acres, involving 3,093 sets of resettlement houses, with a total construction area of 481,940 square meters, and a total investment of about 2.6 billion yuan.
According to Hou Guojun, the project manager at the scene, in order to promote the progress of the project in an intensive manner, the project is divided into three districts for construction, and the construction party has formulated a plan for classified construction and scientific scheduling, so as to achieve both epidemic prevention and control and project construction.
The Linxu River System Project is located in the jurisdiction of Kaiyuan Street and Huanghua Town, and more than 800 households need to be demolished in 2 towns (streets). To this end, Huanghua Town and Kaiyuan Street have set up high-standard demolition headquarters and started demolition.
Hu Zhiwei, secretary of the Kaiyuan Street Discipline Work Committee, said: The project involves the demolition of 327 houses in Kaiyuan Street, 17 enterprises and farms, more than 850 mu of land need to be acquired, 106 agreements have been signed, and 14 enterprises have been signed. At present, the farmers who signed the agreement are actively moving, and the demolition work will start in the near future. In the next step, while doing a good job in epidemic prevention and control, we will start the demolition and relocation of Xiaoyujiazhuang and Tianjiazhuang in Xiashenjie Village, and strive to rush back the work delayed due to the epidemic according to the requirements of the time node.
Shi Zhenguo, deputy mayor of Huanghua Town, said that the land acquisition and demolition of the Linxuhe Park project involved 2 administrative villages in Huanghua Town, requiring land acquisition of more than 1,200 mu, more than 500 houses and more than 30 enterprises, and more than 1,000 graves. The two resettlement areas cover an area of more than 100 acres, and the demolition and relocation has entered the stage of signing the agreement, and it is planned to complete the demolition of 24 households by the end of March. Source: Linzhou on the Clouds