laitimes

The wall collapsed and killed 2 fire and rescue personnel!

author:Shanghai emergency guard
The wall collapsed and killed 2 fire and rescue personnel!

At about 18:36 on August 5, 2023

Ganzhou Economic and Technological Development Zone, Jiangxi

A fire broke out in Jiangxi Zhongnan Environmental Protection Equipment Co., Ltd

The burned area is about 700 square meters

In the course of a firefighting battle

The retaining wall on the northeast side of the plant collapsed

As a result, 2 fire and rescue personnel died

Fifteen fire and rescue personnel were injured

The direct economic loss was more than 670 yuan

The wall collapsed and killed 2 fire and rescue personnel!

Recently, the Jiangxi Provincial Emergency Management Department released an investigation report on the accident, which showed:

The "8.5" fire accident of Jiangxi Zhongnan Environmental Protection Equipment Co., Ltd. in Ganzhou Economic and Technological Development Zone is a production safety liability accident caused by serious violations of laws and regulations by relevant enterprises, non-implementation of main responsibilities, and failure of local governments and their relevant departments and units to perform their duties.

The cause of the fire was that during the upgrading and renovation of the steel structure of the 2# workshop (G-D axis of the plant) leased by Zhongnan Environmental Protection Company, the gas cutting operators carried out unlicensed illegal thermal cutting operations in the area above the fire point, and the high-temperature metal slag that fell from the splash ignited the PPR tank and other combustibles placed in the 1# workshop (G-K axis of the plant) immediately below the working face, causing a fire.

At the initial stage of the fire, the on-site construction personnel of Changding Engineering Company and the on-site operators of Zhongnan Environmental Protection Company had insufficient emergency response and fire extinguishing capabilities, the on-site fire-fighting facilities did not meet the requirements, and the fire was hastily extinguished at the initial stage of the fire, and the organization was not effective, which caused the spread of the fire, exposing the lack of fire emergency plans of relevant enterprises, and the failure to effectively carry out fire training and emergency drills.

01

How the fire broke out

At about 15 o'clock in the afternoon of August 5, 2023, according to the construction arrangement of the "Plant Renovation Project", Xiong Mouhua, the construction team leader, led 10 construction personnel such as Zhang and Li Mouping, divided into 4 groups to work in different positions in the 2# workshop. Among them, Zhang and Li Mouping carried out gas cutting and installed overhead crane track operations at the G-axis position in the factory.

From 16:46 to 16:53, Zhang used an air cutting gun to cut screws and angle irons on the G-14 steel pillar, and adjusted the size of the bolt hole.

At about 18:36, Xiong Mouhua, who was checking the construction situation in the workshop, found that the PPR tank (tank height of about 4 meters) was on fire in the PPR tank (about 4 meters high) located under the north side of the second column (G axis) in the northeast to southwest direction and the 14th (G-14) steel column in the northwest to southeast direction of the plant.

The wall collapsed and killed 2 fire and rescue personnel!

The process of starting the fire (video screenshot)

The situation of the initial extinguishing of the fire

02

At about 18:36, Xiong Mouhua immediately shouted for help after discovering the fire. The on-site construction personnel tried to extinguish the fire, and first used the hobby lifting platform to carry people to extinguish the fire, but due to the deep tank tank, the fire extinguisher could not be sprayed to the root of the flame, and the fire extinguishing was ineffective and the fire gradually increased.

At about 18:39, the employees of Zhongnan Environmental Protection Company operated an overhead crane to try to transfer the PPR tank around the fire site, but failed due to the large fire.

At about 18:41, the employees of Zhongnan Environmental Protection Company connected the portable fire hose in the workshop and handed it over to the fire extinguishing personnel on the lifting platform of the curved arm truck to extinguish the fire, but due to the insufficient water output of the portable fire hose, the fire extinguishing was still ineffective.

At 18:42, employees of Zhongnan Environmental Protection Company used their mobile phones to call 119 to call the police.

At about 18:49, due to the ineffective fire extinguishing at the scene, the fire was out of control, and the on-site personnel were evacuated one after another.

03

Fire fighting and rescue situation

At 18:42, the command center of the Ganzhou Fire and Rescue Detachment received an alarm, and successively dispatched 4 brigades, 5 fire stations, 4 government full-time fire brigades, 23 fire trucks, and 95 fire rescue personnel to the scene for disposal, and the detachment's full-service command headquarters was dispatched.

At 18:49, the fire rescue brigade of Ganzhou Economic and Technological Development Zone led 5 vehicles and 20 people from Jintan Avenue Fire and Rescue Station to the scene, immediately organized the evacuation of personnel, and set up 2 water cannons at Gate 1 and Gate 3 of the plant to control the fire.

At 18:52, 4 vehicles and 20 people from 4 government full-time fire brigades under the brigade arrived at the scene one after another, and a water cannon was added to Gate 1 to control the fire.

At 7:02 p.m., the fire spread further. The detachment's Yingbin Avenue special service station reinforcements 5 vehicles and 22 people arrived at the scene, added 1 mobile water cannon and 1 water cannon at Gate 3 to control the fire, and used a high-spray truck to suppress the fire from a high position.

At 19:12, the outer wall on the northeast side of the plant collapsed outward in an instant (the length of the collapse was about 175 meters), and the on-site safety officer immediately issued an emergency evacuation order, but because there was no warning of the collapse, 17 commanders and fighters could not avoid danger and were injured or buried by the collapsed wall. The brigade quickly set up 3 search and rescue teams to carry out rescue, and 5 vehicles and 20 people from the Hongqi Avenue Fire and Rescue Station and the Special Service Station who arrived one after another immediately joined the search and rescue operation.

As of 19:28, 16 injured people were rescued and sent to the hospital for treatment (one of them died after resuscitation).

At 19:30, there was still one full-time government firefighter who was buried, and the detachment's full-service command arrived at the scene and re-established two search and rescue teams to carry out search and rescue under the cover of water cannons.

At 19:40, 2 vehicles and 6 people from the Shixingling Fire and Rescue Station in Rongjiang New District arrived at the scene and used a high-spray truck to control the fire at a high level in the east corner of the plant.

At 19:43, one full-time government firefighter who was buried was rescued and immediately sent to the hospital for treatment (died after rescue).

At 19:45, the on-site command decided to set up 2 mobile guns on the northeast side of the plant for long-range strikes, 1 fire extinguishing robot on the northwest side, and 2 high-spray vehicles on the southwest side to cool the roof of the plant.

At 19:50, 2 vehicles and 7 people from the Ganxin Avenue Fire and Rescue Station arrived at the scene and rotated as a reserve force.

At 23:50, the fire was completely extinguished.

Analysis of the cause of the accident

(1) Determination of the cause of the fire. According to the results of on-site investigation, on-site test, and evidence extracted from the fire scene, combined with witness testimony and video analysis, the factors of spontaneous combustion, residual fire, electrical fault, and fire caused by the production process were ruled out.

The cause of the fire was comprehensively determined to be: during the upgrading and renovation of the steel structure of the 2# workshop (G-D axis of the plant) leased by Zhongnan Environmental Protection Company, the gas cutting operators carried out unlicensed illegal thermal cutting operations in the area above the fire point, and the high-temperature metal slag that fell from the splash ignited the PPR tank and other combustibles placed in the 1# workshop (G-K axis of the plant) immediately below the working face, causing a fire.

The wall collapsed and killed 2 fire and rescue personnel!

On-site investigation and experiments

(2) Analysis of the causes of wall collapse. Through the on-site inspection, testing and identification of the collapsed wall and expert demonstration, it is comprehensively determined that the factors that cause the overall collapse of the outer retaining wall of the plant are mainly internal causes and inducements.

1. There are congenital defects in the engineering quality of the outer retaining wall of the plant, and there are serious safety hazards.

The main performance is as follows: first, the structural columns, ring beams and parapets of the perimeter retaining wall are not effectively connected with the main steel frame; second, the height-thickness ratio of the perimeter retaining wall and the typical column spacing of the structural column do not meet the requirements of the specification; third, the concrete compressive strength of the foundation beam of the perimeter retaining wall, and the lap anchorage of the steel reinforcement of the structural column and the window lintel do not meet the requirements of the specification. As a result, the out-of-plane stable bearing capacity of the periphery retaining wall itself is much lower than the gravity load, and it cannot be kept stable, which is the internal factor that causes the overall overturning and collapse of the wall.

2. There are no fire protection measures for the main steel structure of the plant, which fails to delay the heating process of the steel structure. After testing and identification, there is no fire protection coating on the surface of the main steel structure of the plant, which does not meet the design requirements, resulting in the rapid thermal expansion of the steel frame under the fire state, and the outward tilt of the wall caused by the uneven heating of the inner and outer sides of the outer wall, the use of the steel structure beyond the design conditions and the technical transformation, etc., are important inducing factors for the overall overturning and collapse of the wall.

The wall collapsed and killed 2 fire and rescue personnel!

The parapet wall on the northeast side of the plant collapsed as a whole

(3) Causes of casualties of fire and rescue personnel.

1. There are major safety hazards in the building structure. There is a hidden danger of insufficient stability of the collapsed wall, and there are serious structural safety hazards in the masonry peripheral retaining wall structure due to the design and construction of the relevant national regulations. At the same time, the collapsed wall is set up with a reinforced concrete ring beam at an elevation of 3.3 meters and 9.8 meters, and the huge gravitational potential energy produces a strong destructive force when it collapses, causing serious damage to fire rescue personnel and vehicles.

2. The overall overturning and collapse time is short and the harm is great. The time for the masonry perimeter wall of the brick-concrete structure to collapse in the event of a fire is less than one-third of the normal fire-resistant design requirements, and it is difficult to predict in advance. The masonry perimeter wall near the K-14 steel column on the northeast side of the plant suddenly overturned outward, driving the adjacent walls with a span of 175 meters to instantly overturn and collapse in 3 seconds, and the collapse speed was extremely fast, and the fire rescue personnel had no time to avoid danger.

The wall collapsed and killed 2 fire and rescue personnel!

The fire engine was badly damaged

3. The combat operation surface of fire fighting is limited. The circular lane on all sides of the fire plant is only the northeast lane to facilitate the operation of fire fighting vehicles, the lane is about 12m wide, which is the closest to the fire area, and this operation face is equipped with five entrance and exit openings to facilitate quick internal attack. The width of the lane in other directions is narrow, the distance to the area of fire is increased several times, and there are three entities that do not catch fire. There are a number of cars parked on all lanes, and there are polypropylene, steel frames, finished plastic buckets and other items on the northeast side of the fire extinguishing operation to occupy the road and pile up, resulting in the limited development of fire rescue vehicles, and the vehicle parking position is close to the outer parapet wall of the plant, and it is impossible to reserve enough safety distance.

The wall collapsed and killed 2 fire and rescue personnel!

Schematic diagram of fire extinguishing operations

The accident related to the main problems exposed by the enterprise

1. Jiangxi Zhongnan Environmental Protection Equipment Co., Ltd.

As the lessee of the burning plant and the controlling shareholder of Sumitomo Elevator Company, first, the safety awareness was weak, and the production of PPR tanks was engaged in the production of PPR tanks in the Class E plant, and the fire safety conditions required by the production process were not re-approved and the fire-fighting facilities were upgraded; , illegal production in the new production plant without obtaining an industrial product production license.

2. Jiangxi Sumitomo Fuji Elevator Co., Ltd.

As a fire plant construction (property rights) unit, the first is not to conscientiously fulfill the primary responsibility of the construction unit for the quality of the project, and entrust the project supervision task to the Zhengdong supervision company that has an equity relationship with the construction unit, resulting in the on-site construction supervision workflow in the form, and arranging personnel without relevant qualifications to participate in the on-site management of the design, construction and supervision units. The second is to change the use of the plant at will, lease the Class E plant to the unit of Class C production process to engage in production operations, and do not sign a safety management agreement with the three tenants, fail to coordinate and manage the safety production and fire protection work, and fail to conduct regular safety inspections. Supervise and rectify hidden dangers, especially in the case of knowing that there are cracks in the outer walls of the plant, not to deal with them, and let the risks and hidden dangers exist for a long time; This eventually led to a fire and a collapse of the wall.

3. Jiangxi Changding Construction Engineering Co., Ltd.

As the construction unit of the plant heightening and renovation project of Sumitomo Elevator Company, the main responsibility for production safety was not implemented, the safety production management organization was not established, the safety production responsibility system and safety production rules and regulations for all employees were not established and improved, and the safety production education and training and assessment were not organized, and the safety management was seriously lacking; the plant heightening and renovation project did not prepare the construction organization design, did not arrange full-time safety management personnel, did not establish a fire safety responsibility system, did not formulate an emergency plan, and did not organize targeted fire drills; in violation of regulations, Long Mousheng, who had not obtained the qualification certificate of the constructor, was arranged to be the person in charge of the project, and Zhang Mousheng, who had not obtained the qualification certificate for special operations, was hired, Li Mouping and 6 personnel carried out electrical welding fire operations, and did not clean up the combustibles at the operation site, resulting in a fire accident.

4. Ganzhou Dongxin Construction Engineering Co., Ltd.

As the construction unit of the plant project construction project of Sumitomo Elevator Company, it allowed others to undertake the project with the company's qualifications, failed to carry out construction in accordance with the design drawings and relevant technical standards, resulting in serious quality and safety hazards in the construction project, and failed to arrange personnel with the qualification of construction engineer to serve as the project leader and participate in the completion and acceptance of the plant.

5. Ganzhou Zhengdong Engineering Construction Supervision Consulting Co., Ltd.

As the supervision unit of the plant construction project of Sumitomo Elevator Company, the project supervision was a mere formality, and the project supervision failed to perform its obligations in accordance with the supervision contract, and appointed a person who did not have the supervision qualification to be responsible for on-site supervision; the actual construction person in charge and the construction personnel without professional qualifications were appointed to be responsible for the construction of the project, and the construction process was not carried out according to the drawings.

6. Jiangxi Provincial Co-construction Engineering Design Institute Co., Ltd.

As the design unit of the Sumitomo Elevator Company's plant construction project, first, the design documents did not meet the requirements of the specification, the Sumitomo plant construction drawing design documents issued were not strictly controlled, the connection between the retaining wall and the steel structure was not clarified in the design documents, and the design intent was not explained to the construction unit and the supervision unit before construction. Explain the design documents, resulting in the reduction of the quality of the construction project at the source; the second is that the company's electronic signature management is chaotic, and the personnel on the construction drawing design documents issued by the company are all using the seal without their consent, and arrange the personnel who do not meet the requirements to participate in the completion acceptance of the plant, and the management documents such as the completion acceptance record form are replaced by signatures.

7. Ganzhou Xinzhu Construction Engineering Construction Drawing Design Review Co., Ltd. As the design drawing review agency of Sumitomo Elevator Plant Construction Project, the construction drawing review was not strict, and the construction drawing design did not meet the requirements of relevant standards and specifications was not found, and a qualified opinion was issued.

Persons who have been subject to compulsory measures by judicial organs

1. Ling Moufeng, male, the legal representative of Sumitomo Elevator Company, did not implement the main responsibility for production safety, and was directly responsible for the accident. He was criminally detained on August 6, 2023 on suspicion of the crime of major liability accidents.

2. Huang Mouzhong, male, the legal representative of Zhongnan Environmental Protection Company, does not implement the main responsibility for production safety, and is directly responsible for the accident. He was criminally detained on August 6, 2023 on suspicion of the crime of major liability accidents.

3. Hu Mouqi, male, legal representative of Changding Engineering Company, the main responsibility for production safety is not implemented, and he is directly responsible for the accident. He was criminally detained on August 6, 2023 on suspicion of the crime of major liability accidents.

4. Zhang, male, a construction worker employed by Changding Engineering Company, carried out gas cutting operations before the accident and was directly responsible for the accident. He was criminally detained on August 6, 2023 on suspicion of the crime of major liability accidents.

5. Li Mouping, male, a construction worker employed by Changding Engineering Company, carried out gas cutting operations before the accident and was directly responsible for the accident. He was criminally detained on August 6, 2023 on suspicion of the crime of major liability accidents.

It is recommended that it be transferred to the judicial organs for processing

1. Liu Mouming, male, the actual person in charge of the Ganzhou Branch of Jiangxi Provincial Co-construction Engineering Design Institute Co., Ltd., and the actual person in charge of the design of the plant construction project of Sumitomo Elevator Company. The construction drawing design of the plant project of Sumitomo Elevator Company issued did not meet the requirements of relevant standards and specifications, violated Articles 37, 52 and 56 of the Construction Law of the People's Republic of China, and Article 3 of the Regulations on the Quality Management of Construction Projects, and was mainly responsible for the serious consequences caused by the collapse of the wall. His behavior is suspected of being a crime, and it is recommended that he be transferred to the judicial organs for filing and investigation.

2. Xu Moujun, male, legal representative of Jiangxi Provincial Co-construction Engineering Design Institute Co., Ltd. The design of the construction drawings of the Sumitomo Elevator Company's plant project did not meet the requirements of the relevant standards and specifications, violated Articles 37, 52 and 56 of the Construction Law of the People's Republic of China, and Article 3 of the Regulations on the Quality Management of Construction Projects, and was responsible for the serious consequences caused by the collapse of the wall. His behavior is suspected of being a crime, and it is recommended that he be transferred to the judicial organs for filing and investigation.

3. Li Mousheng, male, the actual person in charge of the construction of the plant of Sumitomo Elevator Company. Borrowing qualifications to contract engineering projects, and there are serious quality problems, and the main responsibility for the serious consequences caused by the collapse of the wall. His behavior is suspected of being a crime, and it is recommended that he be transferred to the judicial organs for filing and investigation.

4. Long Mousheng, male, employee of Changding Engineering Company, person in charge of the construction site of the plant heightening and renovation project of Sumitomo Elevator Company. Failure to obtain the construction engineer qualification certificate, arranging personnel who have not obtained the safety officer certificate to serve as on-site safety production management, employing construction welder certificates who have not obtained the special operation qualification certificate to engage in electro-oxygen welding operations, failing to identify the risks and hidden dangers of the electro-oxygen welding hot work site, and being mainly responsible for the occurrence of the fire. His behavior is suspected of being a crime, and it is recommended that he be transferred to the judicial organs for filing and investigation.

It is recommended that those held accountable accountable

The accident investigation team handed over to the discipline inspection and supervision organs for further investigation and handling of clues such as problems in the performance of duties by public officials of local party committees, governments, and relevant departments discovered during the investigation of the accident.

end

▌Source: China Safety Production Network, Jiangxi Provincial Emergency Management Department

The wall collapsed and killed 2 fire and rescue personnel!

It is the greatest encouragement for emergency responders!

The wall collapsed and killed 2 fire and rescue personnel!