Tonglin Road in Laishan District is a secondary road connecting Gangcheng East Street and Guanhai Road to Qingquan Road, in recent years, with the increase of traffic flow and the growth of road service life, the road surface has been damaged to varying degrees, potholes and other problems. In order to completely solve this phenomenon, the Laishan District Comprehensive Administrative Law Enforcement Bureau plans to start the overall reconstruction project of the entire road line on April 14, which is expected to be completed on July 22.
Diagram of road reconstruction sections
In order to minimize the impact of road construction on surrounding shops, enterprises and institutions, and daily vehicles, the Laishan District Comprehensive Administrative Law Enforcement Bureau will adopt a sectional construction method to carry out the work. The specific construction schedule is as follows.
From April 14th to May 27th, the construction of the section from Yinhai Road to Xinyuan Road was carried out, and during the period, the roadway was closed from April 27th to April 30th.
Yinhai Road - Xinyuan Road: Vehicle detour route from April 14 to May 27
From April 21st to June 30th, the construction of the section from Guanhai Road to Yinhai Road will be carried out, and during this period, the roadway will be closed from May 1st to June 2nd.
Guanhai Road - Yinhai Road: Vehicle detour route from April 21 to June 30
From May 17th to June 13th, the construction of Xinyuan Road to Gangcheng East Street (the eastern half) was carried out, and during the period, the roadway was closed from June 3rd to June 9th.
Xinyuan Road - East Half of Gangcheng East Street: Vehicle detour route from May 17 to June 13
From May 22nd to June 23rd, the construction of Xinyuan Road to Gangcheng East Street (west half) was carried out, and during the period, the roadway was closed from June 10th to June 16th.
Xinyuan Road - the western half of Gangcheng East Street: Vehicle detour route from May 22 to June 23
From June 17th to July 1st, the construction of Guanhai Road to Qingquan Road (northern half) will be carried out, and the half will be closed for construction during this period.
Guanhai Road-Qingquan Road North Half: Vehicle detour route from June 17th to July 1st
From July 2nd to July 22nd, the construction of Guanhai Road to Qingquan Road (southern half) will be carried out, and during this period, the roadway will be closed from July 2nd to July 14th.
Guanhai Road - Qingquan Road South Half: Vehicle detour route from July 2 to July 22
The Laishan District Comprehensive Administrative Law Enforcement Bureau hereby reminds residents that during the construction period, in case of weather, traffic control and other factors, each section of the construction plan will be adjusted.