laitimes

Municipal shorthand mantras

author:Accompany you to the municipal examination

-- Construction of urban road subgrade

1. The machine management between the exposed property management room is handed over to the security guard

characteristics of subgrade construction;

(1) The construction of urban road subgrade engineering is in the open air, which is greatly affected by natural conditions, there are many professional types, many structures, and criss-cross pipelines in the construction area of the project, and there are many cooperative work and interference between professions and society, resulting in many construction changes. In particular, the old road reconstruction project has extremely high traffic pressure, complex underground pipelines, and high requirements for driving safety, pedestrian safety, and protection of trees and structures.

(2) The subgrade construction is mainly based on mechanical operation, supplemented by manual cooperation; when manual cooperation with earthwork operation, a special person must be set up to command; and the mode of parallel operation of flowing water or segmentation is adopted.

2. Soil (stone) square hole wall shoulder slope pipe

Urban road subgrade engineering includes the subgrade (roadbed) itself and related earthwork (stone), culverts, retaining walls, shoulders, slopes, various pipelines and other projects along the line.

3. Prepare attachments

The basic process of subgrade construction: preparatory work→ ancillary structures→ subgrade (earth, stone) construction

4. Fence who handed over, test the network line pile

Preparation for subgrade construction

(1) Set up a fence in accordance with the traffic guidance plan approved by the traffic management department to guide temporary traffic

(2) Before the start of construction, the technical person in charge of the construction project shall make a technical safety disclosure to the construction personnel according to the approved construction plan, emphasizing the engineering difficulties, technical points and safety measures. Operators can grasp the key points and clarify responsibilities.

(3) Closed and encrypted the known measurement control points, establish a measurement control network, and then carry out the construction control pile pay-off measurement, restore the center line, repair the corner pile, the outer pile on both sides of the road, etc.

(4) Before construction, according to the engineering geological survey report, the subgrade soil should be tested for natural water content, liquid limit, plastic limit, standard compaction, CBR, and if necessary, particle analysis, organic matter content, soluble salt content, frost heave and expansion should be tested.

5. Water limit test

Before the construction of the subgrade, the natural water content, liquid limit, plastic limit, standard compaction, CBR test should be carried out on the subgrade soil according to the engineering geological survey report, and if necessary, particle analysis, organic matter content, soluble salt content, frost heave and expansion should be tested.

6. Comply with the drainage dismantling, modification and consolidation

(1) Underground pipelines, culverts (pipes) and other structures can be carried out at the same time as the roadbed (earthwork), but the construction of new underground pipelines must follow the principles of "underground first, then aboveground" and "deep first and then shallow".

(2) Demolition, reconstruction, reinforcement and protection of existing underground pipelines and other structures.

(3) Build drainage facilities for surface water and groundwater to create conditions for subsequent earthwork and stone engineering construction.

7. Digging, filling, flattening, repairing, and building

Subgrade (earth, stone) construction process: excavation of trenches, filling of embankments, leveling of subgrades, compaction of subgrades, trimming of roadbeds, construction of protective works, etc.

8. In addition to the flat fill, high partial pressure

When the original ground elevation is lower than the design subgrade elevation, earthwork (i.e., fill subgrade) is required.

(1) Remove the water from the original area, remove tree roots, weeds, silt, etc. The pits of grave pits, wells, and tree root pits should be properly disposed of, and filled in layers to the height of the original ground.

(2) The filling section should be leveled in advance, when the ground lateral slope is steeper than 1:5, it needs to be repaired into the form of steps, the height of each layer of steps should not be greater than 300mm, and the width should not be less than 1.0m.

(3) According to the measurement centerline pile and downhill foot pile, fill and compact in layers.

(6) The height of the subgrade fill should be increased according to the design elevation. When filling to the last layer, the thickness of the fill should be controlled according to the design section and elevation and rolled and trimmed in time.

(7) The fillers with different properties should be classified, layered filling, and compacted, and special construction plans should be formulated for the construction of high slopes of the roadbed.

(1) The filling should be carried out in layers. After the lower layer of filling is qualified, the upper layer can be filled. The width of the roadbed fill should be 500mm wider on each side than the design width.

9. In addition to the dry evidence to avoid the ban, divide the digging and leave the pressure fill,

When the design elevation of the roadbed is lower than the elevation of the original ground, it is necessary to excavate and form the subgrade - excavate the roadbed.

(1) Before the construction of the roadbed, the water on the ground should be eliminated and drained, and the root pits, grave pits, wells and other parts should be technically treated.

(2) Excavation according to the measurement center line and side piles.

(3) When excavating, it should be excavated in layers from top to bottom, and it is strictly forbidden to dig holes. During mechanical excavation, structures and pipelines must be avoided, and manual excavation should be used within 1m from the pipeline edge, and manual excavation must be used within 2m from the directly buried cable. The excavation section shall not be over-excavated, and the amount of compaction that should be rolled to the design elevation shall be left.

(6) The trench of the rainwater branch pipe and the inspection well should be filled with lime soil or lime fly ash gravel.

10. Clear the edge and fill the pressure

(1) The surface should be cleaned up when building a rock-filled embankment, the edge of the building should be stacked first, and then the stone should be filled horizontally layer by layer to ensure the stability of the slope.

(4) The trenches around the pipelines and structures within the subgrade should be backfilled.

11. The machine is thick and heavy

(1) Before the formal compaction of the subgrade, the test section should be done when conditions permit, so as to obtain the technical parameters related to the construction of the subgrade.

(2) The main purposes of the test are:

1) Determine the value of subgrade pre-settlement.

2) Reasonable selection of compaction equipment, the selection of machinery and tools to consider the factors of different grades of the road, the size of the engineering quantity, geological conditions, operating environment and construction period requirements.

3) According to the requirements of compaction, determine the number of compaction times.

4) determine the thickness of each layer of virtual paving within the width of the roadbed.

5) According to the type of soil, humidity, equipment and site conditions, choose the compaction method.

12. 5080 light solid protection

(1) When the pipeline is located within the subgrade, the compaction degree of the backfill of the trench shall comply with the provisions of the "Code for the Construction and Acceptance of Water Supply and Drainage Pipeline Engineering" GB50268-2008, and light compaction tools should be used within 50cm above the top of the pipe.

(2) When the covering thickness from the top surface of the pipeline structure to the roadbed is not more than 50cm, the pipeline structure should be reinforced.

(3) When the covering thickness from the top surface of the pipeline structure to the roadbed is 50~80cm, protection or reinforcement measures should be taken for the pipeline structure when the roadbed is compacted.

13. The original velocity is in the direction of the distance, and the machine inspection water is high

The key points of urban road subgrade compaction should be mastered: according to the actual situation of the project, the relationship between the compaction machine, compaction method and compaction thickness should be reasonably adjusted to achieve the required compaction density.

(1) Compaction method (formula): gravity compaction (static pressure) and vibration compaction.

(2) The principle of soil subgrade compaction should be followed: "first light and then heavy, first static and then vibrating, first low and then high, first slow and then fast, and the wheel tracks are overlapped." "The maximum speed of the roller should not exceed 4 km/h.

(3) Rolling should be carried out from the edge of the roadbed to the center, and the outer edge of the roller wheel should be kept at a safe distance from the edge of the roadbed.

(4) The parts that cannot be rolled should be compacted with a small tamping press to prevent leakage, and the tamping area is required to overlap 1/4~1/3.

(4) The roller is not less than 12t grade, and the rolling should be carried out from both sides of the road to the center of the road until there is no obvious wheel track on the surface.

(3) The rock-filled embankment should be compacted with a vibrating roller of more than 12t, a tire roller of more than 25t or a rammer of 2.5t.

(5) When rolling, measures such as sprinkling or changing soil and drying should be taken according to the dryness and wetness of the soil.

(2) Loosen and dry the over-wet soil, or add water evenly to the over-dry soil to make its water content close to the optimal water content range.

(5) The top surface of the pipe culvert within the fill height can be filled with more than 500mm before it can be rolled by a road roller.

(4) Check the width, thickness and moisture content of the paved soil layer before rolling, and roll it after it is qualified.

14. The layer bed is bent and curved

(1) Mainly check the compaction degree of each layer, and take measures to improve when it does not meet the quality standards.

(2) The road bed should be smooth and solid, without significant wheel tracks, slurry, waves, peeling and other phenomena.

(3) The embankment slope should be compact, stable and smooth.

(4) The top surface of the roadbed (roadbed) should be tested for compaction and deflection value, and meet the requirements of the design or related standards.

15、压弯高平线宽坡 9530

Inspection and acceptance items: the main control items are compaction degree and deflection value (0.01mm), and the general items have requirements such as longitudinal elevation of the roadbed, centerline deviation, flatness, width, cross slope and embankment slope.

Subgrade compaction standard
Cut-and-fill type The depth below the top surface of the bed, cm The type of road Compaction % Frequency of inspection Test Method
Every 1000㎡ A set of 3 points per layer
Excavation 0~30 Expressways, trunk roads ≥95 The ring knife method is used for fine-grained soil, and the sand filling method is used for coarse-grained soil
Secondary trunk roads ≥93
Branch ≥90
fill 0~80 Expressways, trunk roads ≥95
Secondary trunk roads ≥93
Branch ≥90

Yesterday 速记口诀

1. Cast-in-place masonry reinforcement

A common retaining wall construction method in urban road and bridge engineering

2. Heavy arm (wall) column bar bar

According to the form of retaining wall structure and structural characteristics

3. Self-stabilizing pouring construction province

Structural features of gravity retaining wall

4, Upper and lower tables

Balanced retaining wall composition

5. Fill the soil steeply and dig less foundation

Structural features of balanced retaining wall

6. The cantilever height of the filling is not good

Structural features of reinforced concrete cantilever retaining wall

7. The bottom surface is supported

Reinforced concrete buttress retaining wall composition

8. The filling and ribbing force is good

Structural features of reinforced concrete buttress retaining wall

9. The base column is pulled and unloaded

Constructed of a column-plate retaining wall with unloading plates

10. Fill the soil less and dig pre-assembly

Features of the structure of the column-plate retaining wall with unloading plates

11. Pre-assembly of anchor plate ribs

Structural features of bolted retaining wall

12. a column plate pull block

It is composed of a self-supporting (tail rod type) retaining wall

13. Provincial soft pre-spelling soil block

Structural characteristics of tail rod retaining wall

14. The price of geotechnical neatness and softness is beautiful

Structural characteristics of reinforced earth retaining wall

15. The foundation variable view water filtration joint

Retaining wall construction requirements

16. The main fovea is centered by Longjing

The retaining wall structure bears the earth pressure and the size of the order

Shorthand three days ago

1. Particle gaps

Basic classification of asphalt mixture:

2. Loose and dense leaching holes

Asphalt mixture structure

3. Crowded

Asphalt mixture structure type

4. Friction and stickiness

Mechanical strength of asphalt mixture

5. The suspended skeleton is empty

The structure of asphalt mixture composed according to the principle of grading

6. The large sticky angle is small before subcharge

Characteristics of suspension-dense structural asphalt mixture

7. The thickness is more and the thickness is less, and the viscosity is low and the angle is high

Characteristics of skeleton-void structure asphalt mixture

8. The thickness of the break is high

Characteristics of skeleton-dense structure asphalt mixture

9. Special use for groups

The difference between the main types of hot mix asphalt mixture

Shorthand seven days ago

1. Ground as a plasma ring

Classification of urban roads

2. Ground traffic service, road width setting

Grading and basis of urban roads

3. Structural mechanics, flexible and rigid drainage

Method of classification of urban road pavement

4. The resistance of small bends becomes large and soft, and the large bends become small and rigid

Pavement damage factors of urban roads

5、31502

The service life of the pavement structure design

6. Subgrade surface layer, subgrade pad subsurface surface

Composition of urban road structure

7. Tighten and stabilize the gradual (reduced) layer and appropriate seams

Principles of asphalt pavement road structure composition

8. The fine sand is not padded

Subbase setting

9. The medium tide is too wet and frozen water and soil

Bedding settings

10. Cold 5 times hot various, waterproof and anti-slip modification layer

Uses of various asphalt mixtures