The latest and most complete main material installation, detailed process and precautions, so that the main material installation link of your home, easy to control without overturning!
At last!!! A lite version of the installation acceptance form is also available for you! When loading the main material, you can directly take it out and copy the homework!
First, the installation process:
1. Heating
Oil construction, after painting, the first item is to install heating, at this time pay attention to the kitchen bathroom must be made perfect seam, and then install heating, otherwise once the heating is installed, the back tiles can not be made beautiful seams!
2. Gas pipe
The second item is to change the gas pipe, and when the gas master is constructing, he must show the other party the cabinet design drawing, so as to ensure that the location is accurate.
Otherwise, if the pipe is far away, you have to spend money in vain, and if the position left is not accurate, you will have to be tossed back and forth again when it comes to loading the cabinet!
3. Water heater
The third item is the water heater, which requires a half-pack storage electric water heater, which must be installed before the bathroom ceiling. In this way, if the ceiling is suspended later, the gap at the joint is smaller and more beautiful, and it saves more space when wrapped!
Gas water heaters in the kitchen should also be installed in front of the ceiling. In this way, the gas pipe can be hidden in the ceiling to be more beautiful! At this time, the exhaust pipe of the kitchen hood must also be installed quickly, so that the ceiling can be directly opened in one step.
If you forget this item, after the ceiling, and then remove the top to install the smoke pipe, not only the installation of the smoke pipe is prone to problems, but even the ceiling is easy to deform!
4. Kitchen and bathroom ceiling
Next, check all the items to be installed in the kitchen bathroom roof to confirm that there are no omissions, and then the fourth ceiling construction can be carried out.
Pay attention to the position of air heating and lighting when installing, and be sure to meet your usage habits.
5. Bathroom
After the ceiling is installed, it is the fifth item, and the bathroom cabinet, toilet, shower, and shower room of the bathroom should be installed centrally.
Because the sealed gel needs time to dry, don't pay attention to protection on the day, don't let other masters bump it!
6. Cabinets and smoke stoves
After the bathroom is installed, it is the turn of the sixth cabinet and the smoke stove, which are installed in about a day as much as possible.
When installing, the location and size must be seen on the spot, while the two masters are present, you can adjust in time, once in place, otherwise after the master withdraws from the field, you find the problem, if you want to adjust, you have to communicate and coordinate back and forth, it is too tossed!
7. Metal door
Because the main materials of the kitchen and bathroom are installed, there is no need to worry about the restrictions and bumps in and out of the door, it is time to install, the seventh metal door of the kitchen and bathroom.
This project is installed very quickly, it can't be used for half a day, as long as it is checked according to the acceptance table, there will be no problem with the high probability!
8. Wooden floor
At this point, the kitchen and bathroom are all done, and the eighth item is the wooden floor of the living room and bedroom.
If you are looking for detail quality, it is definitely best to install wooden floors first, and then wooden doors. Because the frame of the wooden door can press the wooden floor well, the floor and the floor are more fitted, and the details will be more beautiful!
If you pursue trouble-saving, install the wooden door first and then install the wooden floor, so that the wooden floor and skirting board at the door frame can be installed in place at one time.
9. Wooden door
Next is the wooden door of the ninth bedroom, to let the master pay attention to the gap under the door, too small to ventilate is not good, too large is not good sound insulation, but also light transmission.
When installing, you can check what material the wooden door you choose is from the opening and cutting.
10. Switch lamps and small hardware
Finally, switch lamps and hardware, because installation masters often have a starting charge, so it is best to save these things together and install them once, not only the cost is more cost-effective but also allows you to save time.
At this point, the main material of hard installation has been fully done! It's almost furniture, appliances and soft furnishings to enter!
Second, avoid pits
In the main material installation link, in addition to mastering the process, special attention should be paid to these points:
1. Installation sequence
When installing all the main materials, in order to stagger the time to ensure the construction period, kitchen cabinets, smoke stoves, wooden doors, metal doors and wooden floors can also be flexibly adjusted for installation. Pay attention to the place of connection, just consider the place in advance.
2. Sealant
Buy a good sealant online in advance, if you use the free glue brought by the masters, not only is it less environmentally friendly, the key is that it is easy to yellow and fall off in a few years! When the time comes, find someone to repair it, but it will be troublesome and costly!
3. Angle valve
Waterway installation has to use angle valves, this small thing is not expensive, but poor quality in less than two years to start leaking water not only maintenance trouble, but also property hidden dangers, so it is recommended to buy a few good spare points in advance, each outlet with one.
4. Keep an eye on the scene
The main material installation should be focused on the site as much as possible, and it is more trouble-free to be in place at one time! If you don't install it the first time, you will have to wait for a month to rework or repair it later!
5. Acceptance form
This main material installation acceptance form, you must put it away!! When each project is installed, check and accept against this table, and most problems can be controlled!
For more decoration questions, welcome to view previous videos, or leave a message in the comment area!