Project overview
Route directions
Starting from the south side of the 346 National Highway Luyuan Interchange, crossing the Sangan River to the south, crossing with Yinyuan West Road and Jinqiao Road, continuing south through the Huangsipu Ruins Planning Area and crossing Nanyuan Road, and then crossing with Xinjing Road from the west side of Zhangjiagang substation through Huangsipu Park, and continuously crossing Yangtang Road, Renmin Road, Huamiao River to the south, and finally SuyuZhang Highway.
Design mileage
The total design mileage is 6.080km.
Design standards
It is built according to the standard of a six-lane first-class highway.
Design speed 80km/h.
Progress is current
At present, the substructure of the East Third Ring Road is 90% complete.
At present, the prefabricated box girder erection work is mainly carried out, and the erection has been completed by 32%.
In terms of cross-road construction, the left-dimensional prefabricated beam of the main line across Xinjing Road has been erected;
The cast-in-place beams of the main line across Yangtang Road have been completed by 75%, and the construction of cast-in-place beams on Yangtang Road is expected to be completed by the end of the month.
Plan for the next step
In the next step, the construction unit will continue to rapidly promote the prefabrication and erection of the prefabricated box girder.
The entire line is expected to be completed and opened to traffic by the end of 2022, so let's look forward to it!
Source: Zhangjiagang Municipal Transportation Bureau