With the sound of a cannon at the southern end of the Liangmu Road tunnel,
A glimmer of light shines through,
Liangmu Road Road Engineering (Phase I) Project
The western line of the tunnel was successfully completed!
Liangmu Road Works (Phase I)
The Liangmu Road Road Engineering (Phase I) project starts from the south of Taixian Road in the north, passes through the Mantou Mountain area in the form of a tunnel, and the south line is in the form of an elevated line, landing in the north of Lidong Road, and ending at Lidong Road, with a total length of about 2.1 kilometers.
The design road grade of the project is a first-class urban trunk road, the design lane is two-way 4 lanes, and the design speed is 60km/h. The tunnel of the project is partially separated from two holes, with a length of about 1.5 kilometers on the west line and 1.6 kilometers on the east line, with a net width of 10.75 meters for a single tunnel.
The project is an important passage connecting Xianlin with the future science and technology city and Lixiang and Xiaoheshan areas, and is the central axis road on the millennium development axis of Yuhang District. The breakthrough of the west line marks a phased victory in the construction of the tunnel, and also lays a solid foundation for the double-width breakthrough of the Liangmu Road tunnel and the opening of the whole line.
Up to now, 960 meters have been excavated on the east line of the Liangmu Road Road Engineering (Phase I) tunnel, and only 627 meters remain. The project as a whole is expected to complete the tunnel breakthrough in October this year, and the installation and pavement construction will be completed in December, and strive to be completed by the end of this year.
In addition, the construction of the Liangmu Road Road Project (Phase II), which has attracted much attention, is also in full swing.
The project stretches from Yunmen Avenue in the south to East-West Avenue in the north, with a total length of about 5.8 kilometers. After completion, it will not only improve the north-south longitudinal traffic accessibility within the cloud city, but also connect the road network of the future science and technology city and Liangzhu and bottle kiln areas, which is expected to be completed by the end of this year.