There is a Zhongnan Junqifu community in Nanxun, Huzhou
Almost a year has passed since the agreed delivery time
Now the owners have finally received the notice of repossession
Not past the time of the home inspection
It is said that it is a belly fire
Ms. Yuan, owner of Huzhou Nanxunjun Qifu Community: The total price of the house is more than 1.14 million.
Reporter: When will the house be delivered?
Ms. Yuan: At that time, it was agreed that June 30, 2023, but on April 30, 2024, I was temporarily notified to come to collect the house.
Reporter: Did you talk about any compensation or how?
Ms. Yuan: Nothing.
Ms. Yuan's purchase contract shows:
Buyers and developers agree
The commercial housing has not been delivered for 90 days
The buyer has the right to terminate the contract
The developer shall refund the full amount paid
Interest is paid
At the same time, 1% of the total room price
Pay liquidated damages
Ms. Yuan said that she just needed to live by herself
So I still chose a home inspection
Ms. Yuan, owner of Huzhou Nanxunjun Qifu Community: I can see a lot of fire in the community, you can say here, I came in to shoot two days ago, we didn't come in to collect the house, the road has collapsed. I took a look at it a few days ago, and I took it again today, and it's even more serious than what I took a few days ago.
Reporter: It's still collapsing?
Ms. Yuan: Yes, yes, this is my door, and the delivery is still like this without cleaning and nothing. I'll show you that the fire protection facilities haven't been done yet, you can take a look at these, these are the things that mean that when the house is handed over, there are still workers working inside, and nothing is done in it.
What worries the owners even more:
Many houses are not connected to water and electricity
Mr. Fei, owner of Huzhou Nanxunjun Qifu Community: They have not installed all the water and electricity meters now.
Reporter: The meter is not installed?
Mr. Fei: No, no, this is the water meter, the water meter includes all the facilities now, all of them are like this.
Reporter: What about the gas meter?
Mr. Fei: The gas meter is inside, it is the pipe coming through, just put it here, and he will be fine.
Reporter: Have you ever asked about three books, one certificate and one table?
Mr. Fei: He didn't show us it, and he didn't say if there were.
Reporter: Have you asked the developer whether this standard has met the delivery standard?
Mr. Fei: He said yes, he said let's open an account by ourselves, but he didn't install a watch, nothing was installed.
The owners all say
The average price when they bought a house was more than 10,000 yuan
The house price is in the first gear in Nanxun
Mr. Fei, the owner of Huzhou Nanxunjun Qifu Community: At that time, the quality of Zhongnan was also okay. Then it signed a contract with us, including the property, which was signed by Zhongnan's own property at that time, and it informed us that the property had been replaced on the day of delivery, and they just had a few security guards standing below, and there was no specific person in charge.
Reporter: What did the security guard say?
Mr. Fei: They all said that they came to help, and they themselves mentioned that because it was delayed, their own property was afraid that we would not pay the property fee at that time, and they were afraid that we would offset it.
At the entrance of the complex
The reporter ran into the developer
Staff of Huzhou Yuexin Real Estate Co., Ltd
The other party said
Questions about changing properties
There was a misunderstanding among the owners
Huzhou Yuexin Real Estate Co., Ltd. Staff: Because Zhongnan Property has been owned by China Resources, this is also the government to help us to ensure the delivery of the building to raise funds, and there is no way.
Reporter: Is there a contract with the new property?
Huzhou Yuexin Real Estate Co., Ltd. Staff: The contract has been signed, and it should be around May 20 to May 25, and the government will complete the filing and approval procedures.
The staff member emphasized
The reason why the owners saw that there were still workers working on the construction
It's because they are still insisting on "not lying flat"
In order to ensure the quality of the community
Working overtime
Reporter: Have you met the delivery standards, three books, one certificate and one table?
Huzhou Yuexin Real Estate Co., Ltd. Staff: The delivery standard has been reached, and the delivery standard agreed in the completion contract is the completion record form and the actual measurement report, both of which were publicized when they were delivered.
Reporter: I don't think there is any water and electricity.
Huzhou Yuexin Real Estate Co., Ltd. Staff: The gas has been connected, and the water is connected below the third floor. The local authorities are also helping us coordinate, and it is expected that it will be completed around May 20th.
Reporter: Can the water meter and electricity meter be delivered first if it is not installed?
Huzhou Yuexin Real Estate Co., Ltd. Staff: It is two systems and two logics with completion, because I have completed the acceptance, and now the information is handed over, and they want to record the system. If water and electricity are needed temporarily, the developer will be responsible for giving them them, and now ensure that the small owners renovate first.
The staff repeatedly emphasized
At present, the developer has made every effort to ensure the delivery of the building
It is hoped that the owners will actively cooperate with the resumption of the house as soon as possible
The owners said this
Unacceptable
Mr. Fei, the owner of Huzhou Nanxunjun Qifu Community: We are now asking for liquidated damages, and they are now saying that our customers will go to court.
Huzhou Yuexin Real Estate Co., Ltd. Staff: At present, we can only achieve the stage of ensuring delivery and property certificate. First of all, these major matters have been implemented, there are no major stuck points, and the corresponding steps for handling the property certificate have also been arranged, and the owner has been informed.
Reporter: Anyway, it is determined that the property certificate can be handled?
Huzhou Yuexin Real Estate Co., Ltd. Staff: That's right.
Reporter: After the property certificate arrived, did you delay the receipt of compensation in the end?
Huzhou Yuexin Real Estate Co., Ltd. Staff: At present, what I can reply to is only in accordance with the requirements of the state, to ensure the delivery of the building and the property certificate.