Video|Dozens of "air slender men" did "surgery" to replace the soft cross of the catenary

author:Purple Cow News

Loading...

On May 13, the Nanjing East Station of the Beijing-Shanghai Railway was crowded, and more than 100 catenary workers from the Nanjing Maintenance Section of the Shanghai Maintenance Office of the Transportation Management Company of China Railway Electrification Bureau gathered in the station yard and completed a large-scale aerial catenary soft span replacement "operation" within 60 minutes of "skylight", marking the successful start of the 2024 Beijing-Shanghai Line soft span overhaul project of the Nanjing Vascular Section.

Video|Dozens of "air slender men" did "surgery" to replace the soft cross of the catenary

Nanjing East Railway Station is the largest double-track electrified railway hump marshalling station, freight station and hub station in East China, and is known as the largest railway "train processing plant" in East China, undertaking the task of dismantling and marshalling four railway freight trains in Beijing-Shanghai, Ningtong, Ningqi and Ningxi.

Video|Dozens of "air slender men" did "surgery" to replace the soft cross of the catenary

It is understood that the replacement of soft span construction is one of the important construction projects of the catenary comprehensive overhaul project, and it is also a difficult project to be constructed. After each construction, the new equipment is put into use immediately, and there is no transition and adjustment time, which determines that the operators must complete all the new installation, demolition, adjustment, and opening work within the limited "skylight", so as to ensure that the construction can be opened immediately after the end of the operation. Secondly, the soft spanning process is more complex, the scope of construction work is wider, the workload of construction work is larger, there are more personnel and tools to participate in the operation, and the safety risk is large.

Video|Dozens of "air slender men" did "surgery" to replace the soft cross of the catenary

The construction is located in the marshalling yard of the busy trunk line of the Beijing-Shanghai Railway and Nanjing East Railway Station, with about 140 pairs of trains passing through each day, and there are many strands in the field, and the task of the battle is arduous. Combined with the successful replacement experience of Bengbu Station, Linchang Station and Changzhou Station, the Nanjing maintenance section has organized and held construction plan layout meetings for many times, and strictly checked the construction team formation, safety risk research and judgment, construction plan optimization, emergency plan formulation, soft span calculation and prefabrication, and the professional departments carefully sorted out the construction plan, formulated a detailed check schedule, concentrated superior forces, and selected the backbone forces with rich construction experience and high comprehensive quality to coordinate the operation under the premise of ensuring safety and quality, so as to effectively improve the "skylight" Utilization rate and construction efficiency.

Video|Dozens of "air slender men" did "surgery" to replace the soft cross of the catenary

On the same day, on the various strands of the station, 2 operation vehicles and 10 vehicle ladders were lined up, and dozens of "air slender men" were hung on the catenary in the air, dragging a catenary soft span of more than 30 meters from the ground to a height of 15 meters. The catenary workers climbed up and down, with a clear division of labor, tightened bolts, adjusted parameters, and replaced parts...... The movements are skillful and orderly, tense and fast weaving the railway "safety net", and the collision sound of maintenance tools, the rumble of the operation car, and the shouts of the commander echo in the station.

"For us, this is a rare 'surgery' with a large device. The skylight time is short, and every safety link must be controlled in place. Cui Pan, the person in charge of on-site construction, introduced.

At 16:30 on the same day, after 60 minutes of intense construction, the operators successfully completed the tasks of 2 groups of soft span overall erection, suspension reversal, and old soft span dismantling, the line blockade was lifted, and the new clues ushered in the upcoming train.

Next, this section will use 23 "skylights" to complete 45 sets of soft span replacement tasks, greatly improving the quality of power supply equipment that has been in operation for 18 years, ensuring that it is put into operation in a better state, and providing safe and high-quality guarantee for passenger travel.

Correspondents: Du Xihao, Wang Zilong, Yangtze Evening News/Purple Cow News reporter Cao Lujie