With a total weight of 76,000 tons, the "land aircraft carrier" turns in the air

author:Southwestern Railroad

Loading...

April 25, 2:46 a.m

G5 Beijing-Kunming Expressway Chengmian Expansion Project

In the way that the four bridges rotate together

Achieved the crossing of the Northern Ring Road Liaison Line

and Chengdu North Ring Road

(hereinafter referred to as: Chengdu North Ring Line Railway Hub)

Precise docking with the main bridge

With a total weight of 76,000 tons, the "land aircraft carrier" turns in the air

The turnaround bridge of the G5 Beijing-Kunming Expressway Expansion Project is located in Qingbaijiang District, Chengdu, which is the throat of the northbound passage out of Chengdu City. The Chengdu North Ring Railway Hub crossed by the turnaround bridge, connecting Qingbaijiang International Logistics Port to the north and Chengdu North Railway Station, the largest freight train marshalling station in Sichuan to the south, is the traffic artery for Chengdu's north-south trains, and the average daily throughput of freight trains and passenger trains such as China-Laos trains and China-Europe trains is more than 170 trains, which is a particularly busy railway trunk line.

With a total weight of 76,000 tons, the "land aircraft carrier" turns in the air

Considering the busyness of the Chengdu North Ring Line railway hub, in order to ensure the safety of the train, while not affecting the normal operation of the China-Laos train and the China-Europe train, it was finally decided to adopt the four-bridge simultaneous rotation method.

With a total weight of 76,000 tons, the "land aircraft carrier" turns in the air

Synchronous rotation construction of four bridges

Two turnaround bridges on the south side cross the Chengdu North Ring Road

The length is 125 meters and 112 meters, respectively

The weight is more than 16,000 tons

Two turnaround bridges near the north side

It is necessary to cross the Northern Ring Road

The span is 160 meters and 112 meters

Among them, the weight of the 160-meter bridge reached more than 28,000 tons

The total weight of the cluster is 76,000 tons

Such a large volume of cluster turning

It has set a new weight record for cluster rotary bridges in southwest China

To minimize construction

Impact on the passage of rail freight trains

The construction site will first complete the prefabrication of the bridge on both sides of the existing railway

Then through the hydraulic jack system

The bridge body is rotated at an altitude of more than 20 meters

In order to achieve the purpose of crossing the Chengdu North Ring Road railway hub

Ensure the normal passage of passing trains

How to turn a bridge with a total weight of 76,000 tons?

According to the introduction

The construction unit is under the pier

The rotating system is embedded in advance

After the start of the turnaround works

Four sets of hydraulic jacks

Pull the strand through the computer unified control

The ball hinge in the rotating system is driven to rotate

With a total weight of 76,000 tons, the "land aircraft carrier" turns in the air
With a total weight of 76,000 tons, the "land aircraft carrier" turns in the air

During the turn

The construction personnel always observe the change of angle

Measure the coordinates of the rotation

And through the BIM digital twin system

Precise control of the turning process

Ensure that the parameters must be "just right"

ultimately

It lasted 66 minutes

The four bridges are rotated separately

Precise rotation at 71.8°, 71.8°, 77.9° and 77.9°

With a total weight of 76,000 tons, the "land aircraft carrier" turns in the air
With a total weight of 76,000 tons, the "land aircraft carrier" turns in the air

After the rotation is completed

G5 Beijing-Kunming Expressway Chengmian Expansion Project

The main part of the railway-related bridge was basically completed

It will lay a solid foundation for the completion and opening of the whole line by the end of this year