It is expected to be officially put into use next year! The project in Jinshan is 85% complete →

author:i Gold Mountain
It is expected to be officially put into use next year! The project in Jinshan is 85% complete →

As a major project in Jinshan District in 2021, the construction progress of the second phase of the Xinjiang Water Purification Plant II Project has attracted much attention. At present, the project is in full swing and is expected to be officially put into use in 2023. At that time, the treatment capacity of Jinshan domestic sewage and industrial wastewater will be greatly enhanced.

It is expected to be officially put into use next year! The project in Jinshan is 85% complete →

The reporter saw at the construction site that the crane was running back and forth, and the workers were working in an orderly manner. It is understood that the second phase of the Xinjiang Water Quality Purification Plant II project expanded the facilities and equipment on the 4.6 hectares of land reserved in the first phase, with a construction area of 3704.3 square meters. At present, the main structure is about 85% complete. Wei Zhengjun, head of the second phase of the Project of Xinjiang Water Purification Plant II, said: "It is expected that by the end of this year, the structural part will be completed by more than 90%, and the installation of process equipment will be followed by the follow-up, and it is planned to enter the equipment commissioning and trial operation stage in March next year." ”

It is expected to be officially put into use next year! The project in Jinshan is 85% complete →

It is understood that the first phase of the New River Water Purification Plant II has been officially put into use in 2019. At present, up to 75,000 tons of sewage can be treated per day. After the second phase is officially put into operation, the amount of sewage treatment will be increased by 75,000 tons per day. At that time, the sewage treatment capacity in the high-tech zone, Tinglin Town, Zhangyan Town and other areas north of the Caolang Highway will be greatly improved. Wei Zhengjun, head of the second phase of the Xinjiang Water Purification Plant, said: "The sewage treatment volume of the first and second phases is 75,000 tons per day, adding up to 150,000 tons per day, which can meet the requirements of sewage discharge treatment in the entire region in terms of sewage treatment saturation. ”

It is expected to be officially put into use next year! The project in Jinshan is 85% complete →

At present, our district has formed a sewage treatment pattern of "five pieces and seven factories", that is, the Fengjing sewage plant and xingta sewage plant in the Fengjing area, the Fengting sewage plant in the Zhujing area, the langxia sewage plant in the Langxia Luxiang area, the Jinshan Wei sewage plant in the Jinshan New Town area, the Xinjiang sewage plant and the second plant in the eastern jinshan area, the sewage treatment capacity of the whole district is 353,000 cubic meters / day, and the effluent quality of each plant has reached the urban sewage treatment level A discharge standard. In addition to the second phase of the Xinjiang No. 2 plant under construction, the third phase of the Fengjing sewage treatment plant expansion project is scheduled to start next year.

Reporter | Qi Jingwei Tang Yichao

Correspondent 丨 Zhou Jie