laitimes

Subway Line 13 split! Another stop in Changping is about to enter the construction site

author:Beijing Resettlement Housing

Neighbors of Changping

Recently, some netizens broke the news

Metro Line 13 split project

There has been new progress at Tiantongyuan Station

Subway Line 13 split! Another stop in Changping is about to enter the construction site

Posted near the Tiantongyuan North District 1 neighborhood

"Rail Transit Line 13 Capacity Expansion and Upgrading Project"

Line 13A Tiantongyuan Station needs to be sealed

Announcement of some sites in the community of Tiantongyuan North District 1

Subway Line 13 split! Another stop in Changping is about to enter the construction site
Subway Line 13 split! Another stop in Changping is about to enter the construction site

The announcement is as follows

Rail Transit Line 13 capacity expansion and upgrading project

Announcement of some sites in the community of Tiantongyuan North District 1

Tiantongyuan Residents: Hello!

In order to improve the travel conditions and improve the quality of travel in the Tiantongyuan area, according to the Beijing Municipal Development and Reform Commission's "Reply on the Feasibility Study Report of the Rail Transit Line 13 Expansion and Upgrading Project" (Jingfa Reform (Pre-period) [2019] No. 13), Tiantongyuan Station has obtained the Beijing Municipal Planning and Natural Resources Commission's "Letter on the Review Opinions on the Temporary Construction Land Planning Opinions for the Temporary Construction Site of Tiantongyuan Station No. 1 of the Rail Transit Line 13 Expansion and Upgrading Project "Multi-planning" (Beijing Regulation Self-Comprehensive Review Letter [2021]) No. 0267) (see annex for details). The temporary enclosure of this construction needs to occupy 310m on the south side of the north district of Tiantongyuan (see the attached map for details); and the west side of the north district of Tiantongyuan (103m×28m) for construction.

In order to achieve the substantive start of the station as soon as possible, it is necessary to seal part of the west and south sides of the north district of Tiantongyuan as soon as possible to carry out above-ground demolition and modification, greening migration and diversion road construction work, and during the construction of the subway, the west sealing area of the north district of Tiantongyuan will be used as the construction site of Tiantongyuan Station; The enclosed area on the south side is used as a traffic guide.

In order to ensure the convenience of passage in the community during the closure period, the road will be hardened in the 3m area east of the west side of the north district of Tiantongyuan before the closure to ensure the passage of motor vehicles and pedestrians, and I hope that the majority of residents and friends will understand and cooperate.

After 7 days from the date of this announcement (April 2, 2022) (April 8, 2022), motorized and non-motorized vehicles will not be parked in the enclosed area and the hardened pavement area, and vehicles that have not been removed after 7 days will be handed over to the relevant departments for disposal. For the inconvenience caused to all residents during the construction of the subway, our unit apologizes and hopes that the majority of residents and friends will support the infrastructure construction in the Huitian area.

The content of the review opinion letter for the relevant project is as follows

Subway Line 13 split! Another stop in Changping is about to enter the construction site

Beijing Municipal Commission of Planning and Natural Resources

Beijing Regulation Self-Review Letter [2021] No. 0267

About the Tiantongyuan Station of Line 13A Expansion and Upgrading Project of Rail Transit Line 13

Planning opinions for temporary construction land at Construction Site No. 1

Letter of "Multi-Regulation" Review Opinion

Beijing City Railway Co., Ltd.:

Your unit's "Request for Application for The Planning Of the Temporary Construction Land of Tiantongyuan Station No. 1 of the Expansion and Upgrading Project of Beijing Rail Transit Line 13" was included in the deliberation of the "Multi-planning" platform (City Railway Office Zi [2021] No. 15). The capacity expansion and upgrading project of Rail Transit Line 13 is one of the projects approved by the National Development and Reform Commission in the "Reply on Adjusting the Second Phase of Beijing Urban Rail Transit Construction Planning Plan" (Development and Reform Foundation [2019] No. 1904). The tiantongyuan station of the project has completed the preliminary design expert review, and the temporary land use plan of the station has been studied by the "multi-plan" collaborative platform (joint review meeting of the temporary land use department for rail transit construction) organized by our committee, and a preliminary review opinion letter of the "multi-plan"collaborative platform of the project has been issued (Beijing Regulation Since preliminary review letter [2021] 0051). The relevant comments are hereby communicated as follows:

1. Temporary land use plan for the station

In principle, it is agreed to the temporary construction land plan for the construction site of Tiantongyuan Station No. 1 of the Capacity Expansion and Upgrading Project of Line 13A of Rail Transit Line 13, and the temporary land is located at the intersection of Litang Road and Taipingzhuang Middle 2nd Street in Changping District. The temporary area is about 28,149 square meters, of which the planned road covers an area of about 20,969 square meters and the planned road red line covers an area of about 7,180 square meters (see the annex for specific locations).

2. Construction purpose and occupation time of temporary land of the station

The main purpose of the temporary land for the temporary land of Tiantongyuan Station of Line 13A expansion and upgrading project of Rail Transit Line 13 is construction site, traffic guidance and pipeline relocation, and the temporary occupation time is about 24 months.

Third, the next step

1. Please follow the requirements of the Notice of the Ministry of Natural Resources on Regulating the Management of Temporary Land Use to handle the examination and approval of relevant temporary land use in accordance with the law.

2. Before the construction enters the site, please do a good job of coordination with the relevant land ownership units and users on the issue of users and unit access, and the construction enclosure location should fully consider the relationship with the surrounding buildings to ensure the normal passage of residents and units and meet the fire protection requirements.

3. Please arrange the construction organization plan reasonably, and take practical measures to strictly control the temporary land and the scope of the construction enclosure.

4. Please protect the trees within the scope of the temporary land, if it involves logging and relocation, please go through the relevant procedures in the competent department of landscaping of your unit.

5. Involving traffic guidance and reform matters, please go through the relevant procedures with the public security traffic management department of your unit.

6. Rail transit construction temporary land is strictly prohibited for other uses, before the end of the project to hand over the relevant land, your construction unit must dismantle the above-ground objects, and break the underground construction shafts and other temporary projects, restore the use of land conditions.

7. The construction enclosure should pay attention to the coordination with the surrounding environment.

8. Please organize the construction unit to sort out whether the buildings (structures) within the scope of each construction enclosure occupy the underground pipeline, if there is pressure, you should communicate with the relevant pipeline management unit, and consult the municipal professional companies to determine the pipeline dismantling or protection plan as soon as possible.

9. Please use your unit in strict accordance with the scope of temporary construction land and the time occupied, perform the safety management responsibility of temporary land in accordance with the law, and timely vacate and restore after the completion of the project construction.

According to the relevant announcement content

Line 13A Tiantongyuan Station is about to start construction

Let's look at its current state

Subway Line 13 split! Another stop in Changping is about to enter the construction site
Subway Line 13 split! Another stop in Changping is about to enter the construction site

The red area is the enclosing construction area

And not far away from LishuiQiao East Third Road

Line 13A East 3rd Road Station

The construction area will also be fenced off

Subway Line 13 split! Another stop in Changping is about to enter the construction site
Subway Line 13 split! Another stop in Changping is about to enter the construction site

Xiaobian saw that there was already a simple fence on the auxiliary road

A few days ago, Xiaobian also on the East Third Road Station

Have done relevant reports

Neighbors who don't know the situation yet

Let's take another look back

There is a new trend at the East Third Road Metro Station

Let's take a look

Subway Line 13 split! Another stop in Changping is about to enter the construction site

Notice

Dear relevant residents of Tiantong Zhongyuan District 1: Hello!

The construction of Dongsan Road Metro Station is based on the Beijing Municipal Development and Reform Commission's "Letter on the Preliminary Work of the Expansion and Upgrading Project of Rail Transit Line 13", "Reply on the Feasibility Study Report of the Expansion and Upgrading Project of Rail Transit Line 13", the "Letter of the Beijing Municipal Planning and Natural Resources Commission on the Review Opinions on the Design Scheme of the Expansion and Upgrading Project of Beijing Rail Transit Line 13" and the "Opinions on the Planning of the Temporary Construction Land for the Construction Site of the Construction Site of Dongsan Road Station of Line 13A of the Rail Transit Line 13 Expansion and Upgrading Project" Letter of Review Opinion" and other relevant documents are established.

Now start the preliminary entry work, in order to achieve the construction conditions of the East Third Road Station, it is necessary to temporarily relocate the 10kV electric overhead line on the south side of Taipingzhuang Zhong'er Street (between Lishuiqiao East 1st Road and East 3rd Road), and it is proposed to temporarily occupy the west area of Tiantong Zhongyuan District 1, Tiantong Zhongyuan District 1, Tiantong Zhongyuan 1 District 1 East District South Community Green Land for 10kV overhead line relocation, of which 5 poles are erected in the south green area of Tiantong Zhongyuan District 1 West District, and 9 poles are erected in the south green area of Tiantong Zhongyuan District 1. 2 electric poles were erected in the south green space of the east area of Tiantong Zhongyuan District 1, and during the construction period of the 10kV overhead power line and before restoration, about 162 trees in the above 3 communities need to be regularly pruned in accordance with the principle of taking into account the safe use of power lines and the normal growth of trees.

The 10KV overhead line relocation plan is scheduled to be carried out from March 30, 2022 to May 30, 2022, and is scheduled to be restored in 2025.

The 10KV overhead line relocation related matters are hereby announced for 7 (March 19, 2022 to March 25, 2022) natural days, and if there is any objection during the publicity period, please apply to our unit for a hearing. Thank you to the majority of residents for their support for the construction of the subway.

China Railway 23rd Bureau Group Co., Ltd

Xiaobian came to the scene where the notice was posted

Subway Line 13 split! Another stop in Changping is about to enter the construction site

The "Notice" is posted at the entrance of the community

Subway Line 13 split! Another stop in Changping is about to enter the construction site

Tiantong Zhongyuan District 1

Subway Line 13 split! Another stop in Changping is about to enter the construction site

Tiantong Zhongyuan District 1 West District

Subway Line 13 split! Another stop in Changping is about to enter the construction site

To achieve the construction conditions of The East Third Road Station

It is necessary to use the 10kV power overhead line on the south side of Taipingzhuang Middle Second Street

(Between Lishuiqiao East 1st Road and East 3rd Road)

Make temporary relocations

Involving Tiantong Zhongyuan District 1 West District, Tiantong Zhongyuan District 1,

Tiantong Zhongyuan District 1 East District South Side Community Green Land

Subway Line 13 split! Another stop in Changping is about to enter the construction site
Subway Line 13 split! Another stop in Changping is about to enter the construction site
Subway Line 13 split! Another stop in Changping is about to enter the construction site

The construction time of the relocation plan is

30 March 2022 to 30 May 2022

A recovery is planned for 2025

Let's take a look at the details of the station

Subway Line 13 split! Another stop in Changping is about to enter the construction site

On baidu maps

The location of the subway station has been marked

Intersection of Taipingzhuang Middle 2nd Street and Lishuiqiao East 3rd Road

Subway Line 13 split! Another stop in Changping is about to enter the construction site

The official website was released in August 2020

Prequalification announcement for civil construction of the project

Subway Line 13 split! Another stop in Changping is about to enter the construction site

Beijing Rail Transit Line 13 Capacity Expansion and Upgrading Project

Civil construction 12 contract sections

Prequalification Announcement

The project Beijing Rail Transit Line 13 capacity expansion and upgrading project civil construction 12 contract section has been approved by the Beijing Municipal Development and Reform Commission to Beijing Development and Reform (early stage) [2019] No. 13 construction, the bidder is Beijing Rail Transit Construction Management Co., Ltd., the construction funds come from government investment (local), the proportion of project investment is 100%, the bidding agency is Beijing Yiqun Engineering Consulting Co., Ltd., the project has met the bidding conditions, is now open bidding, Prospective bidders are invited to submit prequalification applications.

Project overview and scope of the tender

Construction site: Beijing

Construction Scale:

1 station 1 section (East 3rd Road Station, East 3rd Road Station ~ Tiantongyuan East Station Shield Section)

Contract Estimate:

39177.4 (million yuan)

Duration requirements:

1461 calendar days

Scope of Tender:

Civil works, installation works and other work, the details of which are detailed in the tender documents.

December 30, 2021

The "Beijing Rail Transit Line 13 Capacity Expansion and Upgrading Project" was released

Civil Construction Supervision 12 Contract Sections

Supervision and Bidding Announcement

Subway Line 13 split! Another stop in Changping is about to enter the construction site

Supervision of tender announcements

The construction of the 12 contract section of the civil construction supervision project of the Beijing Rail Transit Line 13 Expansion and Upgrading Project has been approved by the Beijing Municipal Development and Reform Commission to beijing development and reform (review) [2021] No. 231, the bidder is Beijing Rail Transit Construction Management Co., Ltd., the construction funds come from the government investment (local), the proportion of capital contribution is 100%. The project has met the bidding conditions, and the supervision and related services of the project are now open for bidding.

Construction site: Within the jurisdiction of Beijing Municipality

The total length of the project is about 13 km

Estimated (estimated) investment amount:

74010.69 (million yuan)

Planned Duration:

944 calendar days

All supervision services carried out by civil construction contractors within the scope of the 12 contract section of the Beijing Rail Transit Line 13 Expansion and Upgrading Project.

I hope the project will go smoothly

Start construction at an early date