In the new spring of the Year of the Tiger, striving to be the first, in the past few days, major water conservancy projects in many parts of our province have resumed work and production one after another, and have increased their horsepower to promote construction.

In Pyeongchang County, Bazhong, the construction site of the Jiangjiakou Reservoir is busy, and workers are stepping up the excavation of diversion holes. Jiangjiakou Reservoir is one of the 172 major water conservancy projects that the State Council has determined to accelerate the promotion of, and construction began in October last year, and the excavation of the No. 1 and No. 2 construction branch holes has been completed.
Chen Geng, deputy director of the Construction and Management Center of Jiangjiakou Reservoir in Bazhong City: In 2022, we will ensure that the diversion hole is completed on May 20, the acceptance of the diversion and interception stage of the project is completed at the end of October, and the excavation of the dam foundation is started at the end of the year.
The geographical location of Jiangjiakou Reservoir is relatively remote, and the geological conditions in the area are complex, among which the maximum excavated hole diameter of the diversion hole and the flood discharge hole on the right bank of the dam reaches 15 meters, which brings a lot of challenges to the construction.
Wang Jun, chief engineer of the General Contracting Project Department of Jiangjiakou Reservoir Project: In view of the excavation of this super large section cave chamber, technical measures such as less charge, diligent measurement, weak blasting, etc. are taken to ensure the excavation of the cave room.
Sprint at the beginning. In Yanyuan County, Liangshan Prefecture, another major water conservancy project under construction in our province, the Longtang Reservoir, is also stepping up the construction of the dam.
Reporter Li Fang: My current location is the hub area of Longtang Reservoir, and the excavation of the shoulder of the dam is underway at the site, and the project is advancing in an orderly manner as planned.
The Longtang Reservoir and Irrigation District Project is the first large-scale water conservancy demonstration project in Sichuan Province to be built under the general contracting mode of design, procurement and construction, including two parts: the reservoir hub project and the irrigation district project. Since the start of construction in May last year, the reservoir irrigation district project has mainly carried out the construction of three controlling tunnels, and at the same time, the work surfaces of the hub project have also been fully launched, and as of now, the excavation of the reservoir dam shoulder has been completed by 95%.
Zhao Chun, safety director of Liangshan Longtang Reservoir Hydropower Development Co., Ltd.: At the end of 2023, the construction of the project (the whole) will be basically completed, and water storage will begin in March 2024, which will solve the agricultural irrigation of 362,000 mu in Yanyuan County, solve the drinking water problem of 140,000 people, and help the basic guarantee of water security in the region.
Key reservoir projects have grabbed the construction period and sprinted rapidly, and the construction of important irrigation areas has also been promoted simultaneously. In Yibin, the first phase of the Xiangjiaba Irrigation District North Main Trunk Canal Project Cat Tuo River bottom tunnel is accelerating the excavation, tunnel through the upper reaches of the Yangtze River rare and endemic fish national nature reserve important waters, in order to protect the ecology, the project in Sichuan water conservancy construction for the first time using a shield machine to cross the bottom of the MinJiang River.
Wei Huyan, head of the first shield machine of the engineering department of Sichuan Xiangjiaba Irrigation District Construction and Development Co., Ltd., said: Compared with blasting, the shield machine is more in line with the requirements of ecological environmental protection, and the safety factor is higher, and it can also save costs.
For the slag generated during tunnel boring, the project also specially customized the belt transfer system, which greatly improved the excavation efficiency.
Liu Yuqi, deputy chief engineer of the shield boring branch of the first phase of the first phase of the north main trunk canal of Xiangjiaba Irrigation District: In the normal propulsion process, we spend about three hours, using the way of belt conveyor transmission, we only need one and a half hours.
At present, the tunnel has completed 40% of the progress of excavation. According to the plan, the lower crossing of the Min River will be completed by the end of March, laying an important foundation for the next step of irrigation district construction. The Xiangjiaba Irrigation District Project is an important part of the "five horizontal and six vertical" water diversion and water replenishment ecological water network in Sichuan Province, with a planned irrigation area of 5.3 million mu, which can solve the water problem of 143 towns and more than 4 million rural people in the irrigation area after completion.