"Case" fine decoration work interface handover control

Today, we still use the typical cases on the spot to talk about how to control the work interface of one of the three core elements of fine decoration management.

Case 1: The embedded bottom box is seriously offset

Measures: The floor wall reserved switch socket bottom box and water supply pipe pressure groove, the floor slab drainage point reserved hole and drawing reserved size should be accurate, avoid change. Tiles or stones pasted on the kitchen and bathroom walls should be combined with decorative layout drawings to embed the bottom box in the middle of the plate.

"Case" fine decoration work interface handover control
"Case" fine decoration work interface handover control

Case 2: Leakage from the riser hole in the bathroom and balcony

Measures: Each bathroom caisson, each balcony to do closed water test, one household and one table record, civil engineering general contractor, supervision, Party A on-site confirmation, signature and archiving, resolutely avoid leakage of toilet and balcony riser holes.

"Case" fine decoration work interface handover control

Case 3: Defects in civil engineering handover

Measures: When hardcover receives the civil work surface, it must make a detailed inspection of the working surface, focusing on the empty drum of the plaster layer, the uneven base of the ceiling, the deviation of the ground elevation, the deviation of the verticality of the wall, the size of the head and other defects that cannot be eliminated by the fine decoration process, which will be rectified by the general contractor of civil engineering.

Case 4: No written transfer procedures

Measures: Party A takes the lead, supervises and follows up, each unit implements, and the handover of the work surface must go through the written transfer procedures.

"Case" fine decoration work interface handover control

Wall empty drum recording

"Case" fine decoration work interface handover control

Door and window work surface handover

Case 5: The protection of finished products is not in place

Measures: When bidding, the relevant content of the protection of finished products is written into the contract, and the quotation is included in the total price of the bidding, and reward and punishment measures are formulated.

"Case" fine decoration work interface handover control

Finished protection of doors and windows, railings, risers

Case 6: Leakage from the outer window

Measures: Test the water window by window, 1 pipe every 2 floors, supervise the water test process of the side station, and form a layer of data.

"Case" fine decoration work interface handover control

------