  On November 26, Wang Kailu, member of the party group and deputy director of the Guizhou Provincial Water Conservancy Department, was a guest of the "Online Interview" column jointly created by the Guizhou Provincial People's Government Network, the Contemporary Pioneer Network and the Tianyan News Client.

Online interview | Wang Kailu, deputy director of the Guizhou Provincial Water Conservancy Department: Guizhou has done this in the "Hundred Libraries Conference Battle" of water conservancy

Wang Kailu, member of the party group and deputy director of the Guizhou Provincial Water Conservancy Department, made a guest appearance for the "online interview". Photo by Pan Xianwan

  In order to speed up the solution of regional water shortages and engineering water shortages, Guizhou should carry out the "Hundred Reservoirs Conference Battle" of water conservancy. What is the progress? Wang Kailu made the following introduction.

  target

  During the "14th Five-Year Plan" period, on the basis of accelerating the construction of reservoir projects under construction, more than 100 new reservoirs were started and more than 100 reservoirs were completed.

  By the end of the "14th Five-Year Plan", the design water supply capacity of the province's water conservancy projects has increased from 12.6 billion m³ at the end of the "13th Five-Year Plan" to 15.5 billion m³, which is equivalent to adding the water supply capacity of 4 more Qianzhong water conservancy hubs, and basically solving the problem of regional water shortage and engineering water shortage in the province.

Online interview | Wang Kailu, deputy director of the Guizhou Provincial Water Conservancy Department: Guizhou has done this in the "Hundred Libraries Conference Battle" of water conservancy

Qianzhong Water Conservancy Hub Project Pingzhai Reservoir Lower Gate Storage Water Upstream Sancha River. Photo by Qin Gang

  progress

  Up to now, 15 backbone water source projects will be newly started in 2021 (of which 11 are in poverty alleviation counties), with a total storage capacity of 72.35 million m³, and an additional water supply capacity of 83.74 million m³ after completion; 67 water storage acceptances have been completed, and 38 have been completed and accepted. The annual water supply guarantee capacity is 563 million m³, and the province's water supply guarantee capacity reaches 13.174 billion m³. It is expected that 10 new reservoirs will be started by the end of the year.

  In terms of large reservoirs. The Qianzhong Water Conservancy Hub Project was basically completed and put into operation, the main canal was tested to Guiyang on January 28, 2018, the power station has been officially connected to the grid for power generation, and the construction of the water transmission section and branch canal from the exit of the Kaisong Tunnel to the Songbaishan Reservoir is currently being promoted.

Online interview | Wang Kailu, deputy director of the Guizhou Provincial Water Conservancy Department: Guizhou has done this in the "Hundred Libraries Conference Battle" of water conservancy

Liuzhi Special Zone Jiayan Reservoir, the left bank of the dam shoulder. Photo by Cao Jingjian

  The Jiayan Water Conservancy Hub and the Qianbei Northwest Water Supply Project passed the safety appraisal of water storage in the lower gate in August this year, and basically have the conditions for water storage in the lower gate.

  In addition, maling reservoir, Huangjiawan water conservancy hub project, Fengshan reservoir has passed the interception acceptance. On November 23 this year, the National Development and Reform Commission approved the feasibility study report of the Guanyin Reservoir Project and agreed to build the Guanyin Reservoir Project.

  Of the 422 small and medium-sized backbone water sources under construction, 244 engineering dams have completed the main construction (of which 184 have passed the acceptance of water storage) and 76 projects have carried out interception acceptance.