The Qingdao Oriental Eden Project will start full construction and be completed by the end of 2022

author:Al Jazeera

Peninsula all-media reporter Liu Hong correspondent Wang Xuan

From the Xiangmao River Bridge in Qingdao High-tech Zone overlooking the north bank of Jiaozhou Bay, not far from the riverbank, the Qingdao Oriental Eden Storm Forest Pavilion, which resembles a "broken hood", is hoisting the mesh shell structure, and the prototype of the venue has appeared, the silver-gray steel structure crisscrosses, the overall shape is smooth, and the scale is huge.

The Qingdao Oriental Eden Project will start full construction and be completed by the end of 2022

Overcoming difficulties, the construction of the four venues began in an all-round way

On November 6, at the construction site of the Qingdao Oriental Eden Project, two track cranes were separated on both sides of the Storm Forest Pavilion, and the net shell hoisting was promoted with high efficiency, and 50% of the total project volume was completed. The entrance to the north side of the Storm Forest Pavilion has completed the construction of the main structure, and the overall construction of the metal roof, glass curtain wall and integrated mechanical and electrical engineering is underway. The water extreme hall on the east side has entered the foundation construction stage of the main structure, and the basement of the water quality hall on the west side has also officially entered the foundation construction stage. The overall project construction has entered a new stage of comprehensive construction promotion, and the final charge has been launched towards the year-end goal of 2021.

Qingdao Oriental Eden Project is a world-class eco-cultural tourism destination with the theme of "water", the core area covers an area of about 400 acres, the scenic spot integrates cultural tourism, ecological tourism, entertainment experience, science education, seminar forum, social welfare and other content in one, a total of four areas are set up in the entrance area, water quality area, water extreme area, storm forest area, it is planned that before the end of December this year, the storm forest pavilion will complete the pillar unloading, as well as the deepening design of the internal source area and the test of the on-site lighting effect. Before the Spring Festival, the construction of the theme structure of the Water Extreme Pavilion and the main structure of the basement of the Water Quality Pavilion will be completed, and by the end of 2022, the project will be fully completed.

The Qingdao Oriental Eden Project will start full construction and be completed by the end of 2022

Forge ahead, ensure quality and promote construction

With the arrival of early winter, the project construction is about to face a harsh climatic environment, and the winds on the seaside will also adversely affect the construction of the project. "Sea breeze and temperature have a great impact on high-altitude work, and we must carry out wet work in advance before the cold winter comes, and complete the entire construction of the mesh shell structure." According to Wang Yonggang, general manager of Qingdao Oriental Eden Project, the construction period of the mesh shell structure is very tight, and under the premise of ensuring the safety of construction, the steel structure construction workers currently work two shifts, and the construction time is up to 20 hours. Concrete pouring and metal roofing construction are also currently working overtime. At the same time, the equipment investment is also in a saturated state, "on the basis of the 400-ton track crane, we added a 500-ton track crane, and now the two equipment are working at the same time, and the efficiency is greatly improved." ”

There are many factors affecting the progress of the project, in order to ensure the normal progress of construction, Qingdao Oriental Eden Project considers many factors such as project progress, quality, worker demands, epidemic prevention and control, etc., reverses the construction period, pre-orders materials and equipment in advance, ensures the normal operation of personnel and materials, and lays a stable foundation for the acceleration of the project.

According to Wang Yonggang, the internal design of the Water Extreme Pavilion and the Water Quality Pavilion that has just started construction has been basically completed, of which the Water Extreme Pavilion will create a comprehensive venue integrating interpretation and interactive entertainment, and set up groundwater science popularization displays. The Water Quality Pavilion will be mainly for young children, and a small theater will be set up to entertain and educate. After the completion of the project, citizens and tourists will feel the relationship between water and life in the scenic spot, and create a world-class cultural tourism destination.