With the "sky pump" car slender
The arm tube gushes out the last side of the concrete
CcCC Second Aviation Bureau undertakes
The key project of the southern section of the Xiangyang Ring Expressway
The main bridge of the thermal power plant special bridge was successfully completed
The southern section of the Xiangyang Ring Expressway project starts from Yushan Town, Xiangzhou District, passes through Lumen Mountain, crosses the Han River, 207 National Highway, and is connected to the South Outer Ring of Xiangjing Expressway in Yinji and Xiangjing Expressway in Xiangcheng District, with a total length of about 31.6km, using the first-class highway standard construction, two-way four-lane, and the design speed is 100 km / h.
Among them, the thermal power plant special bridge has a total length of 1.2 kilometers, and the main bridge construction section is located in the thermal power plant area, spanning 7 strands of the running railway section, with a length of 214 meters, a width of 26 meters, and a maximum span of 100 meters, which is the wave-shaped steel web continuous box girder bridge with the most spanning iron in Hubei Province.
During the entire construction of the main bridge, the railway under the bridge could not be stopped for a day, and the train traffic was huge. The average number of trains entering and leaving the country per day reached more than 30, and a train carrying coal passed through about half an hour, which became the biggest constraint restricting the construction period of the main bridge of the special bridge of the thermal power plant.
After many demonstrations and reviews, the project team finally chose to carry out the support of the permanent steel sheet pile of the deep foundation pit before the construction of the pile, so as to reduce the impact of the pile construction on the foundation by "wearing" the "protective clothing" for the foundation; during the construction process, the professional monitoring and measurement institution was requested to monitor and monitor the excavation of the pile sheet pile and the foundation pit all day long until the pile construction was completed.
A wave just flattened, and the waves rose again. The main 100-meter-span cantilever cast-in-place box girder is located directly above the seven rails, and the sparks generated during the construction of the welded corrugated steel web fall into the coal truck running on the rails, with unimaginable consequences. To this end, the project team has formulated a series of measures to solve the existing difficulties and security risks one by one. In view of the hidden dangers of Mars that may fall due to welded corrugated steel webs, a temporary protective shed was built above the rail, and the "hard hat" was "worn" for the train track to intercept Mars that may fall on the rail during the construction process; a special car was arranged to sprinkle water on the protective shed regularly, maintain the humidity of the protective shed, and completely extinguish Mars.
Two months after the official break into the thermal power plant area
The pouring of all the piles of the main bridge was completed 3 days in advance
The full width of the main bridge is realized