At 23:57 on the evening of October 31, the entire control project of the Xunfeng Expressway, the jinghe Special Bridge, was successfully completed for 908 days, which not only laid a solid foundation for the Xunfeng Expressway to achieve the scheduled completion and opening of traffic, but also marked that the construction of the Xunfeng Expressway project had entered the sprint stage in an all-round way.
The Jinghe Special Bridge starts from the village of Breakfast Inotou, Xinmin Town, Binzhou City, and then crosses the West Morning Highway, G342 National Highway, Jinghe River, Jingzhong Highway, and ends in Yaolian Village, Taiyu Town.
Jinghe Special Bridge is one of the control projects of the whole line of Xunfeng Expressway
The left side of the bridge is 1642 meters long
The total length of the right is 1682 meters
The main bridge is 736 meters long
The highest pier has a net height of 101.9 meters

The whole bridge is continuous steel box girder Helong
Construction of the bridge began in April 2019
After the dragon
The xunfeng expressway will be opened to traffic at the end of the year
Lay a solid foundation
Xunfeng Expressway, as an important part of the Heze-Baoji Liaison Line (G3511) in Shaanxi Province, is also a key construction project of the Liupanshan Concentrated Contiguous Poverty Alleviation Plan in the Extremely Poor Area, which is of great significance for improving the national highway network, driving the development of regional advantageous resources, accelerating the promotion of poverty alleviation in poor areas and the rapid development of the Guanzhong Tianshui Economic Zone.