Midea Rongke Roland View Project Progress At a Glance
Building 1 reality view
Progress of 1 building
■
The main construction is completed 1/3
Seven floors of wall pillar formwork support
Building 2 reality view
Progress of 2 buildings
The main construction is completed 2/3
Ten layers of discharge line, wall treatment, electroslag pressure welding
Building 6 reality
Progress of 6 buildings
Seven-story wall molds were removed; eight-layer wall columns were lashed with steel bars and erected inside
Building 8 reality view
Progress of 8 buildings
Six-layer wall column formwork molding
Building 10 reality view
Progress of 10 buildings
Seven layers of frame erection, roof paving
Building 11 reality map
Progress of 11 buildings
Nine floors are erected and the roof is paved
Building 12 reality map
Progress of 12 buildings
Seven floors of inner frame erection, roof paving, actual measurement and repair
Building 13 reality view
Progress of 13 buildings
The three floors are erected and the roof is paved