Recently, a number of road construction in Xixian New Area has ushered in new progress.

Jinghe New Town Longji Warehouse West Road Municipal Road Project

The latest progress in traffic road construction!

The project is located 90 meters east of Baomao Expressway, starting from the current origin avenue in the north, and setting up a line along the planned line to LONGi supporting road 2-origin 2nd road in the south. The total length of the road design is 1032.053 meters, and the width of the red line is 36 meters. The engineering involves majors such as roads, traffic, rainwater, sewage, sponge city, etc.

At present, the project has completed 25,000 cubic meters of spoiled earthwork, 80% of rainwater engineering, sewage engineering and water supply engineering, and 300 meters of roadbed foundation.

The second phase of the road network of Jinwan Science and Technology Innovation Zone

The latest progress in traffic road construction!

Including the first phase of the road network, the second phase of the road network, Fengyu No. 2 Road, and Fengwan No. 4 Road, there are 11 surface roads with a total length of about 9,900 meters. Among them, Fengwan No. 5 Road, Fengyu No. 1 Road, Jinke No. 3 Road (Fengwan No. 5 Road-Fengyu No. 1 Road) and the underground ring tunnel are co-constructed up and down, and Kewen Lane and the underground ring tunnel are horizontally co-constructed.

At present, the main lanes of Jinke 3rd Road (Fengyu 2nd Road-Fengwan 4th Road), Fengyu 1st Road (Jinke Road-Jinke 3rd Road), Fengwan 5th Road (Jinke 3rd Road-Jinke Road), Jinke 5th Road, Fengyu Road and Jinke Road have been connected, Fengyu 2nd Road (Jinke Road-Jinke 3rd Road) has been completed, 95% of the main lanes of Fengwan 4th Road have been paved, and the main lanes of Fengyu 1st Road (Jinke 3rd Road-Jinke 5th Road) have been paved.

Jinke Ring Tunnel

The latest progress in traffic road construction!

The project is in a circular direction, along Fengyu 1st Road, Jinke 3rd Road, Fengwan 5th Road and Kewen Lane, with 3 lanes in one direction and a total length of 1,683 meters on the main line. The ring tunnel is connected to the underground parking lot of the commercial buildings of the headquarters of many enterprises in the second phase of the Jinwan Science and Technology Innovation Zone, realizing the series connection and sharing of parking spaces on independent plots, which will provide convenience for the settled enterprises and surrounding citizens to travel after completion.

At present, the structure of the underground ring tunnel and the comprehensive pipe gallery has been basically completed, the bottom asphalt in the ring tunnel is 92% complete, the upper asphalt is 45% complete, the water supply and reclaimed water pipelines are 92% completed, and the progress of electrical, fire protection, intelligent and other system projects has been more than half.

The Qin Palace went all the way down the salty copper railway

The latest progress in traffic road construction!

The project is located at the intersection of Qingong 1st Road and Xiantong Railway, designed to use a 5-hole box bridge to cross the railway, the middle hole is a comprehensive pipe gallery channel, the box culvert is 8 meters wide, and two holes on each side are arranged with two-way 6 lanes and non-motorized lanes and sidewalks, with a box culvert width of 12 meters + 5.5 meters, and the construction content includes roads, lighting and traffic engineering.

At present, box culvert jacking, ramp construction and other operations are being carried out, and it is expected that after the box culvert jacking is completed at the end of the month, it will enter the road construction stage. After the completion of the salty copper railway project, Qingong 1st Road will go north through Metro Line 14 and the salty copper railway, and connect with Lanchi 3rd Road through the ramp, and the interchange project located on the south side of the railway has completed the asphalt paving and marking of the road, and has the conditions for opening to traffic.