Fast entry to ensure performance
01
Running into the field, the wind and fire from the beginning
Time is tight and tasks are heavy
The project team after receiving the task
With a high sense of responsibility and mission
Quickly get into a "combat state"
Running into the field
We are fully committed to ensuring that the project is performed to a high standard
02
Overcome difficulties and forge ahead to play a role
During the project approach phase
The project team is not afraid of difficulties
Have the courage to take responsibility
With the spirit of overcoming difficulties
Promote the implementation of various tasks of the project
There is no office space, and the office is allocated in containers
There is no canteen, so rent a demolished house to run a canteen
There are no dormitories, so we rent resettlement houses for accommodation
Complete the "home building" action in the early stage of the project with low cost and high efficiency
"Festival" does its best to practice low-cost construction
Lay a solid foundation for the project to sprint to the fullest
Escort the high standard performance of the project
03
External docking, multiple measures to win support
In order to ensure the smooth progress of the project
Make sure that there are no missing items in the relationship connection
Project design docking relationship tree diagram
From the application of documents to the entry of mechanical materials
The division of labor is clear and the responsibilities are clear
One-time inspection through the start of construction
Twice for night construction permits
Assist in the high standard performance of the project
04
Take the initiative and seize the opportunity for development
In order to ensure high standards and high quality performance
The project team actively understands
Territorial government documents, construction standards, inspection standards
The owner's construction period expectations, construction requirements, and inspection standards
Set the tone for construction
Promote the steady and far-reaching implementation of the project
05
Strive for the first position, and the speed of the three rounds casts the quality
Under clear standards and requirements
The project completed the temporary construction of the construction area and office and living area in 12 days
During construction
Heavy pollution weather warnings have been issued for a total of 49 days
The project is stitched and stitched
109 acres of field level were completed in 3 days
The construction of 438 supporting piles was completed in 15 days
450,000 square meters of earthwork were completed in 45 days
During the peak period, there were 15 excavators and 120 muck trucks in the field
The project currently has 56 precipitation wells
The construction of 438 supporting piles was completed
Earthwork and sand and gravel transportation, tower crane foundation construction
The construction of anti-floating anchors and other work are being carried out in an orderly manner
As of the end of the first quarter
The first and second nodes of the project were all completed ahead of schedule
The total construction period was advanced by 68 days
Owner-oriented to promote performance
The project team adheres to the "customer first" code of conduct
In-depth communication and accurate understanding of the needs of owners
The owner applies for state financial support
On January 31, the demand for the warehousing of the output value before March 8 was put forward
The warehousing standard is:
The erection of the basement formwork in the Q9 area was completed
The excavation of the first bid section is completed
The erection of the formal reinforcement room was completed
01
Unify your thinking and set your goals
To accomplish this goal
The project held a special meeting on output value storage
And in the weekly office meeting, team expansion meeting, production meeting
Set up the output value warehousing section
Determine the direction and goal
The division of labor is clear, and the pace is unified
02
Invert the plan, and correct the schedule
Sort out the progress of output value warehousing and form an inverted plan
Down-to-the-day detail
Preparation of output value warehousing scheme
Provide technical support for on-site construction
Convene daily meetings of all units
Determine the construction tasks for the second day
Critical tasks are corrected on a daily basis
03
Race against time, keep moving
Facing the Spring Festival holiday
Organize the subcontractors participating in the project in a timely manner
Find out the home address and willingness of the workers to return to their hometowns
Hold a mobilization meeting and sign a letter of responsibility
In the case of guaranteeing everyone's Spring Festival holiday
An additional 6 days of construction time were added
The "progress bar" of engineering construction has been continuously "loaded"
04
Focus on key points and implement precise policies
The earthwork volume of the project is about 450,000 square meters
It is required to be completed within one month
The construction period is tight and the task is heavy
Among them, there is a large amount of construction slag and white garbage in the topsoil
It is difficult to dispose of construction waste during the day
It can only be processed overnight
In order to provide a working face with sand and gravel units as soon as possible
The project handled two night construction permits
6 overnight excavations to ensure the performance of the contract
Received good reviews from the owners
Embody the spirit of competing for the first place in three rounds
05
Work hard and perform efficiently
After unremitting efforts
The project completed the output value warehousing node on March 8 with high quality
It has been highly praised by the owners
After four months of sincere cooperation
The owner took the initiative to elect the project department to apply for the honor of "competing for the first" in Wuhou District
And took the initiative to ask for a special issue on the safety of the Wuhou District Government
Team building and strong performance
Gather strength with unity, and create a great cause with struggle
The project has been on site since November 2023
It's not just about production fulfillment
Team building activities are also actively carried out
Promote first-class professional team building
01
Unite and cooperate to build dreams together
The project enhances the cohesion and centripetal force of the team in a variety of ways
Actively carry out internal training
Improve the professional skills and comprehensive quality of team members
Empower enterprises to develop high-quality development
Carry out theme group days, employee exchange seminars, etc. on a regular basis
Listen to the voices of employees and increase the enthusiasm of Jianye
Cohesion to build one
Credible, respectable, reliable, willing, daring, and promising
Professional team
02
A new starting point, a new journey, and we are committed to developing the Wuhou market
After four months of unremitting efforts
The project has won high recognition from the owner and the local government
And received a letter of commendation before the Spring Festival
The project team adheres to the corporate character of "dare to be the first in the world and always strive for the first".
The target of the output value warehousing node will be completed by March 8, 2024
And will take this as a starting point to actively explore the Wuhou market
Actively look for new opportunities for cooperation
Expand the influence in the Wuhou market
The project will continue to implement the requirements of the "Basic Management Improvement Year".
Continuously improve the level of project management and the overall quality of employees
Make unremitting efforts to create high-quality, high-efficiency and high-benefit projects
Make greater contributions to the high-quality development of the enterprise
Project Overview
The Wuhou New Material Industrial Park project is a key project in Sichuan Province and Chengdu City. It is located in Group 4 of Jiang'anhe Community, Jinhuaqiao Street, Wuhou District, Chengdu, and Group 2 of Shuangfeng Community, Tuoqiao Street. The total construction area is 132,748.86 square meters, of which the above-ground construction area is 75,200 square meters and the underground construction area is about 58,800 square meters. The project will be built into a modern industrial park with industrial agglomeration and innovation driven. It is of great significance to enhance the industrial structure of Wuhou District of Chengdu and promote regional economic development.
Source: Southwest Company of China Construction Third Bureau