Jianguo Xiaojing 3rd Road (Wei 1st Road to Shengli Street, Wei 2nd Road to Wei 5th Road) rain and sewage diversion reconstruction project construction announcement

author:Shunwang

The Jinan Urban and Rural Water Affairs Bureau plans to carry out the construction of rain and sewage diversion pipelines on Jianguo Xiaojing 3rd Road (Weiyi Road to Shengli Street, Weier Road to Weiwu Road) from 0:00 on April 28, 2024. In order to ensure the safety, orderliness and smoothness of road traffic during the construction period, the traffic organization plan during the construction period is now announced.

Jianguo Xiaojing 3rd Road (Wei 1st Road to Shengli Street, Wei 2nd Road to Wei 5th Road) rain and sewage diversion reconstruction project construction announcement

Jianguo Xiaojing 3rd Road (Weiyi Road to Shengli Street) section of the location map

Jianguo Xiaojing 3rd Road (Wei 1st Road to Shengli Street, Wei 2nd Road to Wei 5th Road) rain and sewage diversion reconstruction project construction announcement

Location map of Jianguo Xiaojing 3rd Road (Wei 2nd Road to Wei 5th Road).

First, the construction period

The planned start date is April 28, 2024, and the planned completion date is July 22, 2024, with a construction period of 85 days.

2. Transportation organization during construction

(1) Jianguo Xiaojing 3rd Road (Weiyi Road to Shengli Street)

The construction mode of night phased division of labor is adopted, and the whole is divided into two construction sections from east to west, and each construction section is constructed in stages.

1. Section 1 [Jianguo Xiaojing 3rd Road (Shengli Avenue - Fuxing Street)]

(1) Phase I

During the construction of the northern half of the sewage pipeline, the non-isolated guardrail of the northern half of the machine will be cancelled during the construction, and the 2.2m wide non-motorized lane and 0.8m wide sidewalk of the northern half will be fixed, and the remaining motorway width will be 6.5m and the southern half of the non-motorized lane will be 1.5m.

Jianguo Xiaojing 3rd Road (Wei 1st Road to Shengli Street, Wei 2nd Road to Wei 5th Road) rain and sewage diversion reconstruction project construction announcement

Cross-sectional design of the first phase of Jianguo Xiaojing 3rd Road (Shengli Avenue - Fuxing Street).

(2) Phase II

The central rainwater pipe of the construction road, during the construction period, all the isolation guardrails on the road are canceled, the 3m wide motorway in the middle of the road section is fixed, and the non-motorized lanes in the north and south halves are canceled, and the remaining motorway width is 7.2m.

Jianguo Xiaojing 3rd Road (Wei 1st Road to Shengli Street, Wei 2nd Road to Wei 5th Road) rain and sewage diversion reconstruction project construction announcement

Cross-sectional design of the second phase of construction of Jianguo Xiaojing 3rd Road (Shengli Avenue - Fuxing Street).

(3) The third stage

During the construction of the southern half of the sewage pipeline, the non-isolated guardrail of the southern half of the machine will be cancelled during the construction, and the 2.2m wide non-motorized lane and part of the motorized lane in the southern half will be fixed, as well as the 0.8m wide sidewalk, and the remaining motorway width will be 5.8m, and the northern half of the non-motorized lane will be 2.2m.

Jianguo Xiaojing 3rd Road (Wei 1st Road to Shengli Street, Wei 2nd Road to Wei 5th Road) rain and sewage diversion reconstruction project construction announcement

Cross-sectional design of the third phase of Jianguo Xiaojing 3rd Road (Shengli Avenue - Fuxing Street).

2. Section 2 [Jianguo Xiaojing 3rd Road (Fuxing Street-Weiyi Road)]

(1) Phase I

Construction of rainwater pipes, during the construction period to cancel the parking spaces on both sides of the road, fixed the middle of the fenced road section 3m wide road, the remaining road 7m, road remodeling, non-motorized vehicles borrowed sidewalks to pass.

Jianguo Xiaojing 3rd Road (Wei 1st Road to Shengli Street, Wei 2nd Road to Wei 5th Road) rain and sewage diversion reconstruction project construction announcement

Cross-sectional design of the first phase of construction of Jianguo Xiaojing 3rd Road (Fuxing Street-Weiyi Road).

(2) Phase II

During the construction of the sewage pipeline on the south side, the parking spaces on both sides of the road will be cancelled during the construction, and the 2.2m wide road and 0.8m wide sidewalk on the south side of the fenced road section will be fixed, and the remaining 7.8m road will be remodeled. Non-motorized vehicles borrow sidewalks to pass.

Jianguo Xiaojing 3rd Road (Wei 1st Road to Shengli Street, Wei 2nd Road to Wei 5th Road) rain and sewage diversion reconstruction project construction announcement

Cross-sectional design of the second phase of Jianguo Xiaojing 3rd Road (Fuxing Street-Weiyi Road).

Jianguo Xiaojing 3rd Road (Wei 1st Road to Shengli Street, Wei 2nd Road to Wei 5th Road) rain and sewage diversion reconstruction project construction announcement

Schematic diagram of the construction layout of the construction section of Jianguo Xiaojing 3rd Road (Weiyi Road to Shengli Street).

(2) Jianguo Xiaojing 3rd Road (Wei 2nd Road - Wei 5th Road)

The construction mode of night phased division of labor is adopted, and the whole is divided into three construction sections for construction one by one.

1. Section 1 [Jianguo Xiaojing 3rd Road (Wei 5th Road - Wei 4th Road)]

Adopt the construction mode of night division period. The construction of the rain and sewage pipe groove is 3.5m on the south side of the road. During the construction period, the road was reshaped in a cross-section, with a 3.25m wide non-mixed traffic lane from east to west and a 3.25m wide motorway from west to east.

Jianguo Xiaojing 3rd Road (Wei 1st Road to Shengli Street, Wei 2nd Road to Wei 5th Road) rain and sewage diversion reconstruction project construction announcement

Jianguo Xiaojing 3rd Road (Wei 5 Road - Wei 4 Road) construction cross-sectional design

2. Section 2 [Jianguo Xiaojing 3rd Road (Weisi Road - South Gate of the Shandong Provincial Commission for Discipline Inspection of the Communist Party of China)]

(1) Phase I

The construction of the sewage pipeline on the south side, the night construction mode is adopted, the south side of the motorway is enclosed for 3m, the road is reshaped during the construction, the non-motorized road on the north side is changed to a 3.5m wide motorway from east to west, and the machine is not mixed driving, and the right lane from east to west is changed to a 3.5m wide motorway from west to east.

Jianguo Xiaojing 3rd Road (Wei 1st Road to Shengli Street, Wei 2nd Road to Wei 5th Road) rain and sewage diversion reconstruction project construction announcement

Cross-sectional design of the first phase of construction of Jianguo Xiaojing 3rd Road (Weisi Road - South Gate of the Shandong Provincial Commission for Discipline Inspection of the Communist Party of China).

(2) Phase II

Construction of the north side of the rainwater pipe, fixed enclosure of the north side of the road non-motorized lane 3m, non-motorized vehicles through the motorway for traffic, the use of machine non-mixed traffic.

Jianguo Xiaojing 3rd Road (Wei 1st Road to Shengli Street, Wei 2nd Road to Wei 5th Road) rain and sewage diversion reconstruction project construction announcement

Cross-sectional design of the second phase of construction of Jianguo Xiaojing 3rd Road (Weisi Road - South Gate of the Shandong Provincial Commission for Discipline Inspection of the Communist Party of China).

3. Section 3 [Jianguo Xiaojing 3rd Road (South Gate of the Communist Party of China Shandong Provincial Commission for Discipline Inspection - Weier Road)]

(1) Phase I

The construction of the sewage pipeline on the south side adopts the night construction mode, encloses the straight left motorway on the south side by 3m, and the road is reshaped during the construction, and the left-turn road from west to east on the south side is changed to a straight left lane from west to east, with a lane width of 3.3m.

Jianguo Xiaojing 3rd Road (Wei 1st Road to Shengli Street, Wei 2nd Road to Wei 5th Road) rain and sewage diversion reconstruction project construction announcement

Jianguo Xiaojing 3rd Road (South Gate of the Communist Party of China Shandong Provincial Commission for Discipline Inspection - Weier Road) construction cross-sectional design of the first phase

(2) Phase II

The rainwater pipe on the north side of the construction adopts the night construction mode, encloses the motorway on the north side by 3m, and the road is reshaped during the construction, and the left-turn motorway on the south side from west to east is changed to a 3.8m wide motorway from east to west.

Jianguo Xiaojing 3rd Road (Wei 1st Road to Shengli Street, Wei 2nd Road to Wei 5th Road) rain and sewage diversion reconstruction project construction announcement

Cross-sectional design of the second phase of Jianguo Xiaojing 3rd Road (South Gate of the Communist Party of China Shandong Provincial Commission for Discipline Inspection - Weier Road).

Jianguo Xiaojing 3rd Road (Wei 1st Road to Shengli Street, Wei 2nd Road to Wei 5th Road) rain and sewage diversion reconstruction project construction announcement

Jianguo Xiaojing 3rd Road (Wei 5 Road - Wei 4 Road) construction section construction layout schematic diagram

Jianguo Xiaojing 3rd Road (Wei 1st Road to Shengli Street, Wei 2nd Road to Wei 5th Road) rain and sewage diversion reconstruction project construction announcement

Jianguo Xiaojing 3rd Road (Wei 4 Road - Wei 2 Road) construction section construction layout schematic diagram

3. Detour plan

During the construction period, it can be diverted or detoured through roads such as Jingqi Road, Jingba Road, Jingshi Road, Wei 2 Road, and Wei Yi Road.

Vehicles and pedestrians are prohibited from entering the construction site during construction; At that time, traffic diversion signs will be set up along the construction section, please pay attention to the on-site traffic signs for passing vehicles and pedestrians, follow the signs to pass, and pay attention to safety, strengthen wait-and-see, and pass slowly. Please actively cooperate with the majority of motor vehicles, non-motor vehicle drivers and pedestrians and obey the command of the on-site management personnel. During the construction period, if the on-site traffic conditions change and the traffic organization measures need to be adjusted, a separate announcement will be issued. During the construction period, we apologize for any inconvenience caused to residents and units along the line.

The announcement is hereby made.

Jinan Urban and Rural Water Bureau

April 24, 2024