The latest progress of the planning of Wuhan Baishazhou Xianglong Xincheng Primary School

"I am the owner of Zhongjian Yipin Hongtai Yuejiang Mansion, when I bought a house before, I said that the primary school next to it will soon be completed and put into use, and now it has been a few years, I want to ask when Xianglong Xincheng Primary School can be completed and put into use, which is the contractor, and what stage is the current construction progress. "

▲A map of Wuhan Baishazhou planning (platform exclusive)

Hongshan District Education Bureau Housing Instrument Management Station responded

The handling situation is now replied as follows: Questions about the construction progress of the new project of Xianglong Xincheng Primary School. The new project of Xianglong Xincheng Primary School started on March 20, 2023. The basement floor is currently under construction and is expected to be put into use in September 2025.

▲Wuhan Baisha 5th Road, Baishazhou Xianglong Xincheng Primary School HS1 Primary 8 (i.e., Yangtze River Primary School) planning location

The opening of this primary school in Baishazhou has been decided

▲Wuhan Baisha 5th Road, Baishazhou Xianglong Xincheng Primary School HS1 Primary 8 (i.e., Yangtze River Primary School) planning location

Zhangjiawan plot at the south gate of Baishazhou, Wuhan

Xianglong Xincheng Planning Primary School HS1 Primary 8 Project

The total construction area of the project is 22,110.11 square meters, including 11,661.10 square meters of above-ground construction area and 10,449.01 square meters of underground construction area.

The above-ground construction area includes: 10,058.77 square meters of teaching complex building (including 619.61 square meters of overhead floor area on the first floor), 1,602.30 square meters of wind and rain playground/multi-functional lecture hall (442.04 square meters of multi-functional lecture hall; 1,160.26 square meters of wind and rain playground construction area).

The underground construction area is 9,316.18 square meters for the underground garage and 1,132.83 square meters for the underground bicycle garage. Supporting the construction of indoor and outdoor water supply and drainage, power supply and distribution, HVAC, fire protection, weak electricity and other public works, as well as outdoor sports grounds, runways, roads, greening, etc. The investment amount of the bidding project (10,000 yuan): 13238.42, the planned construction period (calendar days): 500

The opening of this primary school in Baishazhou has been decided