Electrical, water supply and drainage installation project delivery standard legend

author:Mechanical and electrical world

Foreword

In order to improve the construction quality level of the installation project and realize the standardization and standardized management, the company's technical quality department organizes and compiles the "Installation Division Project Delivery Standard" (trial version), as a guiding document for the construction of the installation company, and the subordinate projects must be implemented with reference.

The "Installation Branch Project Delivery Standard" (trial version) is compiled by the Technical Quality Department in accordance with relevant national laws, regulations, industry standards, operating procedures, as well as summarizing the management experience and acceptance standards accumulated by our company in the past, and drawing on the advanced management mode of each construction unit of our company's construction projects.

This standard is explained, supplemented, modified and updated by the Technical Quality Department.

Basis for compilation

1. Code for Quality Acceptance of Building Water Supply and Drainage and Heating Engineering GB50242-2002

2. Code for Acceptance of Construction Quality of Building Electrical Engineering GB50303-2002

3. Code for Acceptance of Construction Quality of Ventilation and Air Conditioning Engineering GB50243-2002

4. Code for Quality Acceptance of Building Decoration and Decoration Engineering GB50210-2001

5. Code for Construction and Acceptance of Building Electrical Lighting Devices GB50617-2010

6. Code for Construction and Quality Acceptance of Building Lightning Protection Engineering GB50601-2010

7. Implementation Guide for Household Acceptance of Chongqing Residential Engineering Quality (No. 2)

8. Relevant construction design drawings

Water supply and drainage works

Basic Requirements:

1. The water supply pipeline is installed firmly, horizontally and vertically, the components are complete, the interface is tight and there is no leakage, the bracket is correctly selected, the installation is firm, the spacing is uniform, the surface of the pipeline is clean and no scratches, the functional test is qualified, and the pipeline identification is correct.

2. The drainage pipeline is installed firmly, the slope direction is correct, the parts are complete, the interface is tight and there is no leakage, the pipeline is smooth and no blockage, the bracket is correctly selected, the installation is firm, the spacing is uniform, the floor drain is selected correctly, the water seal meets the requirements, the surface of the pipeline is clean and no scratches, the functional test is qualified, and the pipeline identification is correct.

3. The elevation of the embedded casing is consistent, the nozzle is smooth, the height of the plate surface of the casing through the floor slab is consistent, and the anti-corrosion coating is uniform.

4. The pipeline is tightly insulated and sealed, with no gaps and voids, and the surface is smooth.

5. The sprinkler pipeline is reasonably arranged, neatly arranged, in rows and lines, the parts are complete, the interface is tight and there is no leakage, the bracket is correctly selected, the installation is firm, the spacing is even, the surface of the pipeline is clean and no scratches, the functional test is qualified, and the pipeline identification is correct

6. The equipment is installed and arranged reasonably, arranged neatly, fixed firmly, and the elevation is consistent, and the operation is normal, safe and reliable.

7. The paint of the pipe and bracket is evenly painted, without falling, pinholes, bubbles, and the color is consistent.

8. The appliance is installed firmly, and the joint with the wall and ground is tight and parallel, the surface of the appliance is clean and free of pollution, damage and leakage, and the bracket is firmly fixed.

Electrical, water supply and drainage installation project delivery standard legend

Expansion joints must be provided on each layer of the plastic drainage pipe. Where the indoor diameter ≥ 110mm is exposed to the drainage plastic riser through the floor slab, a fire arresting ring should be set according to the design requirements.

Electrical, water supply and drainage installation project delivery standard legend
Electrical, water supply and drainage installation project delivery standard legend
Electrical, water supply and drainage installation project delivery standard legend
Electrical, water supply and drainage installation project delivery standard legend

The verticality error of the toilet drainage riser is ≯3 mm per 1 m, and the total length (more than 25 m) is ≯ 15 mm. Checkpoints are installed every other floor, but must be installed at the lowest level and at the top level with sanitary equipment. The center of the inspection entrance is 1m away from the decorative floor. The bottom distance of the drainage main transverse pipe is 30-50 mm from the ground, and the total length of the main transverse pipe is 300-400 mm

Electrical, water supply and drainage installation project delivery standard legend

When the water supply pipe is installed in the corridor and bedroom, it should be as close to the hidden place as possible, and the bracket should be installed after the coating is completed. The brackets should be installed firmly, and the distance between the brackets should meet the requirements of the specification. The brackets of hot and cold water pipes should be flush. The vertical and horizontal bending of the pipe is ≯ 1.5 mm per meter, and the total length (more than 25 m) is ≯ 25 mm.

Electrical, water supply and drainage installation project delivery standard legend
Electrical, water supply and drainage installation project delivery standard legend

The spacing of pipes cannot change when they cross and change direction.

Electrical, water supply and drainage installation project delivery standard legend
Electrical, water supply and drainage installation project delivery standard legend

The pipeline layout is reasonable and the identification is clear

Electrical, water supply and drainage installation project delivery standard legend

The living balcony pipes are arranged with the same spacing, and the brackets meet the requirements of the code

Electrical, water supply and drainage installation project delivery standard legend

The surface of the floor drain should be 2~3mm lower than the finished ground without pollution, and the floor drain grate should be easy to remove.

Electrical, water supply and drainage installation project delivery standard legend
Electrical, water supply and drainage installation project delivery standard legend
Electrical, water supply and drainage installation project delivery standard legend
Electrical, water supply and drainage installation project delivery standard legend

The spacing of buried water supply pipes is 200-300mm, and the identification is clear

Electrical, water supply and drainage installation project delivery standard legend

The layout of the garage pipes is reasonable, the spacing is uniform, the signs are eye-catching, the brackets are firm and reliable, and there is no cross-contamination.

Electrical, water supply and drainage installation project delivery standard legend

The water meters are neatly arranged, the pipes are horizontal and vertical, and the signs are clear

Electrical, water supply and drainage installation project delivery standard legend

The sanitary ware is arranged symmetrically in the center, and the slope direction is correct and pollution-free

Installed in rows of urinals, the elevation is consistent, evenly arranged, neat, and glued at the joints of the wall

Electrical Engineering

Basic Requirements:

1. The indoor strong and weak electric box is firmly installed, the position is correct, the parts are complete, the box opening is suitable for the diameter of the conduit, and the box cover is close to the wall surface without scratches and bruises.

2. The wiring in the box is neat, and there is no twisting phenomenon. The cross-sectional area of the wires pressed on both sides of the screw under the washer is the same, and there are no more than 2 wires connected on the same terminal, and the parts such as the anti-loose washer are complete and the grounding is reliable.

2. The switch in the box is flexible and reliable, the wiring in the box is neat, the circuit number is complete, and the identification is correct.

3. The embedded lamp head box and the cover plate of the transfer box are installed in place, the elevation is consistent, and the marking is clear, and the embedded wall (beam) casing nozzle is smooth, the pipe is clean, the elevation is consistent, and the mark is clear.

4. The equipotential connection of the metal parts or parts of the toilet should be connected with the equipotential connection branch wire with special wiring bolts, and there should be identification, the nut at the connection should be fastened, and the anti-loosening parts should be complete.

5. The socket and switch are installed firmly, the board surface is upright, and the arrangement is neat; there is no gap around, the surface is smooth and clean, and there is no scratch; the wire is separated by color, phase sequence, and wiring is correct; PE wires are not connected in series between sockets.

6. The lamps and lanterns are firmly installed, the lamps and accessories are complete, the surface is smooth and clean, and there are no defects such as damage, deformation, and lampshade damage, and when the height from the ground is less than 2.4 meters, the lamps are grounded or connected to zero reliably.

7. The bridge has complete components, clean surface, no deformation, firm connection, accurate crossing, reliable grounding, reasonable bracket setting, firm fixation, strict fireproof sealing and smooth surface at the wall and floor.

Electrical, water supply and drainage installation project delivery standard legend

The lower end of the indoor strong and weak current box is 1.8m away from the ground, and the lower end is flush.

The distance between the two boxes is 100mm, and the verticality error of the box is <3‰

Electrical, water supply and drainage installation project delivery standard legend

The installation height of the video phone and the lighting switch in the living room is 1.3m away from the ground, and the lower end is flush.

The distance between the two is 100mm, and the verticality error is <3‰

Electrical, water supply and drainage installation project delivery standard legend
Electrical, water supply and drainage installation project delivery standard legend

Toilet equipotential connection of its metal parts or parts, there should be a special wiring bolt and equipotential connection branch connection, and there is identification, the connection nut is fastened, and the anti-loosening parts are complete.

Electrical, water supply and drainage installation project delivery standard legend

The bridge and cable are arranged reasonably, neatly and beautifully, and the circuit number is complete and the marking is correct

Electrical, water supply and drainage installation project delivery standard legend
Electrical, water supply and drainage installation project delivery standard legend
Electrical, water supply and drainage installation project delivery standard legend
Electrical, water supply and drainage installation project delivery standard legend

The electrical piping bracket is reasonable and firm, the pipeline is straight, the anti-corrosion is complete, and there is no pollution

Electrical, water supply and drainage installation project delivery standard legend

The switches are neatly arranged, flat and firm, with no gaps around and the same elevation.

Electrical, water supply and drainage installation project delivery standard legend

The lightning protection belt of the roof is smooth and straight, and the weld is full without omission

Electrical, water supply and drainage installation project delivery standard legend
Electrical, water supply and drainage installation project delivery standard legend