The main construction procedures of the clean plant

A.0.1 The construction and installation content of the clean plant should mainly include building decoration, purification air conditioning system, power utilities and safety facilities and various piping and wiring; the construction and installation of the clean plant should be determined according to the specific engineering characteristics and use functions, and the installation of relevant production process equipment and the installation of secondary piping and wiring should also be arranged.

A.0.2 In the construction and installation of the clean plant, it should be determined according to the specific engineering situation, complexity and other factors, and if necessary, the secondary clean room decoration design or the secondary piping and wiring design should be carried out.

A.0.3 When the construction and installation of the clean plant, all professions and multiple types of work should cooperate closely, and the construction installation program and plan progress should be formulated according to the actual situation of the specific project, and the construction of the clean plant should be completed step by step. The main construction procedures of the clean plant are shown in Figure A.0.3.

Purification knowledge sharing + resumption of work for 28 days (main construction procedures of clean plant in dust-free workshop)

Figure A.0.3 Illustration of the main construction procedures of the clean plant