laitimes

In 2021, the road hardening and water conservancy bridge projects in Fangping Village, Baisha Village and Daobu Village in Yacha Town

1. Tender conditions

The 2021 Road Hardening and Water Conservancy Bridge Project (Project No.: hizw20210922007) in Fangping Village, Baisha Village, Yacha Town, 2021,02007 has been approved by the Administrative Examination and Approval Service Bureau of Baisha Li Autonomous County with Baixing Approval [2021] No. 325, and the bidder (project owner) is Baisha Li Autonomous County Urban and Rural Construction Investment Co., Ltd., the construction funds come from the government, and the project contribution ratio is 100.00% of the government investment. The project has been qualified for bidding, and the project is now open for bidding.

2. Project overview and scope of bidding

2.1 Construction site: Fangping Village, Baisha Village and Daobu Village, Yacha Town, Baisha County

2.2 Project content and scale: The total hardening length of the road surface of the project is 4823.165m, and the total area is 15565.27㎡. The construction content includes road pavement hardening project and new buried water supply pipelines, the specific construction content is as follows: Fangping Village Committee: hardening the road surface, the road hardening length is 2295.097m, the width of the road surface is 3.0m; the new inclined retaining wall is 1, 2m high and 20m long; the new 2 1-1.5*10 cover plate ming culvert, the culvert length is 12m; the new 3 places are 1-0.75 circular pipe culverts, with a total length of 18 m; 6 new small signs; 4 new warning columns. Baisha Village Committee: Hardening of the road surface, the hardening length of the road is 1069.557m, the width of the road surface is 3.5m; the new inclined retaining wall is 3, the height is 2.5m, the total length is 40m; the new 2 cover plates are clear culverts (3-4.0*2.5 and 1-1.5*1.0), with a total culvert length of 12 m; the new 5 1-0.75 circular pipe culverts, with a total length of 30 m; the new small sign boards are 6; and the new warning columns are 40. Daobu Village Committee: Hardening and repairing the road surface, the hardening length of the road is 1408.511m, and the length of road damage modification is 50m. The width of the pavement is 3.0/3.5m; the demolition and reconstruction of 2 cover covers (1-3.0*2.5 and 1-3.0*3.0), with a total length of 8.5m; a new 1-0.75 round pipe culvert, with a total length of 6m; 3 new small signs; 8 new warning columns. The tender control price was $4,973,006.41.

2.3 Planned Duration (Service Period): 170 calendar days.

2.4 Lot Division:

2.5 Scope of tender:

2.6 Quality requirements:

Read on