"People sit at home, and the certificate comes from the line"

author:Hefei view
"People sit at home, and the certificate comes from the line"

In the past, in the field of engineering construction projects, a project "hundreds of matters to apply, stamp dozens of departmental seals, multi-head running slowly" and other prominent problems, so that the road to engineering construction enterprises and handlers to apply for the project is quite tortuous.

Li Cancan, who works in the Jade Mansion Project in Baohe District, has participated in many project construction projects over the years and has a deep understanding of this. In the past, she had to prepare a large number of materials offline, and then carry these materials between various window units, which was time-consuming and laborious.

"People sit at home, and the certificate comes from the line"

"After the system was built, a comprehensive window was set up, which was very convenient! For example, in the process of processing the construction permit, the original must carry a variety of paper materials to the relevant window to handle, if the five-party responsible subject in the field, the time delay is relatively long, now, only need to scan the original at home, you can handle it online, basically realized 'people sitting at home, the certificate comes from the line'. This saves a lot of time for the construction unit and speeds up the construction progress. Li Cancan said.

"People sit at home, and the certificate comes from the line"

There are many links, many departments, many levels, and it takes a long time... In the face of the difficulties, blockages and pain points in the approval process of these engineering projects, in April 2019, the city set up a high-level reform group to adopt an efficient mechanism of "one lead, one platform, parallel approval, and time-limited completion" to build a management platform for the approval and management of engineering construction projects and promote the reform of the approval system for engineering construction projects.

"People sit at home, and the certificate comes from the line"

"The platform covers four subsystems: online office hall, intermediary service hall, approval management system and efficiency supervision system, to meet the needs of the approval process of engineering construction projects."

Wu Yan, a third-level director of the Administrative Examination and Approval Department of the Municipal Urban and Rural Construction Bureau, said that in view of the long approval cycle of engineering construction projects, the large number of examination and approval departments involved, and the complexity of professional types, especially the characteristics of the huge number of examination and approval matters, the city has adopted five measures of "reduction, release, merger, transfer, and adjustment" to compress and streamline the examination and approval matters.

Break down departmental information barriers and reinvent the approval process. The city has established a unified engineering construction project management platform in the city, opened up 10 system approval service channels, so that the applicant (construction unit) can jointly achieve "the coordination of application materials, the coordination of approval opinions, the time-controlled timekeeping of approval, and the sharing of approval results" through a platform. 167 examination and approval departments and 568 examination and approval matters at the municipal and 13 counties (cities) and development zones have been declared and approved on the same system.

"People sit at home, and the certificate comes from the line"
"People sit at home, and the certificate comes from the line"

The blade is inward and self-pressurized. Our city also took the lead in the province to realize the zero form one-click operation of the construction permit stage, to solve the coordination problem of approval supervision and business supervision; complete the registration of the participation in the inspection matters at the completion and acceptance stage, solve the problem of multi-head communication and pre-examination of enterprise declaration and acceptance; take the lead in introducing discipline inspection and supervision intervention, solve the problem of difficult approval and supervision, and form the "Hefei model" of the reform of the approval system for engineering construction projects.

In addition, the efficiency of the approval of various construction projects in our city has been greatly improved, and the original 141 examination and approval items have been reduced to 60 items, with a reduction rate of nearly two-thirds; the time limit for the approval of engineering construction projects has been reduced from 200 working days to 70 working days, and the time limit for compression has reached 65%; the number of cases has gradually increased, and the number of overdue cases has been continuously reduced. By June 2021, more than 20,000 online declarations have been processed, and the number of cases has ranked first in the province.