The installation and construction of concrete cement pipes in Guangzhou mainly has the following links:

author:Huajian cement products in Guangdong Province

1. Design construction drawings. Before the installation of the concrete cement pipe in Guangzhou, the construction drawings for the installation of the concrete cement pipe in Guangzhou should be designed on the basis of the actual situation of the production plant, and the systematicness, effectiveness, coordination and integrity of the construction drawings should be guaranteed.

2. Inventory work before installation, before the formal installation of Guangzhou concrete cement pipe, first carry out unpacking inventory, detailed inspection and inventory of Guangzhou concrete cement pipe, and carefully register the inspection results.

3. Equipment positioning, that is, the foundation release line, to demarcate the installation of the reference line, the relevant building elevation line, edge line, axis and equipment layout drawings for comprehensive consideration.

4. The equipment is in place, that is, through various handling, hoisting, etc., the concrete cement pipe equipment that needs to be installed is transported to the designated location and prepared for installation.

5. Adjust and test the accuracy of equipment, mainly including precision measurement technology, error analysis, etc., to measure the accuracy of some shapes and the accuracy items of all positions to ensure the quality of the project.

6. The device is fixed. It is necessary to fix some concrete cement pipe equipment with large vibration, high speed and heavy weight on the basis of equipment.

7. For the overall concrete cement pipe equipment that exceeds the anti-rust preservation period, the cement pipe making equipment that has been dismantled should be disassembled for cleaning and then assembled.

8. After the equipment is installed, the concrete cement pipe equipment should be refueled and lubricated, and the concrete cement pipe equipment should be repeatedly debugged and tested for a certain period of time, and after confirming that there is no problem, it can apply to the relevant departments for acceptance.