The section from Mengning to Taole on Provincial Highway 302 is being rebuilt

author:Pingluo County Rong Media Center

Video loading...

Video Production: Si Bingxin

In recent days, the reconstruction project of the Mengning boundary to Taole section of provincial highway 302 is being carried out in an orderly manner, and it is expected to reach the conditions for opening to traffic in mid-October.

In early autumn, the heat does not subside. At the reconstruction site of the Mengning boundary to the Taole section of the provincial highway 302 line, the paving area, the crushing area, the testing area and other areas are clearly divided. Workers and machinery came together, busy paving cement to stabilize the gravel base.

Project leader Wei Shiqian introduced: "The reconstruction project of the Mengning boundary to Taole section of the provincial highway 302 line has completed the subgrade project and the bridge and culvert project since the construction in mid-May, and now the cement stabilized gravel base layer paving work is carried out. ”

It is understood that the old road surface of the Mengning boundary to the Taole section of the provincial highway 302 is a three-level highway with a width of 6.5-7m, the driving speed is not high, the local road surface has different degrees of diseases, the traffic capacity is low, and it has not adapted to the needs of the local economic development, in order to improve this situation, Pingluo County implemented the reconstruction project of the Mengning boundary to the Taole section of the provincial highway 302 line, starting from the Mashishan near the boundary of Ningmeng Province, and connecting the Inner Mongolia section of the Tao'e Highway, with a total length of 8.15 kilometers and an investment of more than 41 million yuan.

The project is designed according to the secondary highway standard, with a design speed of 80km/h, two lanes in both directions, a road width of 10.5m, and a design flood frequency of 1/50 of the subgrade and culvert. Asphalt concrete pavement, according to the design of the plane and longitudinal section, fully consider the reinforcement and utilization of the old pavement.

The implementation of the project will further improve the road traffic system in the region, improve the quality and level of highway services, improve transportation conditions, promote regional economic development, and accelerate the development of global tourism.

"At present, 60% of the winning bid amount has been completed, and in mid-October we will reach the conditions for opening to traffic." Project leader Wei Sexqian said.

Source: Pingluo County Rong Media Center

Reporter: Duan Bo Si Bingxin

Editor: Ma Shengwen

Editor-in-Charge: Wang Gang