Source: People's Daily - Guizhou Channel Original draft
In order to ensure the landing of the rural network upgrading and transformation project, on the main battlefield of the upgrading and transformation of the rural network in Chengheng County, the party committee of the Chengheng Power Supply Bureau attaches great importance to it, and has set up a special class for the short board and difficulty of the party committee of the Chengheng Power Supply Bureau - the infrastructure distribution network project to put into operation, promote the smooth operation of the distribution network infrastructure project of the Chengheng Power Supply Bureau, improve the reliability of power supply and solve the problem of low voltage and heavy overload in distribution. From strengthening the project management of the rural network construction and upgrading project, to intensively promoting the implementation of the project, combing the inverted schedule, seizing the time, overcoming all difficulties, and resolutely winning this battle. From multiple dimensions such as safety, quality and progress, we should grasp the whole process of continuous construction and projects under construction. With high-quality requirements, we will ensure that the project is completed on time and on schedule, and help the rural revitalization construction of Chengheng County.
Overcome Difficulties Persist in The Original Intention of Construction Firmly believe that Qingshan will not relax
"The ramp here is steep, straight up and down, you must pay attention to your own safety during the transportation of materials." In the 10kV Yama line transformation project of the continuation project, Wang Dingcheng, deputy manager of the project management center of the Chengheng Power Supply Bureau, went to the construction personnel at the construction site and paid attention to their own safety when transporting materials to the top of the slope.
"From the foot of the slope to the top of the slope is all covered by trees, here is the only power channel, the road is rugged and steep, the personnel up the mountain is very difficult, in addition to the materials to transport to the top of the mountain is even more difficult, but in order to connect this line as soon as possible, we take the way of manpower and machinery to transport the power grid project construction materials to the top of the mountain, rush to complete the erection and elimination work before the power outage plan, and put the project into operation as soon as possible." The head of the construction team implementing the project said.
In Chengheng County, there are many more construction projects to such a power grid, with many points and a wide range of points, and the time is urgent. In order to put the new project into use as soon as possible, the high-fault lines that have been operating for a long time in the past will be eliminated to ensure that the reliability of power supply is improved. Everyone overcame all difficulties and tried their best to concentrate on overcoming this "hard bone."
Up to now, the number of sub-projects put into production has dropped from the original 169 to 33, and the management personnel at all levels and on-site construction personnel of the bureau still have an average of more than 60 people per day, 5 2, white plus black, war sunny days, war rainy days, fighting at the construction site.
Gather elites to fight a decisive battle, bravely undertake the mission of construction, and do not break the oath of Loulan and not return it
During the period of power grid attack, in order to ensure the efficient and effective advancement of project construction, the Chengheng Power Supply Bureau took the initiative to take the lead, actively strengthened the linkage between government and enterprises, held a power grid construction promotion meeting with the county party committee and county government, and issued an emergency notice on effectively doing a good job in the investigation and rectification of the hidden dangers of the "tree obstacle" of the power line channel in the county, creating a good external environment for the construction of the project.
"This battle to tackle tough problems is the top priority of our work now, and we will resolutely obey the decision of the party committee, do a good job in leading the party members to charge forward, and resolutely win the battle to overcome the tough end." Li Yahong, manager of the bureau's project management center, said.
"To attack a strong point, to implement it in every place, to be accurate in the transmission of information, and to make every effort to win this tough battle." Yan Liang, deputy manager in charge of infrastructure production at the bureau, said.
According to the project plan, at each construction point, the management personnel at all levels of the bureau and the on-site construction personnel raced against the clock to grasp the construction progress, and the construction scene was full of hot construction. In the process of tackling tough projects, a feedback meeting on the progress of project implementation is held every day to find difficulties in response to feedback.
At the same time, the power distribution station, the production technology department and other relevant departments involved in the project construction of the business fine, strong ability of the relevant technical personnel to check whether the project has the conditions for operation before the commissioning, the township power supply station is responsible for doing a good job in the project to tackle the problem of obstruction coordination in the construction of the project, the project management center is responsible for solving the problem of "stuck neck" in the construction progress of the project construction, and strive to ensure that the continuation of the project "zero defect" put into operation.
Promote revitalization with quality and ensure the effectiveness of construction
In the critical period of decisive victory and continuous construction of projects, ensuring the transformation of the broad masses of the people from "using electricity" to "using electricity well", optimizing the structure of the grid of the Chengheng power grid, and improving the reliability of power supply are not only the goals and missions of our generation of electric power workers, but also carry forward the spiritual quality of the Qiandian Iron Army, which is particularly able to endure hardships and fight. Through the initiative of leading cadres to lead by example, party members take the initiative to play a pioneering and exemplary role, infrastructure, production, distribution centers and party branches of power supply stations should play the role of fighting fortresses, and the overall cadres and workers should fully develop the Kunliulong spirit of "bearing the overall situation in mind, facing difficulties, self-reliance and self-improvement, and bravely climbing the peak" to ensure that the project will be put into production on schedule from 2018 to 2021.
In order to end the goal as soon as possible, the Chengheng Power Supply Bureau takes safety, quality and progress as the control, strengthens the coordination of the project, accelerates the progress of the project construction, and goes all out to ensure the high-quality completion of the construction project. In terms of safety control, adhere to the "zero" goal of safety, comprehensively do a good job in the responsibility and accountability of safety and quality at the construction site, and carry out safety and quality inspections and inspections from time to time to ensure full coverage of safety control and control, so that the construction site is safe and controllable, controllable and under control. In terms of progress tracking, we should keep an eye on the overall goal of commissioning, issue military orders, and the overall planning of the construction progress of the system specific to the "day", and correct the progress deviation in a timely manner by means of "day" progress notification, poor promotion and "clear explanation", timely correction of schedule deviations, timely coordination and solution of difficulties and pain points in the promotion of the project, and speak with speed to ensure the efficient and orderly progress of the project. Quality elimination. Adhere to the "zero" defect of project production, led by the project management center, organize the production technology department, power distribution station, and power supply institute to go deep into the front line of the construction site to inspect the quality of the project one by one, and run the high quality and high requirements standards through the power grid construction process to ensure that the project is put into use on schedule and quality. (Cao Xu, Yang Jing)