Joint debugging and joint test! The maximum speed of the test train is 385 kilometers per hour!

October 18

After more than half a month of intense and orderly joint debugging and joint testing

New Nanning-Zhuhai high-speed railway

Nanning to Yulin section

(hereinafter referred to as the Nanyu section of the Nanzhu high-speed railway)

Start the speed test of the highest test speed level

That day

Nanyu section of the Nanzhu high-speed railway

High-speed comprehensive inspection train

The test target speed of 385 km/h was reached

This is set by the joint debugging and joint test of the line

Detect the top speed of the train

Nanyu section of the Nanzhu high-speed railway

Joint debugging and joint test! The maximum speed of the test train is 385 kilometers per hour!

The Nanyu section of the Nanzhu high-speed railway starts from Nanning East Station, the capital of Guangxi, to Yulin North Station in the east, with a total length of 193.31 kilometers and a design speed of 350 kilometers per hour.

After the completion and opening to traffic, it is of great significance to further promote the "two-bay linkage" between the Guangxi Beibu Gulf Economic Zone and the Guangdong-Hong Kong-Macao Greater Bay Area, and realize the coordinated development of the Pearl River-Xijiang Economic Belt.

Joint debugging and joint test! The maximum speed of the test train is 385 kilometers per hour!

The step-by-step speed test refers to arranging high-speed comprehensive testing trains to gradually increase the test speed on the line according to the requirements of the joint debugging and joint test test outline. In order to run the maximum test speed of 385 kilometers per hour, the railway locomotive department carefully selected excellent drivers, collected various data, and determined the safety mutual control points through precise calculations to ensure the safety of the test.

Joint debugging and joint test! The maximum speed of the test train is 385 kilometers per hour!

During the joint commissioning and joint test of the Nanyu section of the Nanzhu high-speed railway, China Railway Nanning Bureau Group Co., Ltd. strengthened the organization and leadership, clarified the division of responsibilities, and carried out various tasks in a solid manner according to the deployment arrangement of the China Railway Group, focusing on safety, focusing on test organization and on-site control, and successfully completing the test content of the test outline.

Joint debugging and joint test! The maximum speed of the test train is 385 kilometers per hour!

After the opening of the Nanyu section of the Nanzhu high-speed railway, the running time of the train between Nanning and Yulin is expected to be shortened from the current fastest 1 hour and 44 minutes to about 50 minutes, greatly shortening the time and space distance between the two places, so stay tuned!

Contributed by: Guangxi Reporter Station of People's Railway Newspaper Co., Ltd. (Financial Media Center of Nanning Bureau Group Company)