Fixed asset investment (referred to as "fixed investment") is one of the important indicators to measure the effectiveness of the development and construction of the area, and plays a pivotal role in promoting the economic development of the area. Under the care and guidance of district leaders and relevant departments, the headquarters actively connected with the airport high-speed rail company and the high-speed rail new city company to ensure that the project should be unified. In September, the fixed investment of the Qiantang high-speed rail sector hit a new monthly high, which strongly promoted the high-quality development of the economy.
The construction of the project is in full swing
Since the start of construction of the Hangzhou Airport High-speed Rail and High-speed Rail New City Project, all the construction personnel have worked hard and worked efficiently, key projects have continued to accelerate, and the construction site has been frequently reported.
Hangzhou Airport High-speed Railway
Recently, remarkable progress has been made at all key nodes of the main railway line. Among the three sections of the main line involving Qiantang, the main structure of the shield launch shaft of the Qiantang River Tunnel has been completed, and it is expected that the shield launch conditions will be met by the end of the year; The first continuous rigid structure of the north throat bridge of Qiantang Elevated Station was successfully poured; The pouring of the first pier of the Jingjiang Bridge was completed. The construction of the substructure of the bridge of the main railway line is being carried out.
Since the promotion conference of the Qiantang hub station in June, the construction of temporary facilities and engineering test piles have been completed, and the concrete mixing plant and steel processing plant have been accepted, and the construction of the waterproof curtain pile in the deep foundation pit area and the pile foundation in the main engineering area of the station building is being carried out.
In the high-speed rail new city unit, the two projects that have started are progressing smoothly. Among them, the foundation pit enclosure support system of the Feng Lou resettlement housing project has been completed, and the earthwork excavation has been completed to 40%; The overall progress of the Dongsheng Road project is normal, and the construction of the water-stabilized layer, flat side stone, and asphalt pavement test section has been completed.
The high-speed rail sector mainly involves the relocation of 10 high-grade power lines, of which 3 are within the scope of the high-speed rail new city (110kV1, 220kV2), and the 110kV Bailang line has been cutover, and the remaining two 220kV new tower foundations are under construction.
Fixed investment hit a new high
According to the actual progress of the project, the declaration of fixed asset investment has been completed for each project. According to the data, the Qiantang high-speed rail construction project completed a fixed asset investment of 470 million yuan in a single month in September, making a positive contribution to regional economic development.
Main railway line
The total investment of the Hangzhou Airport high-speed rail project is 38.3 billion yuan. In order to do a good job in investment work, the headquarters and Hangzhou Airport High-speed Rail Company have been in close contact with the company to successfully complete the inspection and valuation work in the second quarter, and the fixed asset investment in the Qiantang section in September was 153 million yuan.
Comprehensive supporting project of station building
In order to accelerate the investment of the project, with the strong attention of leaders at all levels and the full support of various functional departments, the headquarters and Qiantang High-speed Rail New City Company, Hangzhou Airport High-speed Rail Company, Hangzhou Railway Hub Headquarters, China Railway Construction and other units have worked together to complete the first inspection and valuation of the project in September, and the fixed investment of about 265 million yuan has been completed in a single month.
High-speed rail new city area development project
There are a total of 3 projects under development in the high-speed rail new city area (Feng Lou resettlement housing and supporting kindergartens, Dongsheng Road road engineering and high-grade power relocation), and by the end of September 2024, a fixed investment of 258 million yuan has been completed, of which 51.73 million yuan has been completed in September.
In the next step, the headquarters will pay close attention to a series of preliminary work such as feasibility study, site selection demonstration, and preliminary design of the projects planned to start construction within the year, and strive to start construction of each project as soon as possible and accelerate the investment volume.