On July 12, Wang Yong, head of Nanhai District, led a team to the Guangzhou-Foshan West Ring Project (Lishui Section) to carry out the 100-day demolition and remediation action of the key infrastructure construction projects in Nanhai District in 2024. Two buildings (structures) within the red line of the project were demolished on the spot, and a number of enterprises, shops and structures were remediated and investigated. Next, the Lishui Commando will continue to carry forward the spirit of "fast, accurate, and united", fully complete the task of requisition and demolition, and speed up the construction of the Guangzhou-Foshan West Ring Road.
Demolition site.
The Yongtange Mahogany Furniture Factory in Shitang Village was one of the places demolished that day. The construction area of the plant is more than 1,000 square meters, and the expropriation has been completed. The demolition of the building will greatly promote the progress of the expropriation of the area.
Wang Yong, head of Nanhai District, made a speech.
As Wang Yong announced the demolition of the on-site command, the iron arm of the hook machine was waved, the sprinkler sprayed water mist, and the old buildings (structures) of the Yongtan Pavilion Mahogany Furniture Factory fell down in the rumbling. On the same day, the demolition area exceeded 10,000 square meters, and the construction of the Lishui section of the Guangfo West Ring Project was accelerated.
Wang Yong put forward the requirements of the "Four Ones" and made a single heart: firm determination; Stepping on a foot of mud: the mass line; Twisted into a Rope: Collaborative Efficiency; Willing to cut one's body: the spirit of struggle. He also went to some factories, shops, and buildings (structures) to inspect them. In a waste recycling station, it can be seen that there are many private buildings built indiscriminately to store items, destroying land resources and affecting the surrounding environment. In response to this situation, law enforcement officers immediately carried out a centralized inventory of the waste recycling station.
Wang Yong and the relevant persons in charge of the district and town were at the site of the requisition and demolition.
At this year's two sessions in the South China Sea, the government work report clearly proposed to achieve a faster pace to achieve hard connectivity in the Guangzhou-Foshan metropolitan area. It is necessary to seize the opportunity of the construction of the Guangzhou metropolitan area, systematically plan and make precise efforts, focus on promoting the opening up of the bay area and the road network in the integration area, accelerate the pace of "entering the circle and entering the bay" in the South China Sea, and deeply participate in the construction of the Guangdong-Hong Kong-Macao Greater Bay Area.
Guangzhou-Foshan West Ring Road is an important part of the Guangzhou-Foshan Ring Road, the project starts from Foshan West Railway Station and ends at Guangzhou North Railway Station, with a new line length of about 47 kilometers, of which Foshan is about 30.5 kilometers long, with a total investment of about 22.6 billion yuan, and the Lishui section is about 7 kilometers long. Seven new stations were built on the whole line: Shishan East, Dalan, Guanyao South, Hegui, Tanbu, Huadu Port and Shenshan North. The project is a major project for Lishui to fully enter the era of rail transit, which will greatly shorten the time and space distance between the northern area of Lishui and the core area of Guangzhou, and is of great significance for optimizing the urban development pattern and improving the quality of life of residents.
Law enforcement officers inspect firefighting facilities on the spot.
Since the launch of the project in September 2022, Lishui Town has established the Guangfo West Ring Road (Lishui Section) Land Acquisition and Demolition Headquarters, recruiting more than 120 Lishui commandos, divided into 10 detachments and 40 teams, to carry out the expropriation and demolition work in groups.
In May this year, Lishui formulated the "Pearl River Delta Intercity Rail Transit Guangfo Ring Line Foshan West Station to Guangzhou North Railway Station Section Project (Lishui Section) Requisition and Demolition Work Plan", specially established the Guangzhou-Foshan West Ring (Lishui Section) Requisition and Demolition Leading Group, and on the 17th, the requisition and demolition remobilization, clear will continue to play the Lishui commando "fast, accurate, Qi" spirit, with the goal of 100% signing rate, and focus on promoting the remaining expropriation of the Guangfo West Ring (Lishui Section) project to symbolize the demolition.
Lishui traffic layout.
At the same time, the construction work of the fifth working area of Guangfo West Ring (Lishui Section) and Gui Station has been fully rolled out, and the Hegui Station Bridge and Hegui Bridge are under construction.
Lishui has set up a leading group for the 100-day special action to requisition, demolish and hand over land for key infrastructure construction projects in 2024. Next, Lishui will complete the land acquisition and demolition work of the Guangzhou-Foshan West Ring (Lishui Section) project with the goal of "completing the collective part of the contract work by the end of July and the state-owned part of the contract work by the end of August".
Text/Picture Nanhai financial media reporter Chen Zhijian
Video copywriting/shooting/editing Nanhai financial media reporter Yang Jinfei Tan Zhaoliang
Correspondent: Cindy Liao