Share today ▏ "Ten steps" for completion and acceptance! Are you on the right track?

author:Yicheng management
Share today ▏ "Ten steps" for completion and acceptance! Are you on the right track?

After the completion of the completion of the project, we have summarized the completion acceptance process, condensed into "ten steps", and shared it with engineering friends for reference, welcome to forward and share.

Self-inspection and evaluation of the construction unit

After the completion of the project, the construction unit shall conduct a quality inspection of the project, confirm that it meets the requirements of the design documents and the contract, fill in the "Project Acceptance Report", and sign it by the project manager and the person in charge of the construction unit.

The supervision unit submits the "Project Quality Assessment Report"

After receiving the "project acceptance report", the supervision unit should comprehensively review the acceptance data of the construction unit, sort out the supervision data, conduct quality assessment of the project, and submit the "project quality assessment report", which should be reviewed and signed by the director and the person in charge of the supervision unit.

The survey and design unit submits the "Quality Inspection Report"

The survey and design unit shall inspect the survey and design documents and the design change notice signed by the design unit during the construction process, and submit a written "quality inspection report", which shall be reviewed and signed by the person in charge of the project and the person in charge of the unit.

The construction (supervision) unit organizes the initial inspection

The construction unit organizes supervision, design, construction and other units to conduct preliminary inspection and acceptance of the project quality. All parties put forward rectification opinions on the existing problems, and the construction unit fills in the rectification report after the rectification is completed, and the supervision unit and the supervision team verify the rectification. After the initial inspection is qualified, the construction unit shall submit the "Project Completion Report" to the construction unit.

The construction unit shall form an acceptance group and determine the acceptance plan

After the construction unit receives the "project completion report", the relevant personnel of the organization design, construction, supervision and other units shall set up an acceptance group, and the members of the acceptance team shall have the corresponding qualifications, and the acceptance plan shall be prepared for the larger scale or more complex project.

The construction unit submits the engineering technical information

The construction unit will submit the complete engineering and technical data to the quality supervision department for inspection seven days in advance.

Completion acceptance

The construction unit presides over the completion acceptance meeting and organizes all parties to inspect the quality of the project. If there is a quality problem, put forward rectification suggestions.

The supervision department supervisors go to the site to supervise the organizational form, acceptance procedures, and implementation of acceptance standards for the completion and acceptance of the project.

The construction unit shall carry out rectification according to the acceptance opinions

The construction unit shall carry out rectification in accordance with the rectification opinions put forward by the acceptance parties and the "Notice of Rectification Order", and after the rectification is completed, write out the "Rectification Report", which shall be sent to the quality supervision station after being signed and sealed by the construction, supervision, design and construction units, and the supervisors shall participate in the review of the important rectification content.

The project is accepted

For unqualified projects, according to the "Unified Standards for Acceptance of Construction Quality of Construction Projects" and other acceptance specifications, after rectification, re-acceptance until qualified.

Acceptance filing

Within five days after passing the acceptance, the supervision agency will send the supervision report to the county housing and urban-rural development committee. The construction unit shall report to the County Housing and Urban-Rural Development Commission for the record in accordance with the relevant regulations.

Share today ▏ "Ten steps" for completion and acceptance! Are you on the right track?

1. The completion and acceptance of the project shall be carried out in accordance with the following procedures

1. After the completion of the project, the construction unit shall submit the project completion report to the construction unit and apply for the completion acceptance of the project. For the project to be supervised, the project completion report must be signed by the chief engineer. (Before the completion of the project, the construction unit shall notify the quality supervision department to carry out quality supervision and inspection of the project entity in place).

2. After receiving the completion report of the project, the construction unit shall organize experts from survey, design, construction, supervision and other units and other relevant parties to form an acceptance group for the project that meets the completion acceptance requirements and formulate an acceptance plan.

3. The construction unit shall, 7 working days before the completion and acceptance of the project, notify the engineering supervision agency responsible for supervising the project of the time, place and list of acceptance groups.

4. The construction unit organizes the completion and acceptance of the project.

(1) The construction, survey, design, construction and supervision units shall report on the performance of the project contract and the implementation of laws, regulations and mandatory standards for project construction in all aspects of project construction;

(2) Review the project archives provided by the construction, survey, design, construction and supervision units;

(3) Inspect the quality of the project entity;

(4) Make an overall evaluation of the construction of the project, the quality of equipment installation and the management of each link, form the project completion acceptance opinion, and sign the acceptance personnel.

When the construction, survey, design, construction, supervision and other parties involved in the completion and acceptance of the project cannot form a consensus, they should report to the local construction administrative department or supervision agency for coordination, and after reaching a consensus, reorganize the completion and acceptance of the project.

Second, the necessary conditions for the completion and acceptance of the project

1. The design and the contents stipulated in the contract have been completed;

2. The divisions (subdivisions) of the unit project are all accepted and accepted, and comply with laws, regulations, mandatory standards for engineering construction, design documents and contract requirements;

3. The engineering data meets the requirements;

4. The testing data of the relevant safety and function of the branch project included in the unit project are complete; The results of the spot check of the main functional items are in line with the provisions of the relevant professional quality acceptance specifications.

5. The visual quality of the unit project meets the requirements.

6. All special acceptance and acceptance of relevant professional systems have been passed.

The construction unit is responsible for applying to the relevant government administrative departments or authorized testing institutions for various professional and system acceptance:

1) Fire acceptance documents

2) Planning acceptance approval documents

3) Environmental protection acceptance approval documents

4) Elevator acceptance documents

5) Relevant acceptance documents of intelligent buildings

6) Pre-acceptance opinions on the completion file of the construction project

7) Indoor environmental test report of construction project

3. Record the completion and acceptance of the project

The construction unit shall, within 15 working days after the completion and acceptance of the project and the supervision and inspection of the project quality supervision agency comply with the regulations, go to the filing authority for the completion of the project acceptance for the record, and the construction unit shall provide the following documents for the completion of the project filing procedures:

1) Completion acceptance record form;

2) Project completion acceptance report;

3) Construction permits;

4) Review opinions on construction drawing design documents;

5) The project completion report submitted by the construction unit;

6) the project quality assessment report submitted by the supervision unit;

7) Quality inspection report submitted by survey and design units;

8) Approval documents or permission documents issued by planning, public security, fire protection, environmental protection and other departments;

9) The acceptance opinion of the project completion signed by the acceptance team personnel;

10) Project quality warranty signed by the construction unit;

11) Summary table of unit project quality acceptance.

12) Commercial housing shall also submit the "Residential Quality Assurance Certificate" and the "Residential Instruction Manual".

13) Other documents that must be provided according to laws, regulations and rules.