State Grid Hui'an County Power Supply Company: Double "Centipede Ladder" Live Operation to Achieve "Zero Perception" of Users

author:See Quanzhou

  Recently, in Xiaoqiao Town, Hui'an County, the State Grid Hui'an County Power Supply Company organized staff to carry out distribution line drone inspections, and found that the heating temperature of the switch switch lead on the 239th pole of the 10,000-volt Dongshan Line was high, and there was a risk of line failure caused by burnout at any time.

  During the on-site investigation of the elimination environment, the company found that the pole was located on the slope of the mountaintop, and the terrain was complex, and the existing environment could not support the traditional large-scale machinery operation method. In order to ensure the normal production and living electricity of surrounding users, the company finally decided to adopt two groups of centipede ladder live operation elimination scheme, and simultaneously carry out the switch automation transformation work to improve the success rate of the correct action of the FA of the line.

State Grid Hui'an County Power Supply Company: Double "Centipede Ladder" Live Operation to Achieve "Zero Perception" of Users
State Grid Hui'an County Power Supply Company: Double "Centipede Ladder" Live Operation to Achieve "Zero Perception" of Users

The double "centipede ladder" live operation mode was adopted to carry out the 10,000-volt Dongshan Line No. 239 pole switch switch heating shortage elimination and switch automation transformation (photo by Huang Zhenping)

  At 9 o'clock in the morning on the day of the operation, the live staff of the State Grid Hui'an County Power Supply Company carried out various preparations in an orderly manner at the site, cleaned up the working ground, assembled 2 "centipede ladders", laid ground anchors, tied cables, and fixed 16 groups of cables in four positions in the southeast and northwest to ensure the stability and reliability of the 2 groups of 10-meter-long "centipede ladders" during operation. Wearing golden insulated shawls, hard hats, and insulating gloves, they were fully armed and carried out high-altitude live work at the same time, completing the removal of the upper lead of the pole and the insulation shielding work. The shortage elimination staff followed closely to carry out the heat shortage elimination and switch automation transformation operations. The on-site operators cooperated tacitly, efficiently and orderly to complete the hidden danger elimination and switch upgrade work.

State Grid Hui'an County Power Supply Company: Double "Centipede Ladder" Live Operation to Achieve "Zero Perception" of Users

For the first time, the State Grid Hui'an County Power Supply Company used a crawler-type insulated bucket boom truck to carry out live lap operation on the Yuqun branch line of the 10,000-volt home wind line.

State Grid Hui'an County Power Supply Company: Double "Centipede Ladder" Live Operation to Achieve "Zero Perception" of Users

State Grid Hui'an County Power Supply Company carried out 10,000 volt mobile medium voltage power generation vehicles with live access to the grid to ensure that the power grid construction does not stop.

  The double "centipede ladder" live operation eliminated the shortage of 19 public transformers and 3 special transformers, a total of 3,069 users, and realized the "zero perception" of users' electricity consumption. In the next stage, State Grid Hui'an County Power Supply Company will continue to adhere to the concept of "no power outage is the best service", adhere to the principle of "non-stop service", continuously optimize the operation mode, refresh the new technology and new skills of live operation, improve the lean operation and maintenance level of equipment, and strive to achieve both power supply reliability and high-quality service!

Source | State Grid Hui'an County Power Supply Company