laitimes

The "progress bar" of the construction of the CRRC Times energy storage base project is fully loaded

author:The window of Xuzhou

As the first project to start construction in Yibin Energy Storage Industrial Park, the CRRC Times Energy Storage Base Project, since the start of construction in mid-February this year, has been seizing the construction period, wall chart operations, and is expected to be commissioned and produced in July 2024.

The "progress bar" of the construction of the CRRC Times energy storage base project is fully loaded

On May 14, the reporter saw at the construction site of CRRC Times Energy Storage Base that the basic framework of the project had been presented. On the spacious indoor construction site, workers can be seen busy everywhere.

The "progress bar" of the construction of the CRRC Times energy storage base project is fully loaded

"We are now carrying out the installation of masonry and fire protection on the first floor of the No. 1 plant, the reinforcement binding and formwork installation on the second floor, and it is expected that on May 20, the structure of the No. 1 plant will be capped. Plant 2 is currently under construction of roofing, wall panels and corundum flooring, and will enter the site in mid-June for equipment installation. Gao Qiankun, director of the construction management department of Yibin Metalworking Construction Investment Group Co., Ltd., is well aware of the construction progress of the project.

The "progress bar" of the construction of the CRRC Times energy storage base project is fully loaded

The CRRC Times Energy Storage Base project covers an area of about 124.1 acres and will be constructed in two phases. The first phase of the project covers an area of 91.7 acres, with a total investment of 150 million yuan and a total construction area of about 42,420 square meters.

The "progress bar" of the construction of the CRRC Times energy storage base project is fully loaded

In order to speed up the construction of the project, the project owner, the construction unit and the service unit work closely together to seize the current "golden period" of construction in fine weather, continuously refresh the "progress bar" of the project, and strive to be delivered as soon as possible.

The "progress bar" of the construction of the CRRC Times energy storage base project is fully loaded

"At present, there are more than 200 workers on our site, and more than 30 loaders, excavators, cranes, rollers and other equipment. In the next step, we will optimize the use of labor and equipment according to the schedule of the construction period, reverse the construction period, strive for early completion, and smoothly deliver the equipment to CRRC for equipment installation. Gao Qiankun said.

The "progress bar" of the construction of the CRRC Times energy storage base project is fully loaded

It is reported that the CRRC Times Energy Storage Base project is mainly committed to the development of energy storage system and core components industry, and will give full play to CRRC's technical advantages, talent advantages, and industrial chain advantages, continuously deepen the depth and breadth of cooperation with Sichuan and Yibin, and integrate into Yibin's new journey of building a 100 billion zero-carbon energy storage industrial base.