It's already taking shape! The progress of the new terminal of Shadi Airport is directly hit! It is expected to be put into use before the summer transportation

author:House cube

What is the progress of the new terminal at Shadi Airport, which started construction in February?

A few days ago, Leju editors went to the location of Shadi Airport and found that the overall construction progress of the new terminal of Foshan Shadi Airport has been completed for most of the time, and the entire terminal has gradually taken shape.

As seen at the scene, the new terminal as a whole presents a white box shape, and the overall frame has been basically formed.

It's already taking shape! The progress of the new terminal of Shadi Airport is directly hit! It is expected to be put into use before the summer transportation
It's already taking shape! The progress of the new terminal of Shadi Airport is directly hit! It is expected to be put into use before the summer transportation

It is reported that the new terminal project of Foshan Shadi Airport is funded and constructed by China United Airlines, with a total investment of more than 100 million yuan, covering an area of 8,060 square meters and a total construction area of 11,395 square meters.

The new terminal adopts an emerging modular construction method, which can be disassembled, that is, it is easy to build, and it is easy to disassemble and assemble. After the terminal is in use, it can also be relocated, such as to another new airport or cargo terminal, which realizes the reproducibility of use and helps to reduce construction costs.

It's already taking shape! The progress of the new terminal of Shadi Airport is directly hit! It is expected to be put into use before the summer transportation

According to the latest official information, the new terminal is expected to be completed and officially put into use before the summer (July-August).