How to construct the embedded line pipe of the secondary structure? Norms do this!

author:Architectural engineering information

Line pipe embedding is an important concealed project of mechanical and electrical installation, and the construction quality is the guarantee of the quality of electrical wiring and wall finishing projects in the later stage. In the implementation of the project, Bengbu Wanshun Construction and Installation Engineering Co., Ltd. strictly implements the standardized model construction technology according to the relevant specifications of building electrical and decoration engineering, and has achieved good quality results.

How to construct the embedded line pipe of the secondary structure? Norms do this!

Secondary structure line pipe embedded construction technology

The secondary structure line pipe embedded construction, should be built on the top brick and the wall to reach the strength, before the wall plastering, horizontal slotting is strictly prohibited, such as horizontal slotting, horizontal slotting length shall not be greater than 300mm. The key points of construction quality control in each process are as follows:

1. Positioning and pay-off

Based on the one-meter line of the building, the elevation of the wire box is positioned in strict accordance with the size of the drawing, and the positioning line is drawn around the box along the line;

How to construct the embedded line pipe of the secondary structure? Norms do this!

Line box drawing line positioning

Based on the position of the wire box, the positioning line of the trunking should be popped vertically, and the width should be satisfied: the distance between the line pipe and the distance between the line pipe and the wall are ≥ 10mm, and the width of the slotting control line = the outer diameter of the line pipe + the distance between the line pipe + the distance between the line pipe and the wall.

How to construct the embedded line pipe of the secondary structure? Norms do this!

Trunking elastic line positioning

Second, slotting and grooving

The line pipe slotting uses a special slotting machine, which is accurately slotted along the control line, the notch is straight and the depth is consistent, and the slotting depth = the outer diameter of the line pipe + at least 15mm protective layer;

How to construct the embedded line pipe of the secondary structure? Norms do this!

The grooving machine makes precise grooving

Manual groove removal should be adopted, and electric hammer groove removal is strictly prohibited to avoid damaging the secondary structure;

How to construct the embedded line pipe of the secondary structure? Norms do this!

Manual removal

The depth of the trunking should meet the requirements of 15mm protective layer between the conduit and the wall;

How to construct the embedded line pipe of the secondary structure? Norms do this!

The thickness of the protective layer ≥ 15mm

Clean up the floating ash and loose parts in the trunking, and sprinkle water on the trunking to fully moisten the wall.

How to construct the embedded line pipe of the secondary structure? Norms do this!

Clean the trunking and sprinkle with water to moisten

3. Pre-embedded construction

Before the line pipe is embedded, a layer of bottom ash is smeared on the line duct to pave the bottom;

How to construct the embedded line pipe of the secondary structure? Norms do this!

Bottom plastering plastering of the trunking and laying the bottom

When the wire box is fixed, the bottom is close to the elevation control line, and the height of the protruding wall is based on the thickness of the plastering surface ash cake;

How to construct the embedded line pipe of the secondary structure? Norms do this!

The wire box is fixed

Mortar caulking repair is constructed in two times to ensure the compactness of the filling;

How to construct the embedded line pipe of the secondary structure? Norms do this!

Wire box groove mortar caulking

When the conduit is fixed, fix the conduit in the conduit with a clamping nail, and the spacing between the fixing points is not more than 1m;

How to construct the embedded line pipe of the secondary structure? Norms do this!

Conduit fixation

The spacing between the control line pipe and the distance between the line pipe and the wall shall not be less than 10mm;

How to construct the embedded line pipe of the secondary structure? Norms do this!

Control of the distance between the line pipe and the wall

Mortar caulking and filling grooves should be constructed in layers to ensure the compactness of the filling;

How to construct the embedded line pipe of the secondary structure? Norms do this!

Groove mortar caulking

Before the initial setting of the plastering layer mortar, the glass fiber mesh is pressed into the line groove, and the lap width on each side is not less than 100mm, so as to ensure that there is no risk of hollow drum cracking in the later stage of the line groove position;

How to construct the embedded line pipe of the secondary structure? Norms do this!

Press into the fiberglass mesh

After pressing into the surface layer, the surface is smoothed and compacted, and after the final setting, water is sprinkled and moistened in time to avoid hollowing and cracking at the position of the trunking.

How to construct the embedded line pipe of the secondary structure? Norms do this!

Sprinkling curing

Fourth, finished product protection

After the construction of wire pipe embedding is completed, the finished product of the wire box or electrical box shall be protected in time to prevent construction pollution between subsequent processes such as wall spraying.

How to construct the embedded line pipe of the secondary structure? Norms do this!

Temporary closure of the finished product protection