【Key Project】The construction progress is "new" again, and the first ring project (Mingshan Section) has entered the final sprint stage

author:Mingshan District Rong Media Center

On May 13, the construction of the new project from Tongguan Road to Ya'an Vocational Institute of the First Ring Project (Mingshan Section) in the center of Ya'an City has made significant progress, and the key control project - the steel box girder jacking construction of the bridge on the Chengya section of the G5 Beijing-Kunming Expressway was carried out as scheduled, marking that the project has entered the final sprint stage and has laid a solid foundation for the realization of the goal of opening the new project from Tongguan Road to Ya Vocational Institute on schedule.

【Key Project】The construction progress is "new" again, and the first ring project (Mingshan Section) has entered the final sprint stage

The reporter saw at the scene, the bridge steel box girder is located on the side of the highway, there are dozens of fully automatic CNC walking jacks at the bottom, the use of hydraulic transmission device to lift the steel box girder jacking up, and then translate forward to push a stroke, and then the main bridge as a whole is lowered on the temporary pier shelving pad beam, and then the oil cylinder is reduced to the end, so that the construction is carried out back and forth, and the whole project is carried out in an orderly manner.

【Key Project】The construction progress is "new" again, and the first ring project (Mingshan Section) has entered the final sprint stage

"We adopted the jacking construction technology this time because this process can not only solve the construction problem of long-span bridge hoisting on highway bridges, but also reduce the construction cost and safety risk caused by a large number of high-altitude operations." Xue Maosing, chief engineer of the project, introduced to reporters.

【Key Project】The construction progress is "new" again, and the first ring project (Mingshan Section) has entered the final sprint stage

In the specific construction process of the bridge on the G5 Beijing-Kunming Expressway Chengya section, it faces "three difficulties": first, the construction of the upper span expressway, which is difficult to organize and coordinate; Second, it is the first time to use the jacking construction process, and the technical standards are difficult to control; Third, the operating environment is complex and the safety guarantee is difficult. In order to overcome the problems and promote the safe and smooth progress of the project, Mingshan District coordinated with various parties and carefully organized the detour plan and emergency plan to ensure the smooth implementation of the Chengya Expressway control bypass. And assist the construction unit to strengthen the rehearsal and deduction, and repeatedly polish the details of the jacking construction to ensure the success of the jacking construction. At the same time, the safety guarantee was strengthened, and the relevant departments were stationed to monitor the implementation of safety measures to comprehensively resolve the problems of construction difficulties and high risks.

【Key Project】The construction progress is "new" again, and the first ring project (Mingshan Section) has entered the final sprint stage

It is reported that the new project from Tongguan Road to Ya'an Vocational Institute in the first ring project (Mingshan Section) in the center of Ya'an is 2.877 kilometers long, adopts the technical standard of two-way six-lane secondary highway (and municipal road function), with a total investment of about 476 million yuan, and will start construction in February 2023, with a total of 91% of the total project completed and an investment of about 270 million yuan, and the project is expected to be fully completed by the end of June 2024. After the completion of the project, it will form a ring line around Guanghua Mountain with Yucheng Avenue, Yongxing Avenue, Yingchun Road, Huangcha Avenue and Yuming Expressway, becoming a transportation artery supporting the rapid development of the city and promoting the high-quality development of the Sichuan-Tibet Economic Cooperation Pilot Zone and the Yumingjing Core Economic Circle.

【Key Project】The construction progress is "new" again, and the first ring project (Mingshan Section) has entered the final sprint stage
【Key Project】The construction progress is "new" again, and the first ring project (Mingshan Section) has entered the final sprint stage

Scan the code to download the tea source Mingshan APP Reporter: Li Ke Yang Ke Editor: Han Tao Editor: Huang Hao Review: Li Xiaoyang