Fenshi Expressway: Stick to the post and pass the "May Day" to sound the construction charge

author:Yellow River News Network Luliang Channel

Fenshi Expressway is a component of the province's expressway network "four vertical, fifteen horizontal and thirty-three", and is a key project to achieve the goal of "county-to-county expressway" during the "14th Five-Year Plan" period in our province. During the "May Day" period, the construction unit seized the golden period of construction, riveted enough energy to pay close attention to the construction, anchored the goal of opening to traffic this year, and sounded the charge of project construction.

Fenshi Expressway: Stick to the post and pass the "May Day" to sound the construction charge

Lvliangtai reporter Zhang Yiming: I am now at the construction site of the first branch of the Fenshi Expressway. Behind me, the builders seized the favorable weather to carry out asphalt concrete construction, which is the first section of oil paving operation carried out by Fenshi Expressway this year, marking the whole line of Fenshi Expressway into the asphalt surface course construction stage.

Fenshi Expressway: Stick to the post and pass the "May Day" to sound the construction charge

Asphalt surface course construction is the last critical project before the high-speed construction is completed. During the "May Day" period, the builders of Fenshi Expressway seized the favorable node of the temperature rise, started at the same time on a number of working faces, and carried out pavement operations in an all-round way, at present, the main line of the water-stabilized layer has completed 39% of the design amount, and the asphalt surface course has been completed 12%, and it is planned to complete the construction of the water-stabilized layer at the end of July, and the whole line will complete the oil-laying operation at the end of September.

Fenshi Expressway: Stick to the post and pass the "May Day" to sound the construction charge

Zhao Junlong, deputy project manager of Fenshi Expressway Pavement Division 1: "May Day" holiday, we have more than 60 machinery, more than 300 workers are on duty, in the whole bid section of three working faces to carry out operations, every day can lay asphalt surface layer 1 km, water stabilized layer 1.5 km, after the completion of the installation of corrugated guardrails, curb stones and other ancillary projects, to further accelerate the progress of the project.

Fenshi Expressway: Stick to the post and pass the "May Day" to sound the construction charge

While the road work is progressing in an orderly manner, the tunnel construction is also being carried out simultaneously. At present, 4 of the 5 tunnels of Fenshi Expressway have been penetrated, and the longest Dongshan Tunnel of the whole line has been broken through on the left, and the builders have 24-hour uninterrupted cycle construction to ensure that the project is completed on time.

Fenshi Expressway: Stick to the post and pass the "May Day" to sound the construction charge

Ji Ming, Chief Engineer of the Fifth Division Project of Fenshi Expressway Subgrade: 14,925 meters have been completed so far, 96% of the total length has been completed. Among them, the left hole has a total length of 7730 meters, the right hole has a total length of 7800 meters and the remaining 605 meters, at present, the right hole has 3 working faces, 18 meters can be excavated per day, and it is planned to be fully penetrated before the end of June.

Fenshi Expressway: Stick to the post and pass the "May Day" to sound the construction charge

At present, 52 of the 53 bridges on the whole line have been connected, and the projects of housing construction, greening, traffic safety, and mechanical and electrical are progressing in an orderly manner.

Fenshi Expressway: Stick to the post and pass the "May Day" to sound the construction charge

Li Linlin, deputy general manager of Shanxi Traffic Control Fenshi Company: Up to now, 76% of the total estimated investment of Fenshi Expressway has been completed, the foundation of the whole line has been basically completed, the overall tunneling of 96%, the pavement engineering has been fully opened, and the ancillary projects have been promoted synchronously, anchoring the goal of opening to traffic this year, more than 3,000 management and construction personnel of the whole line stick to the front line, work together to ensure that the construction task is completed with high quality and high standards, and hand over a satisfactory answer to the provincial party committee and the provincial government and the people of the province. Reporter: Li Ziye, Zhao Weiwei, Zhang Yiming

Source: Lvliang TV