Code for Construction and Quality Acceptance of Urban Bridge Engineering, CJJ2-2008
Technical Regulations for Structural Reinforcement of Urban Bridges CJJ/T239-2016
Technical Regulations for Waterproofing Engineering of Urban Bridge Decks, CJJ139-2010
Technical Standard for Urban Bridge Maintenance CJJ99-2017
《道桥用改性沥青防水卷材》JC/T974—2005
《道桥用防水涂料》JC/T975—2005
"Technical Specification for Preloading of Steel Pipe Full Hall Bracket" JGJ/T194-2009
"Construction Quality Acceptance Standards for Steel Structure Engineering" GB50205-2020
"Steel Structure Design Standards" GB50017-2017
General Code for Steel Structures GB55006-2021
"Steel Welding and Acceptance Regulations" JGJ18-2012
Steel for Reinforced Concrete Part 1: Hot-rolled Round Steel Bars GB/T1499.1-2017
Steel for Reinforced Concrete Part 2: Hot-rolled Ribbed Steel Bars GB/T1499.2-2018
"Waste Heat Treatment of Steel Reinforcement for Reinforced Concrete" GB13014-2013
"Technical Regulations for Mechanical Connection of Steel Reinforcement" JGJ107-2016
《钢筋机械连接用套筒》JG/T163—2013
Code for Construction and Acceptance of Water Supply and Drainage Pipeline Engineering, GB50268-2008
Code for Construction and Acceptance of Water Supply and Drainage Structures GB50141-2008
"Sliding Template Engineering Technical Standard" GB/T50113-2019
《环氧树脂涂层钢筋》JG/T502—2016
"Concrete Strength Inspection and Evaluation Standard" GB/T50107-2010
"Safety Technical Code for Bowl Buckle Steel Pipe Scaffolding for Building Construction" JGJ166-2016
"Safety Technical Standard for Gantry Steel Pipe Scaffolding for Building Construction" JGJ/T128-2019
"Safety Technical Code for Fastener-type Steel Pipe Scaffolding for Building Construction" JGJ130-2011
"Safety Technical Standard for Socket Disc Buckle Steel Pipe Scaffolding for Building Construction" JGJ/T231-2021
Technical Code for Cold-Formed Thin-walled Steel Structures GB50018-2002
《冷轧带肋钢筋》GB/T13788—2017
"Design Code for Ordinary Concrete Mix Ratio" JGJ55-2011.
《预拌混凝土》GB/T14902—2012
"Unbonded Prestressed Steel Strand", JG/T161-2016
《预应力混凝土用钢丝》GB/T5223—2014
"Steel strands for prestressed concrete" GB/T5224-2014
"Metal bellows for prestressed concrete" JG/T225-2020
"Plastic corrugated pipes for prestressed concrete bridges" JT/T529-2016
"Anchors, fixtures and connectors for prestressed tendons" GB/T14370-2015
Technical specification for the application of anchors, fixtures and connectors for prestressed tendons, JGJ85-2010
"Technical Specification for Composite Steel Formwork" GB/T50214-2013
Yesterday 速记口诀4/25
1. Box culvert jacking starts
The command idling tightens the top test, and the back (backup) part of the perimeter inspection is not started
2. Box culvert jacking excavation
The man-machine continuous side is excellent, and the digging view cooperates with the prohibition of robbery
3. Box culvert jacking operation
Adjust and replace the back (backup) view
4. Box culvert jacking monitoring and inspection
The starting time of the measurement and recording
Three days ago, shorthand mantra 4/23
1. Cable-stayed bridge composition
Cable beam towers
2. The construction method of the tower
The knot body material is prepared, and the naked climb beam is hung
3. Technical requirements and precautions for tower construction
Cross-contamination pours the prop up, depending on the impact of the two pumps
4. Safety measures for tower construction
The tower crane is limited to torsional wind, and the calculation and inspection affect the accident prevention
5. Construction method of main girder of cable-stayed bridge
Push-turn suspension
6. Construction of concrete main beam
No. 0 non-consolidated, wind resistance performance, large span stitching
7. Construction of steel girder of cable-stayed bridge
The qualification is damaged and corroded, and the finished product is coated with the control material
8. Monitoring objects for cable-stayed bridge construction
The tension beam tower is moved
9. The purpose of monitoring the construction of cable-stayed bridges
The feedback determines the pull beam movement
10. The main content of cable-stayed bridge construction monitoring
The shape and range axis deviates from the tower translation, and the cable tower should change the temperature field
Seven days agoShorthand mantra 4/19
1. Cast-in-situ prestressed concrete continuous beam by bracket method
The foundation is arranged, the landing frame is dismantled, the pre-arch is eliminated, and the sinking is avoided
2. Pouring a prestressed concrete continuous beam on the moving formwork
Long group seams, poor built-in
3. Design and assembly of hanging baskets
Quality-ratio variable tilt anchor limit inspection
4. Pouring paragraph
Top 0 overhang
5. Suspension pouring sequence
0 side neutralization
6. Check the content of the beam section before pouring concrete
The backboard rib tube is buried, and the machine is mixed with the seam
7. The tensile sequence of the longitudinal prestressed tendons of the roof and web of the prestressed concrete continuous beam
Pull symmetrically up and down, left and right
8. Prestressed concrete continuous beam closure sequence
Edge times
9. Closing regulations for continuous beams (T structures).
Duan Changguan is even loose, and the warm mix is pre-pressurized
10. System conversion regulations for continuous beams (T structures).
Tension and grouting are about to be released
11. Provisions for the adjustment of the bearing reaction force of continuous beams (T structure).
High dominant
12. Elevation control of cantilever pouring method
The temperature has been poured pre-deformed
Two weeks agoShorthand mantra 4/12
1. Prestressed concrete raw materials
Priority should not be obtained, gravel anti-chlorine rust
2. Prestressed concrete pouring
Strengthen vibration and avoid collisions
3. Basic provisions of prestress tension
The force core is poor, and the anchor is initially recorded
4. Pre-tensioning prestressed construction
The center of the seat beam force, tensioning and releasing the broken pipe reinforcement
5. Prestressed tendon pipeline installation
Casing positioning ribs, welded through the hole
6. Installation requirements for prestressed tendons
Detection of moisture (salt) shall not be installed
7. Tensile requirements for prestressed tendons
Forced demolition and testing of Zhang Chao
8. Anchoring
After stabilization, the anchor seals the cutting head
9. Hole grouting
Check the secret in time to assess the temperature, and the mud sealing anchor is lifted to move strong
Five weeks ago, shorthand mantra 3/23a
1. Classification method of urban roads
Ground as a quality ring
2. Classification and basis of urban roads
Ground delivery service, set up road width
3. Classification method of urban road pavement
Structural mechanics, draining and rigidity
4. Pavement damage factors of urban roads
The resistance of small bends becomes large and soft, and the large bends become small and rigid
5、31502
The service life of the pavement structure design
6. Subgrade surface layer, subgrade pad subsurface surface
Composition of urban road structure
7. Tighten and stabilize the gradual (reduced) layer and appropriate seams
Principles of asphalt pavement road structure composition
8. The fine sand is not padded
Subbase setting
9. The medium tide is too wet and frozen water and soil
Bedding settings
10. Cold 5 times hot, waterproof and anti-slip abrasion modification
Uses of various asphalt mixtures