Liang Xin's assistant| Rainwater frequently floods the elevator! The business of the merchants is affected, and the drainage project is being repaired......

author:Eye-catching video

Loading...

"Yesterday (April 6) the elevator was flooded, and now there is no business. When it doesn't rain, sewage is also a problem, and the sewage can't be discharged. "Light rain has the problem of not being able to drain water, and if it rains heavily, the water has tried to flood the store. "The main body of this commercial building on Guangyun Road in Nanhai District is a hotel, and the tenants on the first floor are running a snack bar, and the merchants all say that they are troubled by sewer problems.

Liang Xin's assistant| Rainwater frequently floods the elevator! The business of the merchants is affected, and the drainage project is being repaired......

Rainwater floods the backyard of the snack bar. Photo courtesy of the interviewee

On the afternoon of April 7, the District Smart City Operation Center, together with the District Civil Affairs Bureau, the District Housing and Urban-Rural Construction and Water Conservancy Bureau, Shishan Town and Dali Town, held a work coordination meeting to clarify the responsibilities of all parties and decided to re-lay the pipe network by the District Housing and Urban-Rural Development Bureau (District Water Investment Company), and during the construction period, the blocked sewage wells were temporarily connected to Shishan to solve the urgent needs of the citizens.

After half a month, recently, Guangdong ushered in heavy precipitation, the reporter visited the merchants again and noticed that the two rows of sandbags placed in front of the door at the beginning of the month are now piled up in a row, and the height is more than the ankle of an adult. According to the hotel, it rained two nights ago (April 20), and because the water level was too high, the two rows of sandbags were moved together, but the water in front of the back door had soaked to the calf, and the sandbags did not play a role.

Liang Xin's assistant| Rainwater frequently floods the elevator! The business of the merchants is affected, and the drainage project is being repaired......

The owner of the snack bar on the first floor, a tenant, said that there was still a drainage problem due to the rainfall, and the water was about 10 centimeters before it reached the storefront.

Liang Xin's assistant| Rainwater frequently floods the elevator! The business of the merchants is affected, and the drainage project is being repaired......

What is the process of repairing the drainage pipes? The reporter learned from the construction personnel that before the heavy rain, the workers had dug the tunnel where the pipeline was buried, but due to the large amount of rain and the low terrain caused by the accumulation of rainwater, the rain hit the sediment and buried the tunnel, and the construction is currently continuing.

Liang Xin's assistant| Rainwater frequently floods the elevator! The business of the merchants is affected, and the drainage project is being repaired......

According to reports, when it is not raining, five or six workers will work at the same time, and it will take about ten days to repair the pipeline. The rain increases the difficulty of construction, and the construction period needs to be relatively extended.

At present, the merchant said that the problem of sewer odor has been alleviated, but the drainage problem in rainy days still affects the operation, and hopes that the drainage pipe construction can be completed as soon as possible.

Deputy Liang Xin will continue to pay attention to the course of the incident.

Text/Nanhai Financial Media Reporter Li Ziying

Video/Nanhai Financial Media Reporter Li Ziying, Lu Yinger, Fan Shijie